PROJECT INFORMATION

Project Title A Proposed Two Storey Residential House-Two Bedroom Villa


Lot Unit B2-L7
Reporting Period January 1-5, 2024
Report Date January 6, 2024
Project Contractor
Compañero, Gilbert S.
Prepared By
Montejo, Elizar Q.

SUMMARY

The current project involves the construction of a two-storey


residential villa. Key features of the villa include: two bedrooms (one
master bedroom and one extra bedroom); maid's room; full bathroom;
powder room; open layout of the kitchen, dining, & living room, with a
viewing deck and a one car garage.

The villa is an ongoing project, and according to the current


status observed by the OJT interns during their first week of
internship, significant progress has been made. The basic foundations
are already in place, indicating a solid start to the construction. The
plastering work, which is crucial for the finishing of the walls, is still in
progress. Structural elements such as beams and columns, along with
the trusses and purlins, have been successfully installed, providing the
necessary support for the building. However, the stairs have not yet
been installed, which is a critical component for accessing different
levels of the villa. Additionally, the roof in the garage has not been
started, leaving that area exposed. Interior features such as doors,
windows, and flooring are also pending installation, which are
essential for the completion of the living spaces. The electrical and
plumbing layouts are currently ongoing, ensuring that the villa will
have all the necessary utilities once completed.

In addition to the structural progress, some exterior features


have also been addressed. The canopy, which provides shade and
protection from the elements, has already been completed. This adds
both functionality and aesthetic appeal to the villa. The setbacks,
which are the distances from the property boundaries to the building,
are within the required limits, ensuring compliance with zoning
regulations. The foundation works are in good condition, indicating a
stable base for the entire structure. These completed tasks are critical
for the overall integrity and functionality of the villa. As the project
continues, the focus will likely shift to the completion of the interior
features and finishing touches, bringing the villa closer to its final form.
PROGRESS STATUS
Tasks % Completed Notes
•Removal of board works for the foundation
are completed.
Checking for foundation works 100
•Setbacks are aligned as-planned.
•Nylons for the alignment are removed.
•No work done for backfill and slab-on-grade
Earthworks 0
concrete pouring.
•Beams and columns for the unit has been
built already before we even start the
internship.
•Beams and columns are aligned with its
concrete walls and is still finishing its
plastering.
•Garage and deck roof frame and girdle has
been installed.
Structural Members
•Installation for roof and eaves frame is
finished. However, the spacing of JEA span is
different. As-planned, it needs a single JEA
span in every spacing (stacking), but in actual,
it uses two JEA span in each spacing
(running).
•Canopies are already built and is being
supported with shores (shoring).
•Water supply layout has already been
installed in place.
•Pipe material usedhas been checked.
Plumbing Rough In 60 •Installation of piping layout is already on-
going and location for water closet, lavatory,
& shower are as-planned at masters bedroom
(2nd floor) and for powder room.
•Installation of outlet and switch layout is
not yet covered and completed.
•Location of panel board is as planned, but
Electrical Rough In 45
installation of panel board is still pending.
•Heights for panel board, switches, and
outlets are yet to be checked.
•Wall layout, location, and alignment is
already completed and is aligned to plan
•There are still holes in the wall that needs to
be patched up as plumbing and electrical
Wall Works 63 roughing are still on-going.
•Wall finishes are not yet completed both
from outside and inside the unit.
•All doorways are yet to be finished.
•Window ways are already in shape.
Ceiling Works -
Mechanical Installations -
Glass Works -
Tile Works -
Finishing Works -
Furnishing Works -
Post Construction Phase -
DOCUMENTATION

- On the first day, we embarked on


an all-around tour of the Aduna
Villa with Architect Cy and Engineer
Zeus. As we visited various units
within the villa, Architect Cy asked
detailed questions about the names
and specifications of different
materials and architectural
elements used throughout the
property. Our team was assigned
two specific units to monitor and
evaluate for their construction
progress, ensuring that each stage
met the required standards and
timelines.

- On the second day, Architect Cy


gave us the blueprints of the units
to verify if the construction aligned
with the planned designs. We
began our day by visiting our
assigned units, ensuring they were
progressing according to the
specifications. Additionally, we
visited a unit in the initial stages of
construction, where we observed
the footing process. We also
witnessed the creation of beams
and columns, including the
formation of stirrups and the
precise spacing required for
structural integrity. .
DOCUMENTATION

- On the third day, we did not check


our assigned units because we
visited Elizabeth Home, where our
classmates were assigned. The villa
there was in the early stages of
construction, and we witnessed the
creation of the foundation. We
interacted with the workers, asking
questions about the processes they
were undertaking and the specific
tasks they were performing. This
visit allowed us to gain insights into
the foundational aspects of
construction and learn directly from
the hands-on experiences of the
workers on site.

- On the fourth day, as we visited


our unit, we noticed that plastering
had already begun on the front side
of the house. Upon climbing to the
second floor, we observed that the
finishing work inside was also
starting. Additionally, shoring was
installed on this day, which we had
not seen on the first to third days.
This installation is crucial as it
prevents the structure from
sagging, ensuring the integrity and
stability of the building as
construction progresses.
DOCUMENTATION

- On the fifth day, we witnessed the


continuation of plastering on the
front side of the villa, with
plastering also beginning on the
back side. However, we noticed
that the cracked beam we had
previously seen was still not fixed.
Additionally, the column exhibiting
honeycomb issues remained
untouched, indicating that these
structural concerns had yet to be
addressed.
PROGRESS STATUS
Tasks % Completed Notes
● Nylon strings were already
removed before we started
the internship
● Formworks are already
Foundation works 100 removed (I assume that the
concrete has sufficiently
cured)
● Allowances for setbacks
were followed

Earthworks

45
35

● No ceiling works yet aside


Ceiling Works
aside from the frame
Mechanical Installations -
Glass Works -
Tile Works -
Finishing Works -
Furnishing Works -
Post Construction Phase -
PROJECT INFORMATION
Project Title A Proposed One Storey Residential House - One Bedroom Villa
Lot Unit B5-L7
Reporting Period July 1-5, 2024
Report Date July 6, 2024
Project Contractor
Butal, Via O.
Prepared By
Somalinog, Honeyline M.

SUMMARY

The current project involves the construction of a one-storey


residential villa, designed as a single-detached house. Key features of
the villa include: one master bedroom with a loft bed; full bathroom;
powder room; open layout of the kitchen, dining, & living room, with a
viewing deck and a one car garage.

The villa is an on-going project and as per current status


witnessed by the ojt interns in their first week of internship, the basic
foundations were already in place. To elaborate, the garage has two
columns built in place while the deck has two pre-fabricated columns
standing upright with an unpatched column holes. The main part of the
house has already been installed with conrete hollow blocks in all
walls, the columns and beams has been seemlessly integrated within
walls. Although some parts still require plastering, door jambs, backfill
and slab-on-grade are still pending, the outlet & switch locations,
plumbing layout, and circuit pipe layout were completed. Septic tank
and grease trap receptacle holes are yet to be created. In addition, no
fixtures, lights, and panel board are installed. The canopy are already
built and only the roof frame was already installed in place, except for
the garage roof frame. As for the rest of the exterior components, the
deck, concrete step boxes, and catch basin canals are still absent.
Overall, the status of the project has a long way to go, and is expected
to finish by the second half of this year, barring any unforeseen
setbacks during construction.
PROGRESS STATUS
Tasks % Completed Notes
 Nylons are already
removed before we started
the internship
Checking for foundation works 100  Removal of batten boards
are completed
 Allowances for setback are
aligned with the plan

 Backfills and holes for


septic tank & grease trap
receptacle are yet to be
0 started
 No work done or
Earthworks preparation for slab-on-
grade concrete pouring
 Columns and beams for the
house are already built in
place when we started our
internship
 Columns and beams for the
main body is integrated
seamlessly on concrete
walls, we are unable to
check the placements
because plastering has
already been done
 No garage roof frame and
Structural Members 84 girder
 400x190 mm and 400x180
mm Garage column dims,
unfinished
 No deck works being
conducted
 Two deck pre-fabricated
columns in place, not
patched and no concrete
pouring
 Installation of roof & eaves
frame for main body is
finished and is aligned on
the material type in plan,
although distribution of Jea
span is not as planned (the
plan indicates single Jea
span every spacing, but in
actual, it has been an
alternate between one and
two Jea spans each
spacing)
 Canopies are already built,
however it is slightly
leaning downwards, the
plan requires a leveled
canopy from the horizon.
 Water supply layout has
already been installed in
place, although based on
the pipe channel on the
wall being cleared, the
outside faucet seems to be
placed on the other side
as-built instead of the
entranceway side as-
planned. (See attached
image on the
documentation)
 Pipe material used are yet
to be checked next week
by the interns
 Drainage layout is already
86 installed in place and is
Plumbing Rough In
aligned as-planned,
although no holes for
septic tank and grease trap
receptacle are present
 Installation of piping layout
is already on-going and
location for water closet,
lavatory, & shower are as-
planned at masters
bedroom and for powder
room
 Installation of outlet and
switch layout is already
completed and hiding of
circuit pipe wall channels
are still on-going
 Location of convenience
outlet heater for masters
bedroom is inconsistent
with the plan, in the plan it
should be located in
between the shower room
and water closet, in actual
built it is located between
lavatory and water closet.(
See attached image on the
documentation)
 Installation of convenience
outlet for ACU in dining
Electrical Rough In 35 area is cancelled in actual
built because in actual,
there is a big window from
where the outlet should
have been installed as
planned. (See attached
image)
 There are two convenience
outlet installed at the side
of the kitchen where the
masters bedroom door is
located in actual built, in
plan, there is only one
convenience outlet. (See
attached image)
 Location of panel board is
aligned as planned, but
installation of panel board
is still pending
 Heights for panel board,
switches, and outlets are
yet to be checked due to
lacking floor finish
 Wall layout, location, and
alignment is already
completed and is aligned
to plan
 Plumbing and electrical
roughing in is still on-going
as for this week, therefore
there are still wall holes
that needs to be patched
Wall Works 67 up
 Wall fixtures are not yet
installed due to incomplete
wall finishes
 All doorways are yet to be
finished
 Window ways are already
in shape, as for location,
there has been a slight
difference in actual built
because in the living space
area there is a window way
that is not present in the
initial plan
 No ceiling works yet aside
from the roof and eaves
Ceiling Works
frame
Mechanical Installations -
Glass Works -
Tile Works -
Finishing Works -
Furnishing Works -
Post Construction Phase -
DOCUMENTATION

Overall Current Status of the Single-Detached House from Day 1


DOCUMENTATION

Unmatched As-Built Component to As-Planned as per


Intern Observation

- Location of convenience outlet heater for


masters bedroom is inconsistent with the plan, in
the plan it should be located in between the
shower room and water closet, in actual built it is
located between lavatory and water closet.

- Installation of convenience
outlet for ACU in dining area is
cancelled in actual built because
in actual, there is a big window
from where the outlet should
have been installed as planned.

- There are two convenience outlet installed at the


side of the kitchen where the masters bedroom
door is located in actual built, in plan, there is only
one convenience outlet.
DOCUMENTATION

Unmatched As-Built Component to As-Planned as per


Intern Observation

- Based on the pipe channel on the wall being cleared, the


outside faucet seems to be placed on the other side as-built
instead of the entranceway side as-planned.