Professional Documents
Culture Documents
BQS659 Week 08 Damages for Non-Completion
BQS659 Week 08 Damages for Non-Completion
NON-COMPLETION
1.0 INTRODUCTION
1.0 INTRODUCTION
• Damages for non-completion means that the
contractor must responsible to complete the works
within the contract period or within Extension of
time (EOT).
• If the contractor fails to carry out their
responsibilities as stated in the contract due to his
own faults, then he will be issued with Certificate of
Non-Completion.
• The contractor is released of his liability for damage
due to non-completion upon the issuance of the
Certificate of Practical Completion
CLAUSE 33.0:
Deduction from
money due to
contractor
CLAUSE 40.0:
CLAUSE 42.0:
P.W.D. FORM Damages for
Partial occupation
203A (REV.2010) non-
completion
CLAUSE 41.0:
Sectional
completion
2.0 P.W.D FORM 203A
(REV 1/2010)
2.0 P.W.D FORM 203A(REV 2007)
• CLAUSE 33.0: Deduction from money due to contractor
- According to this clause, the Government or the S.O can deduct any
money that owing from the contractor to the Government under the
contract. It is as the chargeable to cover the losses incurred by the
government.
• CLAUSE 40.0: Damages for non-completion
- The contractors should complete the works within the extended time
granted as stated in Clause 40.0.
- The Liquidated Ascertained Damages that need contractor pay that
stated in Appendix must be reasonable amount with the Government
suffer loss because of the non-completion of the project.
- Contractor needs to complete the Works (obligation) even though
Liquidated Ascertained Damages is issued.
2.0 P.W.D FORM 203A(REV 2007)
• CLAUSE 41.0: Sectional completion
- In this clause, if there has the different of completion dates for different
sections or parts of the works ,the Liquidated Ascertained Damages for
each sections will be separately according to:
1. Certificate of Practical Completion
2. Delay and Extension of Time
3. Liquidated Ascertained Damages and
4. Defects Liability Period
• CLAUSE 42.0: Partial occupation
- If there is some of the section that is not completed within the stipulated
time, the Liquidated and Ascertained Damages for the remaining works
should be recalculated and to be reduced in the proportion which the
value of the relevant part bears to the contract sum.
3.0 NON-COMPLETION
3.0 NON-COMPLETION
• Non-completion
➢works do not reach practical completion
within contractual completion date
• OBLIGATION to complete the work within
stipulated time.
3.0 NON-COMPLETION
Date for completion
-Works completed
Date for possession of site -C.P.C.
L.A.D.
DELAY
Terminate L.A.D.
Affects of delay
3.0 NON-COMPLETION
• Not contractor’s fault → E.O.T
• Contractor’s fault
-> No E.O.T.
-> Pay L.A.D.
-> Terminate
• Length of delay:
Completion date -C.P.C
3.0 NON-COMPLETION
• Employer’s fault
-> Render the completion
-> Lose right to damages
4.0 CERTIFICATE OF NON-
COMPLETION
4.0 CERTIFICATE OF NON-COMPLETION
1. Notice (warning letter)
• Issuing before Certificate of Non Completion
• Condition precedent to issue Certificate of Non
Completion
• Notice and Certificate of Non Completion : to warn
contractor LAD will be charged if works cannot complete
on time.
Non-completion
Notice to contractor -Certificate of Non Completion
4.0 CERTIFICATE OF NON-COMPLETION
The rate of liquidated and ascertained damages is important to be clearly stated in the
Appendix as shown in figure 6 so that the Contractor is aware of the financial
implication of delay.
On the other side, it clearly show and protect the rights for Employer to claim the
damages if the Contractor breach of contract.
40 Liquidated and Ascertained Damages as the rate of ……………… RM 500.00 per Day
Figure 6
5.1 Liquidated and Ascertained Damages
(cont’d)
Express
provision
for L.A.D
C.N.C has
It is not a
been
penalty
issued
Claiming of
L.A.D by the
employer, he
must shows
that:
The sum is
Retains his
stated in
right
Appendix
Completion
date is
specified
5.2 The latest Legal Position on L.A.D Malaysia
In Malaysia, the contract is governed by the Contract Act 1950. In the Section
75 of the Contract Act 1950 was stated that:
• “When then contract has been broken, if a sum is named in the contract as the
amount to be paid in case of such breach, or if the contract contains any other
stipulation by way of penalty, the party complaining of the breach is entitled,
whether or not actual damage or loss is proved to have been caused thereby, to
receive from the party who has broken the contract reasonable compensation
not exceeding the amount so named or, as the case may be, the penalty
stipulated for.”
Many of the intentions of the standard forms for the treatment of Liquidated
Ascertained Damages are over ruled Act.
5.2 The latest Legal Position on L.A.D Malaysia
(cont’d)
Therefore the court has given decisions to the following effects:
a) loss of income
by the employer
b)factors that
c)cost of contribute to
providing the total loss
finance for the incurred by
contract works the employer
5.3 Computation of Liquidated and Ascertained Damages
(cont’d)
BASED ON THE LOSS INCOME BY THE EMPLOYER
This method is generally applicable to small project that provide revenue to the
Employer.
ii) The estimated income from the business to be conducted in the building
A reasonable amount of profit or income that the contractor in the building to make out of his
business but this way is a bit difficult to establish and subject to much argument
Delay : 15 Days
The expected amount of profit : RM 4,500.00/Day
Therefore,
RM 4,500.00 x 15 Days = RM 67, 500.00
5.3 Computation of Liquidated and Ascertained Damages
(cont’d)
Based on factors that contribute to the total loss incurred by the Employer
This method is usually use for big project which provide revenue to the Employer for
example shopping mall. This method is more comprehensive because it considered
factors such as :
1) Financing
charges
3) Prolongation 2) Loss of
cost income
5.3 Computation of Liquidated and Ascertained Damages
(cont’d)
Example : Housing Scheme
Assumptions:
Project financing based on 20% equity and 80% loan
Delay occur at 75% of completion period
Contract sum = RM 120, 000.00 / Unit
Interest rate = 8%
Total number of unit = 200 units of double storey terrace houses
25% incomplete
Selling price = RM 240, 000.00 / unit
1) Financing charges
= RM 266.67 / Day
5.3 Computation of Liquidated and Ascertained Damages
(cont’d)
= RM 6, 348.90 / Day
5.3 Computation of Liquidated and Ascertained Damages
(cont’d)
BASED ON THE COST OF PROVIDING FINANCE FOR THE WORK
•This method usually is use to non-making profit concern for example for project school,
mosque, clinic etc. In other words this method is applicable for government project.
•In order to calculate the liquidated damages, it is necessary to base lending rate from any
commercial bank in the area where the project is situated.
Example:
Assumptions:
Identification of Sections or Date for Possession [Clause Date for Completion Liquidated & Ascertained
parts 38.3 ] Damages
Block C 10. 8. 2009 15. 11. 2010 RM1, 200.00 per Day
= RM 1, 200.00/ Day
5.6 Deduction for Liquidated and Ascertained Damages
“……. The S.O may deduct such damages from any money due or to become due to the
Contractor failing which…..recovered from the Performance Bond or as a debt due
from the Contractor. The S.O shall inform the Contractor in writing of such deduction.”
(Clause 40.2)