INTERIM
•
•
Prepared by:
Faizzudin bin E’Ali
Mohd Firdaus bin Kamarudin
Muhammad Zaki bin Mohd Yusoff
PAYMENTS
Interim Payment?
•All payment made to the contractor other than
the final payment
Clauses:-
14 days
Issuance of certificate
by S.O
30 days
Payment made by
employer
Contractor’s Application
• Submission payment application by the contractor
= 2.91619%
B Frame
235,000.00 100 235,800.00
C Upper floor
114,500.00 85 97,325.00
D Staircase
54,000.00 40 21,600.00
E Roof
120,000.00 0 0.00
TOTAL
949,300.00 779,225.00
c) The contract sum
Example:
Amount of work done = 25% x Rm100, 000.00 = RM
25,000.00
Where 25% is the percentage of work completed and RM
100,000.00 is the contract sum.
Valuation based on stage of completion
BREAKDOWN OF CONTRACT SUM
PERCENTAGE OF CONTRACT
ITEMS STAGES OF WORKS
SUM
5 Finishes 15
TOTAL 100
Percentage Adjustment
• S.O check contract document and make
adjustments or corrections to:
a) Unreasonable and inconsistent rates
b) Arithmetical errors in the pricing by contractor
60,500.00
TOTAL 54,450.00
Fluctuation of price
‘The amount payable by the Government to the contractor upon the issue by
the S.O. of an interim certificate shall be increased or decreased accordingly….’
(Clause 30 )
Example of calculation
Fluctuation factors = Recovery factor x (Current index figure – Base index figure)
Base index figure
Effective value of work done = Value of work done to date – Value of work done to
previous month
Recovery factor = Percent of material cost, for example 0.70 (estimated material cost is
70% of the total cost of the work)
Assumption:
• First interim certificate can be issue even before signing the contract and
this is not one of a condition in issuance of interim certificate.
• Clause 28.1
‘...and the total value thereof has reached the sum referred to in the
appendix …the S.O. shall at that time make the first valuation of the same’
• Clause 28.2
‘Thereafter, once (or more often at the discretion of the S.O.) during the
course of each succeeding month….each subsequent valuation shall not be
less than the sum referred to in the appendix…’
• S.O. has a right to make any correction in any previous certificate either to
add or omit the value of any work according to his satisfaction.
• In the event of contractor not satisfied with the amount certified, the
contractor may request to the S.O.
Then adjustment will be made in a subsequent certificate.
Payment to contractor
• Within 30 days of the issue of interim
payment, the Government must
– Make the payment to Contractor
Contractor’s application
Valuation
Certificates and payment
Suspension of Works
Payment to Nominated Sub-contractors
Direct payment to Nominated Sub-Contractors
Retention money
Contractor’s application (Clause 30.1) cont’d
– Total of the work done and also the material available on site on
the date of the contractor’s claim.
Certificate & Payment (Clause30.1)
Claims by Cert. by
Contractor Architect Payment
Valuation by QS
21 days 21 days
Period of
honoring cert.
21 days 21 days
Payment by
Payment by contractor to
Claims by Cert. by employer to sub-
Contractor Architect contractor contractor
Period of honoring
Valuation by QS cert.
14 days ≤ 21 days