Professional Documents
Culture Documents
L4-FINAL PAYMENT
L4-FINAL PAYMENT
CLAIM checked
by S.O.
FINAL CERTIFICATE
prepared by S.O
≤30
Days
PAYMENT made
by employer
contractor is The contractor
The claims should be
responsible to should include all
submitted as soon as
submit claims to claims in his claim
possible to the S.O.
the S.O. document
clause
31.3 in
PWD 203A
If during the inspection This schedule must be
there were any defect issued to the contractor
found, the S.O will within 14 days after the
prepare schedule of end of Defect Liability
defect. Period.
If the employer
have to make Final Certificate must
good any defect, be issued within 6
he can claimed month after the
any cost incurred issuance of Certificate
from the of Practical
Performance Completion.
Bond.
PWD 203 A clause 31.4
•Final Certificate is the statement of
all the final valuation
•Employer should pay to contractor
all work done by him and also loss
and expenses incurred by him
Final
contract
The contractor sum or the
can go to total cost of
arbitration if he the
is not satisfied completed
with the Final job
The deductions are for :
Certificate.
•All amount previously
paid by the employer
to contractor
•All sums to which the
employer is entitled
The contents
of the
certificate
are
All necessary
adjustment to
the contract sum
such as all
As an evident variations and
that the works The final claims has been
have been payment is not done
properly carried considered as accordingly
out and final and
completed conclusive if the
dispute is
brought to
arbitrator or
court.
Defects which would not
have been disclosed by
reasonable inspection
before issuance of
certificate
The
certificate
can be
challenged if
If the final
contract sum
exceeds the total
amount paid to
the contractor,
If there is no the excess shall
period stated in be paid to the
the Appendix, contractor by the
the period is employer
within 30 days It is the last
after the issuance certificate
of the certificate.
Before releasing
the final payment,
the S.O. has to
make sure that
the contractor
has
Liquidated damages