Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

I st & Part Bill

Name of the work : Construction of Forest Range Officer Quarter at Tekulapally of Tekulapally Range of
Kothagudem Division, Bhadradri Kothagudem District, during 2022-23 under CAMPA - NPV scheme.

Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20
B (APSS 308). for building foundation.

Columns C1, C6, C4, C10 1 x 4 1.65 1.65 1.65 17.96


Columns C2, C9, C12 1 x 3 1.65 1.65 1.65 13.47
Columns C11-14 1 x 1 3.10 1.65 1.65 8.43
Columns C3, C8, C5, C13 1 x 4 1.65 1.65 1.65 17.96
Columns C7-15 1 x 1 1.65 3.10 1.65 8.43
66.25 Cu.Mt 430.10 1 Cu.Mt 28494.13
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

PCC Under Col. Footings 1 x 13 1.65 1.65 0.15 5.31


1 x 2 1.65 3.10 0.15 1.53
6.84 Cu.Mt 5679.31 1 Cu.Mt 38846.48
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type C13, 1 x 10 x 2 1.70 0.62 21.08
F2 Type C1,C2,C3,C6,C10, 7 x 10 x 2 1.70 0.62 147.56
F3 Type C4,C5,C8 3 x 10 x 2 1.70 0.62 63.24
F3 type C9, C12 2 x 10 x 2 1.70 0.62 42.16
F4 Type CF1 C11-C14 1 x 20 x 1 1.70 0.62 21.08
F4 Type CF1 C11-C14 1 x 10 x 1 3.20 0.62 19.84
F4 Type CF1 C7-C15 1 x 10 x 1 3.20 0.62 19.84
F4 Type CF1 C7-C15 1 x 20 x 1 1.70 0.62 21.08
Footings Total Qty : 355.88 Kgs
Columns
12mm dia
C1 type C13, C14, C15 1 x 3 x 6 3.00 0.89 48.06
C2 Type C1,C2,C3,C6,C7,C10, C11 1 x 7 x 6 3.00 0.89 112.14
16mm dia
C3 Type C4,C5,C8 1 x 3 6 3.00 1.59 85.86
C4 Type C9, C12 1 x 2 x 8 3.00 1.59 76.32
8mm dia
Stirrups 1 x 13 x 20 1.05 0.39 106.47
Stirrups 1 x 2 x 20 1.05 0.39 16.38
Columns Total Qty : 445.23 Kgs
Total Qty : 801.11 Kg 92.75 1 Kg 74302.95
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Column Footings.

F1 type C13 1 x 1 1.55 1.55 0.30 0.72


F2 Type C1,C2,C3,C6,C10, 1 x 5 1.60 1.60 0.30 3.84
F3 Type C4,C5,C7 1 x 3 1.60 1.60 0.30 2.30
F4 type C9, C12 1 x 2 1.60 1.60 0.30 1.54
F5 Type CF1 C11-C14 1 x 1 3.00 1.50 0.30 1.35
F5 Type CF1 C15-C8 1 x 1 1.50 3.00 0.30 1.35
(0.30/3) x ((1.55² )+(0.23x0.30)+
Taper Portion 1 x 1 √(1.55²) X (0.23x0.30))
0.29
(0.30/3) x ((1.60² )+(0.23x0.30)+
Taper Portion 1 x 5 √(1.60²) X (0.23x0.30))
1.52
(0.30/3) x ((1.60² )+(0.23x0.30)+
Taper Portion 1 x 3 √(1.60²) X (0.23x0.30))
0.91
(0.30/3) x ((1.60² )+(0.23x0.30)+
Taper Portion 1 x 2 √(1.60²) X (0.23x0.30))
0.61
(0.30/3) x ((3.00x1.50 )+(0.23x0.30)+
Taper Portion 1 x 1 √(3.00x1.50) X (0.23x0.30))
0.51
(0.30/3) x ((3.00x1.50)+(0.23x0.30)+
Taper Portion 1 x 1 √(3.00x1.50) X (0.23x0.30))
0.51
Total in Cu.Mt :: 15.45 Cu.Mt 10924.10 1 Cu.Mt 168777.35
5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Columns.

Columns upto plinth beam 1 x 15 0.30 0.23 2.55 2.63


2.63 Cu.Mt 14625.56 1 Cu.Mt 38465.22
6) Filling with useful available excavated earth (excluding rock) in trenches, sides
of foundations and basement with initial lead in layers not exceeding 15 cm
thick, consolidating each deposited layer by watering and ramming including
cost and conveyance of water to work site and all operational, incidental,
labour charges, hire charges of T & P etc., complete for finished item of work.
APSS No.309 & 310.

total EW forColumns pits 66.25


Deduct Columns footings -15.45
Deduct Columns up to plinth Beam -2.63
PCC Under Col. Footings -6.84
Total in Cu.Mt :: 41.33 Cu.Mt 384.02 1 Cu.Mt 15871.55
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
7) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20
B (APSS 308) for building foundation.

South side walls 1 x 1 14.10 0.45 0.90 5.71


West Side walls 1 x 1 9.30 0.45 0.90 3.77
East side walls 1 x 1 3.95 0.45 0.90 1.59
" " 1 x 1 1.80 0.45 0.90 0.72
" " 1 x 1 6.12 0.45 0.90 2.47
North side walls 1 x 1 8.56 0.45 0.90 3.47
" " 1 x 1 6.73 0.45 0.90 2.73
" " 1 x 1 0.50 0.45 0.90 0.20
Deduct Columns portion -1 x 15 1.50 0.45 0.90 -9.11
11.55 Cu.Mt 430.10 1 Cu.Mt 4967.66
8) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

Under CRS Walls


South side walls 1 x 1 14.10 0.45 0.15 0.95
West Side walls 1 x 1 9.30 0.45 0.15 0.62
East side walls 1 x 1 3.95 0.45 0.15 0.26
" " 1 x 1 1.80 0.45 0.15 0.12
" " 1 x 1 6.12 0.45 0.15 0.41
North side walls 1 x 1 8.56 0.45 0.15 0.57
" " 1 x 1 6.73 0.45 0.15 0.45
" " 1 x 1 0.50 0.45 0.15 0.03
Deduct Columns portion -1 x 15 1.50 0.45 0.15 -1.51
1.90 Cu.Mt 5679.31 1 Cu.Mt 10790.69
9) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental charges and labour charges such as mixing mortar, finishing, curing,
etc., complete for finished item of work. (APSS 901, 906).

South side walls 1 x 1 14.10 0.45 2.55 16.17


West Side walls 1 x 1 9.30 0.45 2.55 10.67
East side walls 1 x 1 3.95 0.45 2.55 4.53
" " 1 x 1 1.80 0.45 2.55 2.06
" " 1 x 1 6.12 0.45 2.55 7.02
North side walls 1 x 1 8.56 0.45 2.55 9.82
" " 1 x 1 6.73 0.45 2.55 7.72
" " 1 x 1 0.50 0.45 2.55 0.57
Deduct Columns portion -1 x 15 0.23 0.30 2.55 -2.63
Total in Cu.Mt :: 55.93 Cu.Mt 5182.84 1 Cu.Mt 289876.24
10) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20
B (APSS 308). for building foundation.

Stair case Column 1 x 1 1.50 1.50 1.50 3.37


3.37 Cu.Mt 430.10 1 Cu.Mt 1449.44
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
11) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

PCC Under Col. Footings 1 x 1 1.20 1.20 0.15 0.22


0.22 Cu.Mt 5679.31 1 Cu.Mt 1249.45
12) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
Stair case Column 2 x 10 x 1 1.70 0.62 21.08
Footings Total Qty : 21.08 Kgs
Columns
12mm dia
Stair case Column 1 x 2 x 3 3.90 0.89 20.83
8mm dia
Stirrups 1 x 1 x 26 1.05 0.39 10.65
Columns Total Qty : 31.48 Kgs
Total Qty : 52.56 Kg 92.75 1 Kg 4874.94
13) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Column Footings.

Stair case Col. Footing 1 x 1 1.45 1.45 0.30 0.63


(0.30/3) x ((1.45² )+(0.23x0.30)+
Taper Portion 1 x 1 0.59
√(1.45²) X (0.23x0.30))
Total in Cu.Mt :: 1.22 Cu.Mt 10924.10 1 Cu.Mt 13327.40
14) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Columns.

1 x 1 0.30 0.23 1.65 0.11


0.11 Cu.Mt 14625.56 1 Cu.Mt 1608.81
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
15) Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including all operational, incidental, labour charges,
seignorage charges, hire charges of T & P etc., complete for finished item of
work. (APSS No. 309 & 310).

Inside Basement 1 x 1 14.10 9.30 1.80 236.03


Varandah Portion 1 x 1 3.95 1.80 1.80 12.80
1 x 1 6.10 0.50 1.80 5.49
254.32 Cu.Mt 472.49 1 Cu.Mt 120163.66
16) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

Under Plinth Beam


Inside Between C11 to C12 1 x 1 5.83 0.45 0.15 0.39
Kitchen C/w 1 x 1 3.60 0.45 0.15 0.24
Bed Room 3 L/w 1 x 2 3.60 0.45 0.15 0.48
C/w 1 x 1 3.60 0.45 0.15 0.24
Toilet C/w 1 x 1 1.20 0.45 0.15 0.08
Pooja C/w 1 x 1 1.20 0.45 0.15 0.08
Bed Room 2 L/w 1 x 1 3.60 0.45 0.15 0.24
C/w 1 x 1 3.60 0.45 0.15 0.24
Bed Room 1 L/w 1 x 1 4.50 0.45 0.15 0.30
C/w 1 x 1 3.85 0.45 0.15 0.25
2.54 Cu.Mt 5679.31 1 Cu.Mt 14425.45
17) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Plinth Beams (Outer)


12mm dia
C1 to C2, C4 to C5, C8 to C12 3 x 3 x 2 6.10 0.89 97.72
C2 to C3, C5 to C6, C12 to C7,
C11 to C10 & at Kitchen wall 6 x 3 x 2 4.30 0.89 137.77
and Toilet
C3 to C6, C2 to C5, C1 to C4
4 x 3 x 2 5.40 0.89 115.34
and For Toilet wall
C6 to C7, C5 to C12, C4 to C8 3 x 3 x 2 4.25 0.89 68.09
C7 to C10, C12 to C11, 2 x 3 x 2 6.05 0.89 64.61
C9 to C11/12 1 x 3 x 2 4.55 0.89 24.30
C9 to C8/12 1 x 3 x 2 4.60 0.89 24.56
C8 to C15 1 x 3 x 2 1.00 0.89 5.34
C15 to C13 1 x 3 x 2 6.95 0.89 37.11
C13 to C14 1 x 3 x 2 6.35 0.89 33.91
C11 to C14 1 x 3 x 2 1.35 0.89 7.21
Toilets C/w 1 x 3 x 2 1.90 0.89 10.15
Toilets C/w 1 x 3 x 2 1.80 0.89 9.61
Pooja Room C/w 1 x 3 x 2 1.70 0.89 9.08
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
8mm dia
Stirrups 1 x 1 x 41 1.05 0.39 16.79
Stirrups 1 x 1 x 29 1.05 0.39 11.88
Stirrups 1 x 1 x 36 1.05 0.39 14.74
Stirrups 1 x 1 x 29 1.05 0.39 11.88
Stirrups 1 x 1 x 41 1.05 0.39 16.79
Stirrups 1 x 1 x 31 1.05 0.39 12.69
Stirrups 1 x 1 x 31 1.05 0.39 12.69
Stirrups 1 x 1 x 7 1.05 0.39 2.87
Stirrups 1 x 1 x 47 1.05 0.39 19.25
Stirrups 1 x 1 x 43 1.05 0.39 17.61
Stirrups 1 x 1 x 9 1.05 0.39 3.69
785.68 Kg 92.750 1 Kg 72871.82
18) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Plinth Beam.

C1 to C2, C4 to C5, C8 to
3 x 1 x 1 6.10 0.23 0.30 1.26
C12
C2 to C3, C5 to C6, C12
to C7, C11 to C10 & at 6 x 1 x 1 4.30 0.23 0.30 1.78
Kitchen wall and Toilet
C3 to C6, C2 to C5, C1 to
4 x 1 x 1 5.40 0.23 0.30 1.49
C4 and For Toilet wall
C6 to C7, C5 to C12, C4
3 x 1 x 1 4.25 0.23 0.30 0.88
to C8
C7 to C10, C12 to C11, 2 x 1 x 1 6.05 0.23 0.30 0.83
C9 to C11/12 1 x 1 x 1 4.55 0.23 0.30 0.31
C9 to C8/12 1 x 1 x 1 4.60 0.23 0.30 0.32
C8 to C15 1 x 1 x 1 1.00 0.23 0.30 0.07
C15 to C13 1 x 1 x 1 6.95 0.23 0.30 0.48
C13 to C14 1 x 1 x 1 6.35 0.23 0.30 0.44
C11 to C14 1 x 1 x 1 1.35 0.23 0.30 0.09
Toilets C/w 1 x 1 x 1 1.90 0.23 0.30 0.13
Toilets C/w 1 x 1 x 1 1.80 0.23 0.30 0.12
Pooja Room C/w 1 x 1 x 1 1.70 0.23 0.30 0.12
Total in Cu.Mt :: 8.32 Cu.Mt 14739.58 1 Cu.Mt 122633.31
Total : 1022996.55
19) Sanitory Charges 6% on total Cost 61379.79
20) Electrification Charges 7% on total Cost 71609.76
Total:- 1155986.10
II nd & Part Bill
Name of the work : Construction of Forest Range Officer Quarter at Tekulapally of Tekulapally Range of
Kothagudem Division, Bhadradri Kothagudem District, during 2022-23 under CAMPA - NPV scheme.
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Columns
12mm dia
C1 type C13, C14, C15 1 x 3 x 6 4.20 0.89 67.28
C2 Type C1,C2,C3,C6,C7,C10, C11 1 x 7 x 6 4.20 0.89 157.00
16mm dia
C3 Type C4,C5,C8 1 x 3 6 4.20 1.59 120.20
C4 Type C9, C12 1 x 2 x 8 4.20 1.59 106.85
8mm dia
Stirrups 1 x 13 x 28 0.95 0.39 134.86
Stirrups 1 x 2 x 28 0.95 0.39 20.75
Columns Total Qty : 606.94 Kgs
For Stair case I st Flight
Stair case I st flight 10mm dia top
Bar Cross
1 x 1 x 27 1.35 0.62 22.60
Stair case I st flight 10mm dia
Bottom Bar Cross
1 x 1 x 27 1.35 0.62 22.60
Stair case I st flight 10mm dia
Top Bar Long
1 x 1 x 7 5.35 0.62 23.22
Stair case I st flight 10mm dia
Bottom Bar Long
1 x 1 x 7 5.35 0.62 23.22
Landing 10 mm dia Top 1 x 1 x 12 2.60 0.62 19.34
Landing 10 mm dia Bottom 1 x 1 x 12 2.60 0.62 19.34
Landing 10 mm dia Top 1 x 1 x 20 2.00 0.62 24.80
Landing 10 mm dia Bottom 1 x 1 x 20 2.00 0.62 24.80
Landing Beam 1 x 2 x 3 2.60 0.89 13.88
Columns Total Qty : 193.80 Kgs
Total Qty : 800.74 Kg 92.75 1 Kg 74268.64
2) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Columns.

Columns 12 x 1 0.30 0.23 3.00 2.48


Circuler Columns 2 x 0.785 0.23 0.23 3.00 0.24
2.72 Cu.Mt 14625.56 1 Cu.Mt 39781.52
3) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Mid Landing Beam.

Mid landing 1 x 1 x 1 2.60 0.23 0.30 0.18


Total in Cu.Mt :: 0.18 Cu.Mt 14987.79 1 Cu.Mt 2697.80
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Stair case I st Flight.

Stair case I st flight 1 x 1 x 1 5.10


1.25 - 6.38
Mid landing 1 x 1 x 1 2.60
2.02 - 5.25
Total in Sq.Mt :: 11.63 Sq.Mt 1711.91 1 Sq.Mt 19909.51
5) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

Varandah 1 x 1 5.66
2.10 0.23 2.73
1 x 1 4.36
2.03 0.23 2.03
Living / Hall 1 x 1 3.90
1.57 0.23 1.40
Dinning 1 x 1 3.60
5.60 0.23 4.63
Pooja Room & Front 1 x 1 1.80
1.10 0.23 0.45
Kitchen 1 x 1 3.34
3.15 0.23 2.41
Master Bed room 1 x 1 3.83
4.50 0.23 3.96
Bed Room 2 1 x 1 3.60
3.60 0.23 2.98
Bed Room 3 1 x 1 3.60
3.87 0.23 3.20
Toilet 1 & Front side 1 x 1 3.83
1.47 0.23 1.29
Toilet 2 & Front side 1 x 1 3.60
1.35 0.23 1.11
Total in Cu.Mt :: 26.19 Cu.Mt 5310.29 1 Cu.Mt 139076.50
6) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Roof Beams


B1 type Beam
C11 to C14 12mm dia top 1 x 2 x 1 1.35 0.89 2.40
C11 to C14 12mm dia Bottom 1 x 2 x 1 1.35 0.89 2.40
Stirrups 8mm dia 1 x 1 x 9 1.25 0.39 4.39
C13 to C15 12mm dia top 1 x 2 x 1 1.80 0.89 3.20
C13 to C15 12mm dia Bottom 1 x 2 x 1 1.80 0.89 3.20
Stirrups 8mm dia 1 x 1 x 12 1.25 0.39 5.85
B3 type Beam
1 C11 to C10, C12 to C7, C5 to C6,
C2 to C3 12mm dia Top
4 x 2 x 1 5.05 0.89 35.96
" " 16mm dia Extras 4 x 2 x 1 1.68 1.59 21.37
C11 to C10, C12 to C7, C5 to C6,
C2 to C3 12mm dia Bottom 4 x 2 x 1 5.05 0.89 35.96
" " 12mm dia Extras 4 x 2 x 1 1.68 0.89 11.96
Stirrups 8mm dia 4 x 1 x 34 1.25 0.39 66.30
2 C4 to C8, C5 to C12, C6 to C7
3 x 2 x 1 5.00 0.89 26.70
12mm dia Top
" " 16mm dia Extras 3 x 2 x 1 1.66 1.59 15.84
C4 to C8, C5 to C12, C6 to C7 12mm
dia Bottom
3 x 2 x 1 5.00 0.89 26.70
" " 12mm dia Extras 3 x 2 x 1 1.66 0.89 8.86
Stirrups 8mm dia 3 x 1 x 34 1.25 0.39 49.73
3 C13 to C14 12mm dia Top 1 x 2 x 1 6.70 0.89 11.93
" " 16mm dia Extras 1 x 2 x 1 2.23 1.59 7.09
C13 to C14 12mm dia Bottom 1 x 2 x 1 6.70 0.89 11.93
" " 12mm dia Extras 1 x 2 x 1 2.23 0.89 3.97
Stirrups 8mm dia 1 x 1 x 45 1.25 0.39 21.94
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
B4 type Beam
C3 to C6, C2 to C5, C1 to C4
12mm dia top
3 x 2 x 1 6.06 0.89 32.36
" " 16mm dia Extras 3 x 2 x 1 2.02 1.59 19.27
C3 to C6, C2 to C5, C1 to C4
16mm dia Bottom
3 x 2 x 1 6.06 1.59 57.81
" " 16mm dia Extras 3 x 2 x 1 2.02 1.59 19.27
Stirrups 8mm dia 3 x 1 x 41 1.25 0.39 59.96
C1 to C2, C4 to C5 12mm dia top 2 x 2 x 1 6.70 0.89 23.85
" " 16mm dia Extras 2 x 2 x 1 2.23 1.59 14.18
C1 to C2, C4 to C5 16mm dia
Bottom
2 x 2 x 1 6.70 1.59 42.61
" " 16mm dia Extras 2 x 2 x 1 2.23 1.59 14.18
Stirrups 8mm dia 2 x 1 x 45 1.25 0.39 43.88
C9 to C11/12 12mm dia top 1 x 2 x 1 4.52 0.89 8.05
" " 16mm dia Extras 1 x 2 x 1 1.50 1.59 4.77
C9 to C11/12 16mm dia Bottom 1 x 2 x 1 4.52 1.59 14.37
" " 16mm dia Extras 1 x 2 x 1 1.50 1.59 4.77
Stirrups 8mm dia 1 x 1 x 31 1.25 0.39 15.11
B5 type Beam
C8 to C12 16mm dia top 1 x 2 x 1 6.40 1.59 20.35
C8 to C12 20mm dia Bottom 1 x 2 x 1 6.40 2.48 31.74
C8 to C12 16mm dia Bottom 1 x 1 x 1 6.40 1.59 10.18
C8 to C12 20mm dia Extras 1 x 2 x 1 2.13 2.48 10.56
Stirrups 8mm dia 1 x 1 x 43 1.25 0.39 20.96
C11 to C12 16mm dia top 1 x 2 x 1 6.04 1.59 19.21
C11 to C12 20mm dia Bottom 1 x 2 x 1 6.04 2.48 29.96
C11 to C12 16mm dia Bottom 1 x 1 x 1 6.04 1.59 9.60
C11 to C12 20mm dia Extras 1 x 2 x 1 2.01 2.48 9.97
Stirrups 8mm dia 1 x 1 x 41 1.25 0.39 19.99
B6 type Beam
C7 to C10, C15 to C13 12mm dia top 2 x 2 x 1 6.04 0.89 21.50
C7 to C10, C15 to C13 16mm dia
Extras
2 x 3 x 1 2.01 1.59 19.18
C7 to C10, C15 to C13 16mm dia
Bottom
2 x 2 x 1 6.04 1.59 38.41
C7 to C10, C15 to C13 12mm dia
Bottom
2 x 1 x 1 6.04 0.89 10.75
" " 16mm dia Extras 2 x 2 x 1 2.01 1.59 12.78
Stirrups 8mm dia 2 x 1 x 41 1.25 0.39 39.98
CB type Beam
at varandah B1 12mm dia top 1 x 2 x 1 2.76 0.89 4.91
at varandah B1 16mm dia Extras 1 x 3 x 1 0.92 1.59 4.39
at varandah B1 16mm dia Bottom 1 x 2 x 1 2.76 1.59 8.78
at varandah B1 12mm dia Bottom 1 x 1 x 1 2.76 0.89 2.46
at varandah B1 16mm dia Extras 1 x 2 x 1 0.92 1.59 2.93
Stirrups 8mm dia 1 x 1 x 19 1.25 0.39 9.26
at varandah B2 12mm dia top 1 x 2 x 1 2.23 0.89 3.97
at varandah B2 16mm dia Extras 1 x 3 x 1 0.74 1.59 3.53
at varandah B2 16mm dia Bottom 1 x 2 x 1 2.23 1.59 7.09
at varandah B2 12mm dia Bottom 1 x 1 x 1 2.23 0.89 1.98
at varandah B2 16mm dia Extras 1 x 2 x 1 0.74 1.59 2.35
Stirrups 8mm dia 1 x 1 x 15 1.25 0.39 7.31
Roof Beams Total Qty : 1136.20 Kgs
Roof Slab Reinforcement
Long span bars 8mm dia 1 x 1 x 80 16.30 0.39 508.56
Short span bars 8mm dia 1 x 1 x 107 11.85 0.39 494.50
Support Bars 4 x 5 x 6 3.50 0.39 163.80
Support Bars at Varandah 1 x 5 x 10 3.00 0.39 58.50
Roof Slab Total Qty : 1225.36 Kgs
Mid Landing Beam
12mm dia top 1 x 3 x 1 2.75 0.89 7.34
12mm dia Bottom 1 x 3 x 1 2.75 0.89 7.34
Stirrups 8mm dia 1 x 1 x 16 1.00 0.39 6.24
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
For Stair case II nd Flight
Stair case II nd flight 10mm dia
top Bar Cross
1 x 1 x 15 1.20 0.62 11.16
Stair case II nd flight 10mm dia
Bottom Bar Cross
1 x 1 x 15 1.20 0.62 11.16
Stair case II nd flight 10mm dia
Bottom Bar Long
1 x 1 x 8 2.30 0.62 11.41
Stair case II nd flight 10mm dia
Bottom Bar Long
1 x 1 x 8 2.30 0.62 11.41
Stair case Total Qty : 66.06 Kgs
Steel Total Qty : 2427.62 Kgs 92.750 1 Kg 225161.76
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Roof Beams.
B3 type Beams C14 to C10, C12 to
C7, C5 to C6, C2 to C3
4 x 1 x 1 4.61 0.23 0.30 1.27
" " C6 to C7, C5 to C12, C4
to C8
3 x 1 x 1 3.60
0.23 0.30 0.75
" " C13 to C14 1 x 1 x 1 6.27
0.23 0.30 0.43
B4 type Beams C3 to C6, C2 to C5, C1
to C4
3 x 1 x 1 5.63
0.23 0.30 1.17
" " C1 to C4, C4 to C5 2 x 1 x 1 6.27
0.23 0.30 0.87
" " C9 to C11/12 1 x 1 x 1 4.09
0.23 0.30 0.28
B5 type Beams C15 to C12 1 x 1 x 1 7.17
0.23 0.30 0.49
" " C12 to C11 & 14 1 x 1 x 1 6.50
0.23 0.30 0.45
B6 type Beams C15 to C13, C7 to C10 1 x 1 x 1 6.50
0.23 0.30 0.45
CB type Beam 1 1 x 1 x 1 2.33
0.23 0.30 0.16
CB type Beam 2 1 x 1 x 1 1.80
0.23 0.30 0.12
Total in Cu.Mt :: 6.44 Cu.Mt 14987.79 1 Cu.Mt 96521.37
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Roof Slab 125mm thick.

Main Slab 1 x 1 x 1 16.30


11.05 180.12
At Stair case Landing 1 x 1 x 1 1.20
0.90 1.08
Total in Sq.Mt :: 181.20 Sq.Mt 1711.91 1 Sq.Mt 310198.09
9) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Stair case II nd Flight.

Stair case II nd flight


1 x 1 x 1 2.30 1.20 - 2.76
Total in Sq.Mt :: 2.76 Sq.Mt 1711.91 1 Sq.Mt 4724.87
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
10) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3),
promixed with 1kg of water proof compound per bag of cement laid over roof
when it is green including cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all operational, incidental and
labour charges for mixing mortar, laying, rendering smooth and thread lining,
curing, rounding off junctions of wall and slab etc,, complete for finished item
of work.
Main Slab 1 x 1 x 1 16.30 11.05 180.12
Total in Sq.Mt :: 180.12 Sq.Mt 580.98 1 Sq.Mt 104646.12
11) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion (cement:
fine aggregate: Coarse aggregate) using 40mm, 20mm, 10mm size Hard
Broken Granite (IS383, 1970) Machine Crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as
mixing concrete in Concrete Mixer, laying, curing concrete, etc., complete for
finished item of work (APSS No. 402) Steps.
I st Flight 1 x 15 1.20 0.28 (0+0.15)/2 0.38
II nd Flight 1 x 7 1.20 0.28 (0+0.15)/2 0.18
Total in Cu.Mt :: 0.56 Cu.Mt 6143.87 1 Cu.Mt 3440.57
Total : 1020426.75
12) Sanitory Charges 6% on total Cost 61225.61
13) Electrification Charges 7% on total Cost 71429.87
Total:- 1153082.23
III rd Part Bill
Name of the work : Construction of Forest Range Officer Quarter at Tekulapally of Tekulapally
Range of Kothagudem Division, Bhadradri Kothagudem District, during 2022-23 under CAMPA -
NPV scheme.
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks
of size 23 x 11 x 7 Cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour charges such
as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.

9" Brick wall


C1 to C2 1 x 1 x 1 5.15 0.23 2.21 2.62
C2 to C3 1 x 1 x 1 3.50 0.23 2.21 1.78
C3 to C6 1 x 1 x 1 4.45 0.23 2.21 2.26
C6 to C7 1 x 1 x 1 3.27 0.23 2.21 1.66
C7 to C10 1 x 1 x 1 5.32 0.23 2.21 2.70
C10 to C11 1 x 1 x 1 3.43 0.23 2.21 1.74
C11 to C9# 1 x 1 x 1 1.31 0.23 2.21 0.67
C9 to C9# 1 x 1 x 1 3.86 0.23 2.21 1.96
C9 to C8/12 1 x 1 x 1 4.01 0.23 2.21 2.04
C8 to C8# 1 x 1 x 1 1.16 0.23 2.21 0.59
C4 to C8 1 x 1 x 1 3.27 0.23 2.21 1.66
C1 to C4 1 x 1 x 1 4.40 0.23 2.21 2.24
Stair case Toilet L/w 1 x 2 x 1 1.50 0.23 2.21 1.52
C/w 1 x 2 x 1 1.20 0.23 2.21 1.22
Deductions :
Main Door D1 -1 x 1 x 1 0.90 0.23 2.10 -0.43
D2 -1 x 1 x 1 0.80 0.23 2.10 -0.39
Windows W1 -1 x 3 x 1 2.10 0.23 1.35 -1.96
W2 -1 x 3 x 1 1.50 0.23 1.35 -1.40
W3 -1 x 2 x 1 1.20 0.23 1.35 -0.75
KW1 -1 x 1 x 1 1.50 0.23 1.05 -0.36
KW2 -1 x 1 x 1 1.20 0.23 1.05 -0.29
Total in Cu.Mt :: 19.08 Cu.Mt 8125.30 1 Cu.Mt 155030.72
11) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks
of size 23 x 11 x 7 Cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour charges such
as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.

4.5" Brick wall


Hall L/w 1 x 1 x 1 7.61 0.12 2.21 2.02
Extra Bed Room L/w 1 x 1 x 1 3.60 0.12 2.21 0.95
Bed Room I L/w 1 x 2 x 1 3.60 0.12 2.21 1.91
Toilet C/w 1 x 1 x 1 1.35 0.12 2.21 0.36
Bed Room II L/w 1 x 1 x 1 4.75 0.12 2.21 1.26
C/w 1 x 1 x 1 3.85 0.12 2.21 1.02
Pooja C/w 1 x 1 x 1 1.22 0.12 2.21 0.32
Kitchen L/w 1 x 1 x 1 3.15 0.12 2.21 0.84
C/w 1 x 1 x 1 3.35 0.12 2.21 0.89
Toilet 1 C/w 1 x 1 x 1 1.22 0.12 2.21 0.32
Parapet wall L/w 1 x 2 x 1 16.30 0.12 0.80 3.13
C/w 1 x 2 x 1 11.05 0.12 0.80 2.12
at Stair case I st Flight 1 x 2 x 1 5.10 0.12 0.80 0.98
II nd Flight 1 x 2 x 1 2.30 0.12 0.80 0.44
at Landing 1 x 1 x 1 2.30 0.12 0.80 0.22
at Landing 1 x 1 x 1 1.90 0.12 0.80 0.18
Deductions :
Doors D1 -1 x 4 x 1 0.90 0.23 2.10 -1.74
Doors D2 -1 x 1 x 1 0.85 0.23 2.00 -0.39
Doors D3 -1 x 3 x 1 0.75 0.23 2.00 -1.04
Total in Cu.Mt :: 13.79 Cu.Mt 8125.30 1 Cu.Mt 112047.89
13) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Lintels
Main door D1 10mm dia 5 x 4 x 1 1.60 0.62 19.84
Stirrups 8mm dia 1 x 1 x 11 0.65 0.39 2.79
D2 door 10mm dia 2 x 4 x 1 1.50 0.62 7.44
Stirrups 8mm dia 2 x 1 x 10 0.65 0.39 5.07
On Windows W1 10 mm 3 x 4 x 1 2.90 0.62 21.58
Stirrups 8mm dia 3 x 1 x 19 0.65 0.39 14.45
On Windows W2 10 mm 3 x 4 x 1 2.20 0.62 16.37
Stirrups 8mm dia 3 x 1 x 15 0.62 0.39 10.88
On Windows W3 10 mm 2 x 4 x 1 1.90 0.62 9.42
Stirrups 8mm dia 2 x 1 x 13 0.65 0.39 6.59
On Windows KW1 10 mm 1 x 4 x 1 2.20 0.62 5.46
Stirrups 8mm dia 1 x 1 x 15 0.65 0.39 3.80
On Windows KW2 10 mm 1 x 4 x 1 1.90 0.62 4.71
Stirrups 8mm dia 1 x 1 x 13 0.65 0.39 3.30
Sunshades
On Windows W1 8 mm Long 3 x 4 x 1 2.70 0.39 12.64
Short 3 x 18 x 1 0.60 0.39 12.64
On Windows W2 8 mm Long 3 x 4 x 1 1.90 0.39 8.89
Short 3 x 13 x 1 0.60 0.39 9.13
On Windows W3 8 mm Long 2 x 4 x 1 1.70 0.39 5.30
Short 2 x 11 x 1 0.60 0.39 5.15
On Windows Kw1 8 mm Long 1 x 4 x 1 1.90 0.39 2.96
Short 1 x 13 x 1 0.60 0.39 3.04
On Windows Kw2 8 mm Long 1 x 4 x 1 1.70 0.39 2.65
Short 1 x 11 x 1 0.60 0.39 2.57
196.67 Kg 92.750 1 Kg 18241.14
14) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Lintels.

On D1 1 x 5 x 1 1.50 0.23 0.15 0.26


On D2 1 x 2 x 1 1.40 0.23 0.15 0.10
On D3 1 x 3 x 1 1.30 0.23 0.15 0.13
Windows W1 1 x 3 x 1 2.70 0.23 0.15 0.28
Windows W2 1 x 4 x 1 2.10 0.23 0.15 0.29
Windows W3 1 x 3 x 1 2.00 0.12 0.15 0.11
Total in Cu.Mt :: 1.17 Cu.Mt 15224.60 1 Cu.Mt 17812.78
15) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Sunshades.

On Windows W1 1 x 3 x 1 2.70 0.60 - 4.86


1 x 4 x 1 2.10 0.60 - 5.04
1 x 3 x 1 2.00 0.60 - 3.60
Total in Sq.Mt :: 13.50 Sq.Mt 1464.581 1 Sq.Mt 19771.84
16) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks
of size 23 x 11 x 7 Cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour charges such
as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.

9" Brick wall


C1 to C2 1 x 1 x 1 5.15 0.23 0.90 1.07
C2 to C3 1 x 1 x 1 3.50 0.23 0.90 0.72
C3 to C6 1 x 1 x 1 4.45 0.23 0.90 0.92
C6 to C7 1 x 1 x 1 3.27 0.23 0.90 0.68
C7 to C10 1 x 1 x 1 5.32 0.23 0.90 1.10
C10 to C11 1 x 1 x 1 3.43 0.23 0.90 0.71
C11 to C9# 1 x 1 x 1 1.31 0.23 0.90 0.27
C9 to C9# 1 x 1 x 1 3.86 0.23 0.90 0.80
C9 to C8/12 1 x 1 x 1 4.01 0.23 0.90 0.83
C8 to C8# 1 x 1 x 1 1.16 0.23 0.90 0.24
C4 to C8 1 x 1 x 1 3.27 0.23 0.90 0.68
C1 to C4 1 x 1 x 1 4.40 0.23 0.90 0.91
Stair case Toilet L/w 1 x 2 x 1 1.50 0.23 0.90 0.62
C/w 1 x 2 x 1 1.20 0.23 0.90 0.50
Deductions :
Ventilators -1 x 2 x 1 0.90 0.23 0.60 -0.25
Lintels On D1 -1 x 5 x 1 1.50 0.23 0.15 -0.26
" On D2 -1 x 2 x 1 1.40 0.23 0.15 -0.10
" On D3 -1 x 3 x 1 1.30 0.23 0.15 -0.13
" W1 -1 x 3 x 1 2.70 0.23 0.15 -0.28
" W2 -1 x 4 x 1 2.10 0.23 0.15 -0.29
" W3 -1 x 3 x 1 2.00 0.23 0.15 -0.21
Total in Cu.Mt :: 8.53 Cu.Mt 8125.30 1 Cu.Mt 69308.81
17) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks
of size 23 x 11 x 7 Cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour charges such
as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.

4.5" Brick wall


Hall L/w 1 x 1 x 1 7.61 0.12 0.90 0.82
Extra Bed Room L/w 1 x 1 x 1 3.60 0.12 0.90 0.39
Bed Room I L/w 1 x 2 x 1 3.60 0.12 0.90 0.78
Toilet C/w 1 x 1 x 1 1.35 0.12 0.90 0.15
Bed Room II L/w 1 x 1 x 1 4.75 0.12 0.90 0.51
C/w 1 x 1 x 1 3.85 0.12 0.90 0.42
Pooja C/w 1 x 1 x 1 1.22 0.12 0.90 0.13
Kitchen L/w 1 x 1 x 1 3.15 0.12 0.90 0.34
C/w 1 x 1 x 1 3.35 0.12 0.90 0.36
Toilet 1 C/w 1 x 1 x 1 1.22 0.12 0.90 0.13
Parapet wall L/w 1 x 2 x 1 16.30 0.12 0.90 3.52
C/w 1 x 2 x 1 11.05 0.12 0.90 2.39
at Stair case I st Flight 1 x 2 x 1 5.10 0.12 0.90 1.10
II nd Flight 1 x 2 x 1 2.30 0.12 0.80 0.44
at Landing 1 x 1 x 1 2.30 0.12 0.80 0.22
at Landing 1 x 1 x 1 1.90 0.12 0.80 0.18
Deductions :
Lintels on Doors D1 -1 x 4 x 1 1.50 0.12 0.15 -0.10
D2 -1 x 3 x 1 1.40 0.12 0.15 -0.08
Total in Cu.Mt :: 11.70 Cu.Mt 8125.30 1 Cu.Mt 95066.01
18) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20
B (APSS 308). for building foundation.

F/s Steps 1 x 1 5.80 0.90 0.30 1.56


1 x 1 2.80 0.90 0.30 0.75
Total in Cu.Mt :: 2.31 Cu.Mt 430.10 1 Cu.Mt 993.53
19) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

PCC Under Steps 1 x 1 5.80 0.90 0.15 0.78


1 x 1 2.80 0.90 0.15 0.37
Total in Cu.Mt :: 1.15 Cu.Mt 5679.31 1 Cu.Mt 6531.21
20) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks
of size 23 x 11 x 7 Cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour charges such
as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.

9" Brick wall


Front Steps Step I 1 x 1 x 1 5.80 0.90 0.20 1.04
Step II 1 x 1 x 1 5.80 0.60 0.20 0.70
Step III 1 x 1 x 1 5.80 0.30 0.20 1.16
Step I 1 x 1 x 1 2.80 0.60 0.20 0.56
Step II 1 x 1 x 1 2.80 0.30 0.20 0.56
Total in Cu.Mt :: 4.02 Cu.Mt 8125.30 1 Cu.Mt 32663.71
21) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh &
nominal reinforcement as directed by Engineer-in-charge with dubara sponge
finishing, including cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational & incidental, cost and
conveyance of cement, wire mesh, water to work site, centering, scaffolding
and form work, lift charges etc., complete for finished items of work but
excluding cost of steel & its fabrication charges, for finished item of work.
(APSS No.403&903).
1 x 2 x 1 16.30 - 0.45 14.67
1 x 2 x 1 11.05 - 0.45 9.94
Total in Sq.Mt :: 24.61 Sq.Mt 2336.07 1 Sq.Mt 57490.68
22) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong finish
including cost and conveyance of all materials like cement, sand, water etc., to
site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing mortar,
finishing, curing, etc., complete for finished item of work. (APSS 901,906).

Slab Projection Sides 1 x 2 x 1 16.300.90 - 29.34


F/s & B/s 1 x 2 x 1 11.050.90 - 19.89
Stair case Bottom 1 x 1 x 1 5.30 1.20 - 6.36
" 1 x 1 x 1 2.60 1.20 - 3.12
Mid Landing 1 x 1 x 1 2.50 1.20 - 3.00
Window Sunshades W3 1 x 3 x 1 2.10 0.60 - 3.78
W2 1 x 3 x 1 1.50 0.60 - 2.70
W1 1 x 2 x 1 1.40 0.60 - 1.68
K W1 1 x 1 x 1 1.50 0.60 - 0.90
K W2 1 x 1 x 1 1.40 0.60 - 0.84
Varandah 1 x 1 x 1 6.27 2.33 - 14.60
1 x 1 x 1 4.13 2.18 - 9.00
Beam sides R/s 1 x 4 x 2 0.90 0.30 - 2.16
" Bottom 1 x 4 x 2 0.90 0.30 - 2.16
Beam sides L/s 1 x 5 x 2 0.90 0.30 - 2.70
" Bottom 1 x 5 x 2 0.90 0.30 - 2.70
Total in Sq.Mt :: 104.93 Sq.Mt 179.53 1 Sq.Mt 18838.08
23) Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6)
and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, screened sand, water etc., to site,
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar,scaffolding charges, lift
charges, finishing,including cutting of Grooves wherever necessary as directed
by Engineer - in - charge, curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903 & 904).

West side wall 1 x 1 x 1 9.65 - 1.20 11.58


South side wall 1 x 1 x 1 14.20 - 1.20 17.04
East side walls 1 x 1 x 1 3.94 - 1.20 4.72
" " 1 x 1 x 1 1.15 - 1.20 1.38
" " 1 x 1 x 1 6.50 - 3.30 21.45
North side walls 1 x 1 x 1 8.56 - 1.20 10.27
" " 1 x 1 x 1 0.90 - 1.20 1.08
" " 1 x 1 x 1 6.73 - 3.30 22.20
For Steps Top 1 x 1 x 3 6.70 - 0.30 6.03
Side 1 x 1 x 3 6.70 0.20 - 4.02
For Steps Top 1 x 1 x 3 6.50 - 0.30 5.85
Side 1 x 1 x 3 6.50 0.20 - 3.90
Stair case steps 1 x 15 x 1 1.20 0.28 - 5.04
1 x 7 x 1 1.20 0.28 - 2.35
Total in Sq.Mt :: 116.91 Sq.Mt 532.53 1 Sq.Mt 62258.08
24) Plastering 12mm thick in two coats with base coat of 9mm thick in CM (1:6)
and top coat of 3mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, screened sand, water etc., to site,
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar, scaffolding charges, lift
charges, finishing, including cutting of Grooves wherever necessary as directed
by Engineer - in - charge, curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903 & 904).

A) Internal 9" brick walls :


Hall Living area 1 x 1 x 1 3.87 - 3.30 12.77
Dinning Area 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I C/w 1 x 1 x 1 3.83 - 3.30 12.63
L/w 1 x 1 x 1 4.50 - 3.30 14.85
Kitchen Room C/w 1 x 1 x 1 3.15 - 3.30 10.39
Kitchen Room Long wall 1 x 1 x 1 3.32 - 3.30 10.95
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.85 - 3.30 12.70
Pooja Room C/w 1 x 1 x 1 1.35 - 3.30 4.45
Toilet I 1 x 1 x 1 1.25 - 3.30 4.12
Toilet II 1 x 1 x 1 1.35 - 3.30 4.45
Out side Toilet 1 x 2 x 1 1.50 - 2.20 6.60
1 x 2 x 1 1.20 - 2.20 5.28
Window offsets 1 x 3 x 2 2.10 - 0.15 1.89
1 x 3 x 2 1.35 - 0.15 1.21
1 x 4 x 2 1.50 - 0.15 1.80
1 x 4 x 2 0.35 - 0.15 0.42
1 x 3 x 2 1.20 - 0.15 1.08
1 x 3 x 2 0.35 - 0.15 0.31
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 7.61 - 3.30 25.11
Deduction Toilet Open 1 x -1 x 1 1.35 - 3.30 -4.45
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 1 1.22 - 3.30 4.02
Kitchen Room Short wall 1 x 1 x 1 3.15 - 3.30 10.39
Kitchen Room Long wall 1 x 1 x 1 3.32 - 3.30 10.95
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.72 - 3.30 12.27
Bed Room I Short walls 1 x 1 x 1 3.83 - 3.30 12.63
Bed Room I Long walls 1 x 1 x 1 4.50 - 3.30 14.85
Toilet 1 Long walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 1 Short walls 1 x 1 x 1 1.20 - 3.30 3.96
Toilet 2 Long walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Short walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 2 Front area 1 x 1 x 1 1.35 - 3.30 4.45
1 x 1 x 1 1.20 - 3.30 3.96
335.21 Sq.Mt 515.22 1 Sq.Mt 172706.90
C) External 9" brick walls :
West side wall 1 x 1 x 1 9.65 - 3.30 31.84
South side wall 1 x 1 x 1 14.20 - 3.30 46.86
East side walls 1 x 1 x 1 3.94 - 3.30 13.00
" " 1 x 1 x 1 1.15 - 3.30 3.79
" " 1 x 1 x 1 6.50 - 3.30 21.45
North side walls 1 x 1 x 1 8.56 - 3.30 28.24
" " 1 x 1 x 1 0.90 - 3.30 2.97
" " 1 x 1 x 1 6.73 - 3.30 22.20
Stair case walls 1 x 2 x 2 5.30 - 0.90 19.08
" " 1 x 2 x 2 2.30 - 0.90 8.28
'' '' 1 x 1 x 2 2.50 - 0.90 4.50
Parapet wall L/w 1 x 2 x 2 16.30 - 1.45 94.54
1 x 2 x 2 11.05 - 1.45 64.09
360.84 Sq.Mt 515.22 1 Sq.Mt 185911.98
25) Supplying and fixing of false ceiling using Plaster of Paris Boards 12 mm thick
with standard GI ceiling angles, sections perimeter channels including cost and
conveyance of all materials and labour charges etc complete.
Hall 1 x 1 x 1 7.61 3.87 - 29.45
1 x 1 x 1 3.60 1.20 - 4.32
Extra Bed Room 1 x 1 x 1 3.60 3.83 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 4.50 - 17.23
Bed Room II 1 x 1 x 1 3.60 3.60 - 12.96
Toilet Front 1 x 1 x 1 2.10 1.40 - 2.94
Pooja Room 1 x 1 x 1 1.80 1.35 - 2.43
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 3.32 3.15 - 10.45
Total in Sq.Mt :: 97.13 Sq.Mt 454.46 1 Sq.Mt 44141.70

Total : 1068815.06
26) Sanitory Charges 7% on total Cost Since first bill 74817.05
27) Electrification Charges 6% on total Cost Since first bill 64128.90
Total:- 1207761.01
IV th & Part Bill
Name of the work : Construction of Forest Range Officer Quarter at Tekulapally of Tekulapally Range of
Kothagudem Division, Bhadradri Kothagudem District, during 2022-23 under CAMPA - NPV scheme.
Sl. Measurements
Description of Item No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. Shelves 50mm thick.

In Kitchen 1 x 1 x 1 1.80 0.30 - 0.54


1 x 1 x 1 1.60 0.30 - 0.48
Pooja Room 1 x 1 x 1 1.20 0.30 - 0.36
Hall 1 x 3 x 1 1.80 0.30 - 1.62
Bed Room 1 & 2 L/w 1 x 3 x 1 1.80 0.30 - 1.62
C/w 1 x 3 x 1 2.10 0.30 - 1.89
Total in Sq.Mt :: 6.51 Sq.Mt 635.00 1 Sq.Mt 4133.85
2) Flooring with adanga Marbles of I st quality of size not exceeding 0.457 x
0.457m laid over CC Flooring bed set over 20mm thcik CM(1:8) drop kase coat
and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site,
seigniorage charges, sales and other taxes on all materials, and all opertional,
incidental and all labour charges such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete for finished item of work in all floors.

Hall 1 x 1 x 1 7.61 3.87 - 29.45


1 x 1 x 1 3.60 1.20 - 4.32
Extra Bed Room 1 x 1 x 1 3.60 3.83 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 4.50 - 17.23
Bed Room II 1 x 1 x 1 3.60 3.60 - 12.96
Toilet Front 1 x 1 x 1 2.10 1.40 - 2.94
Pooja Room 1 x 1 x 1 1.80 1.35 - 2.43
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 3.32 3.15 - 10.45
Varandah 1 x 1 x 1 6.27 2.33 - 14.60
1 x 1 x 1 4.13 2.18 - 9.00
Total in Sq.Mt :: 120.73 Sq.Mt 1003.20 1 Sq.Mt 121116.34
Skirting
Hall Living area 1 x 1 x 2 (7.61+3.87) 0.10 2.29
Extra Bed Room 1 x 1 x 2 (3.60+3.83) 0.10 1.48
Toilet Front 1 x 1 x 2 (1.35+1.45) 0.10 0.56
Bed Room I 1 x 1 x 2 (3.83+4.50) 0.10 1.66
Bed Room II 1 x 1 x 2 (3.30+3.60) 0.10 1.38
Kitchen 1 x 1 x 2 (3.32+3.15) 0.10 1.29
Pooja Room 1 x 1 x 2 (1.80+1.35) 0.10 0.63
" " Front 1 x 1 x 2 (1.35+1.20) 0.10 0.51
Varandah 1 x 1 x 1 (6.27+2.33) 0.10 62.94
Total in Sq.Mt :: 72.74 Sq.Mt 696.83 1 Sq.Mt 50687.41
3) Providing and fixing non skid ceramic tiles for flooring over and inclusive of
20mm thick base plaster in cement morter 1:5 (1 cement : 5 coarse sand)
including a floating cement slurry including grouting/ filling the joints with white
cement slurry mixed with matching, pigment, curing, cleaning and
leaving/making necessary holes for sanitory connection complete but including
cost of cement and tiles in all heights/level for skirting complete for finished
item of work.
Toilet 1 1 x 1 x 1 2.40 1.35 - 3.24
Toilet 2 1 x 1 x 1 2.70 1.50 - 4.05
Stair case Toilet 1 x 1 x 1 2.20 1.35 - 2.97
Total in Sq.Mt :: 10.26 Sq.Mt 935.75 1 Sq.Mt 9600.80
4) Dadooing to walls with glazed red or white full body ceramic wall tiles of size
200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality conforming
to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and designs, any brand as approved by Engineer - in - charge and set
over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of
3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of
matching shade including cost and conveyance of all materials like cement,
sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all
materials, and all opertional, incidental and all labour charges such as mixing of
cement mortar, laying in position, curing, lift charges etc., complete for finished
item of work in all floors

Toilet 1 1 x 1 x 1 (2.40+1.35) 2.10 7.87


Toilet 2 1 x 1 x 1 (2.70+1.50) 2.10 8.82
Stair case Toilet 1 x 1 x 1 (2.20+1.35) 2.10 7.45
Total in Sq.Mt :: 24.14 Sq.Mt 946.72 1 Sq.Mt 22853.82
5) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base coat of
approved cement primer grade II exterior making three coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and remains
of loose powdered materials, including cost and conveyance of all materials,
cost of brushes, water to site, etc., sales & other taxes, all operational,
incidental, labour charges etc. complete for finished item of work as per SS 912
for internal walls.
Ceiling :
Hall 1 x 1 x 1 7.61 3.87 - 29.45
1 x 1 x 1 3.60 1.20 - 4.32
Extra Bed Room 1 x 1 x 1 3.60 3.83 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 4.50 - 17.23
Bed Room II 1 x 1 x 1 3.60 3.60 - 12.96
Toilet Front 1 x 1 x 1 2.10 1.40 - 2.94
Pooja Room 1 x 1 x 1 1.80 1.35 - 2.43
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 3.32 3.15 - 10.45
Slab Projection Sides 1 x 2 x 1 16.30 0.90 - 29.34
F/s & B/s 1 x 2 x 1 11.05 0.90 - 19.89
Stair case Bottom 1 x 1 x 1 5.30 1.20 - 6.36
" 1 x 1 x 1 2.60 1.20 - 3.12
Mid Landing 1 x 1 x 1 2.50 1.20 - 3.00
Window Sunshades W3 1 x 3 x 1 2.10 0.60 - 3.78
W2 1 x 3 x 1 1.50 0.60 - 2.70
W1 1 x 2 x 1 1.40 0.60 - 1.68
K W1 1 x 1 x 1 1.50 0.60 - 0.90
K W2 1 x 1 x 1 1.40 0.60 - 0.84
Varandah 1 x 1 x 1 6.27 2.33 - 14.60
1 x 1 x 1 4.13 2.18 - 9.00
Beam sides R/s 1 x 4 x 2 0.90 0.30 - 2.16
" Bottom 1 x 4 x 2 0.90 0.30 - 2.16
Beam sides L/s 1 x 5 x 2 0.90 0.30 - 2.70
" Bottom 1 x 5 x 2 0.90 0.30 - 2.70
Total in Sq.Mt :: 202.06 Sq.Mt 260.55 1 Sq.Mt 52646.73
6) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base coat of
approved cement primer grade II exterior making three coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and remains
of loose powdered materials, including cost and conveyance of all materials,
cost of brushes, water to site, etc., sales & other taxes, all operational,
incidental, labour charges etc. complete for finished item of work as per SS 912
for internal walls.
A) Internal 9" brick walls :
Hall Living area 1 x 1 x 1 3.87 - 3.30 12.77
Dinning Area 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I C/w 1 x 1 x 1 3.83 - 3.30 12.63
L/w 1 x 1 x 1 4.50 - 3.30 14.85
Kitchen Room C/w 1 x 1 x 1 3.15 - 3.30 10.39
Kitchen Room Long wall 1 x 1 x 1 3.32 - 3.30 10.95
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.85 - 3.30 12.70
Pooja Room C/w 1 x 1 x 1 1.35 - 3.30 4.45
Toilet I 1 x 1 x 1 1.25 - 3.30 4.12
Toilet II 1 x 1 x 1 1.35 - 3.30 4.45
Out side Toilet 1 x 2 x 1 1.50 - 2.20 6.60
1 x 2 x 1 1.20 - 2.20 5.28
Window offsets 1 x 3 x 2 2.10 - 0.15 1.89
1 x 3 x 2 1.35 - 0.15 1.21
1 x 4 x 2 1.50 - 0.15 1.80
1 x 4 x 2 0.35 - 0.15 0.42
1 x 3 x 2 1.20 - 0.15 1.08
1 x 3 x 2 0.35 - 0.15 0.31
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 7.61 - 3.30 25.11
Deduction Toilet Open 1 x -1 x 1 1.35 - 3.30 -4.45
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 1 1.22 - 3.30 4.02
Kitchen Room Short wall 1 x 1 x 1 3.15 - 3.30 10.39
Kitchen Room Long wall 1 x 1 x 1 3.32 - 3.30 10.95
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.72 - 3.30 12.27
Bed Room I Short walls 1 x 1 x 1 3.83 - 3.30 12.63
Bed Room I Long walls 1 x 1 x 1 4.50 - 3.30 14.85
Toilet 1 Long walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 1 Short walls 1 x 1 x 1 1.20 - 3.30 3.96
Toilet 2 Long walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Short walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 2 Front area 1 x 1 x 1 1.35 - 3.30 4.45
1 x 1 x 1 1.20 - 3.30 3.96
335.21 Sq.Mt 146.73 1 Sq.Mt 49185.36
C) External 9" brick walls :
Basement
West side wall 1 x 1 x 1 9.65 - 1.20 11.58
South side wall 1 x 1 x 1 14.20 - 1.20 17.04
East side walls 1 x 1 x 1 3.94 - 1.20 4.72
" " 1 x 1 x 1 1.15 - 1.20 1.38
" " 1 x 1 x 1 6.50 - 1.20 7.80
North side walls 1 x 1 x 1 8.56 - 1.20 10.27
" " 1 x 1 x 1 0.90 - 1.20 1.08
" " 1 x 1 x 1 6.73 - 1.20 8.07
West side wall 1 x 1 x 1 9.65 - 3.30 31.84
South side wall 1 x 1 x 1 14.20 - 3.30 46.86
East side walls 1 x 1 x 1 3.94 - 3.30 13.00
" " 1 x 1 x 1 1.15 - 3.30 3.79
" " 1 x 1 x 1 6.50 - 3.30 21.45
North side walls 1 x 1 x 1 8.56 - 3.30 28.24
" " 1 x 1 x 1 0.90 - 3.30 2.97
" " 1 x 1 x 1 6.73 - 3.30 22.20
Stair case walls 1 x 2 x 2 5.30 - 0.90 19.08
" " 1 x 2 x 2 2.30 - 0.90 8.28
'' '' 1 x 1 x 2 2.50 - 0.90 4.50
Parapet wall L/w 1 x 2 x 2 16.30 - 1.45 94.54
1 x 2 x 2 11.05 - 1.45 64.09
422.78 Sq.Mt 146.73 1 Sq.Mt 62034.51
7) Timber shall be of the kind as specified, may be teak, shisham, sal, deodar,etc.,
the timber shall be of best quality, well seasoned and free from sap knots,
warps, cracks and other defects, all wood work shall be planed and neatly and
truly finished to the exact dimensions. all joints be neat and strong, truly and
accurately fitted and glued before being fitted together. Chunkhats : The
Chunkhats shall be formed and joined by motise and tenon joint with head
wooden pins and the joints shall be of coated with white lead before being fitted
together.
1 x 5 0.90 - 2.10 9.45
1 x 2 0.85 - 2.10 3.57
Total in Sq.Mt :: 13.02 Each 15254.00 1 Each 198607.08
8) Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm
for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat
of steel primers of approved make and manufacture. M.S. frame shall be
covered with 5mm thick heat molded PVC ‘C’ channel of size 30 x 50mm forming
stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail
on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap
insert for top rail & bottom rail. Paneling of 5mm thick PVC sheet to be fitted in
the M.S. frame welded / sealed to the stiles & rails with 30mm wide x 5mm
thick PVC sheet beading on either side, and joined together with solvent cement
adhesive etc. An additional 5mm thick PVC strip of 20mm width is to be stuck
on the interior side of the ‘C’ Channel using PVC solvent adhesive. Complete as
per direction of Engineer-in-charge, manufacturer’s specification & drawing for
finished item of work.

Toilet doors 1 x 3 0.75 - 1.90 4.28


Total in Sq.Mt :: 4.28 Sq.Mt 2618.00 1 Sq.Mt 11205.04
9) Supplying and fixing fully glazed anodized aluminium hinged type window with
fan light as per drawing using standard outer frame 38.5x33x21x2.5mm thick
and central mullion of size 59(3mm)x33(4mm)x21(3mm) using 5mm thick, glass
fitted with suitable aluminium glazing clips and rubber beading including
supplying and fixing friction hinges (2np.s per shutter), handle with lock(1 no.
per shutter), incl cost and conveyance to site of aluminium sections, glass
rubber beading, fixtures etc., including labour charges for manufacturing
window, fixing in position using wooden blocks and sheet metalscrews etc.,
complete for finished item of work.

W1 1 x 3 2.10 - 1.35 8.50


W2 1 x 3 1.50 - 1.35 6.07
W3 1 x 2 1.40 - 1.35 3.78
Kw1 1 x 1 1.50 - 0.90 1.35
Kw2 1 x 1 1.20 - 0.90 1.08
V1 & V2 1 x 2 0.60 - 0.30 0.36
Total in Sq.Mt :: 21.14 Sq.Mt 7485.00 1 Sq.Mt 158232.90
10) Painting to New wood work with two coats of ready mixed Synthetic Enamel
paints in all shades Grade - I having VOC (Volatile Organic Compound) content
less than 50 grams/ liter first quality all shades to give an even shade over base
coatof wood Primer finishing with putty for wood work after thouroughly
brushing the surface to remove all remains including cost and conveyance of all
materials to site, sales & other taxes, all operational, incidental and labour
charges etc., complete for finished item of work.(3 coats) (APSS No. 1201 &
1212).in All Floors
1 x 5 0.90 - 2.10 9.45
1 x 2 0.85 - 2.10 3.57
Total in Sq.Mt :: 13.02 Sq.Mt 2227.29 1 Sq.Mt 28999.32
11) Supply and fixing of M.S.Grill of size with outer angular frame of rolled steel of
ISA 2525 of size 25mm x 25mm x 4mm welded with safety bars of 45 x 25mm
Square pipes at 150mm centre to centre horizontally and verticlally including red
oxide primer of grade-I quality, sales and other taxes, cost and conveyance of
all materials to site, all labour charges and fixing in position etc., complete for
finished item of work.
W1 1 x 3 2.10 - 1.35 8.50
W2 1 x 3 1.50 - 1.35 6.07
W3 1 x 2 1.40 - 1.35 3.78
Kw1 1 x 1 1.50 - 0.90 1.35
Kw2 1 x 1 1.20 - 0.90 1.08
Total in Sq.Mt :: 20.78 Sq.Mt 2500.00 1 Sq.Mt 51950.00

Total : 821253.16
12) Sanitory Charges 7% on total Cost Since first bill 57487.72
13) Electrification Charges 6% on total Cost Since first bill 49275.19
Total:- 928016.07

You might also like