Project Name: 479-16 Quran Memorization center AWQAF-20230129 02/14/2023
Prepared by: APG 04:34PM
Air System Information
Air System Name GR-AHU-01 Number of zones 3 Equipment Class CW AHU Floor Area 835.0 m² Air System Type VAV Location Doha, Qatar
Sizing Calculation Information
Calculation Months Jan to Dec Zone L/s Sizing Peak zone sensible load Sizing Data Calculated Space L/s Sizing Individual peak space loads
Central Cooling Coil Sizing Data
Total coil load 93.7 kW Load occurs at Jul 0900 Sensible coil load 86.8 kW OA DB / WB 38.9 / 28.5 °C Coil L/s at Jul 0900 5515 L/s Entering DB / WB 22.7 / 14.7 °C Max block L/s at Jul 0900 6056 L/s Leaving DB / WB 9.6 / 8.9 °C Sum of peak zone L/s 6094 L/s Coil ADP 8.2 °C Sensible heat ratio 0.926 Bypass Factor 0.100 m²/kW 8.9 Resulting RH 45 % W/m² 112.3 Design supply temp. 12.0 °C Water flow @ 5.6 °K rise 4.04 L/s Zone T-stat Check 3 of 3 OK Max zone temperature deviation 0.0 °K
Supply Fan Sizing Data
Actual max L/s at Jul 0900 6056 L/s Fan motor BHP n/a Standard L/s 6049 L/s Fan motor kW 13.67 kW Actual max L/(s-m²) 7.25 L/(s-m²)
Zone Sizing Summary for GR-AHU-01 Project Name: 479-16 Quran Memorization center AWQAF-20230129 02/14/2023 Prepared by: APG 04:34PM
Air System Information
Air System Name GR-AHU-01 Number of zones 3 Equipment Class CW AHU Floor Area 835.0 m² Air System Type VAV Location Doha, Qatar
Sizing Calculation Information
Calculation Months Jan to Dec Zone L/s Sizing Peak zone sensible load Sizing Data Calculated Space L/s Sizing Individual peak space loads
Zone Sizing Data
Maximum Maximum Zone
Cooling Design Minimum Heating Floor Sensible Airflow Airflow Time of Load Area Zone Zone Name (kW) (L/s) (L/s) Peak Load (kW) (m²) L/(s-m²) G-RECEPTION HALL 36.7 3383 380 Jul 0900 4.1 400.0 8.46 G-TOILET 05 1.3 82 1 Jan 2300 0.0 43.0 1.90 G-MULTI PURPOSE HALL 27.2 2508 530 Jul 2000 3.5 392.0 6.40
Zone Terminal Sizing Data
Reheat Zone Zone
Reheat Coil Htg Htg Mixing Coil Water Coil Water Box Fan Load L/s Load L/s Airflow Zone Name (kW) @ 11.1 °K (kW) @ 11.1 °K (L/s) G-RECEPTION HALL 7.3 0.16 0.0 0.00 0 G-TOILET 05 0.0 0.00 0.0 0.00 0 G-MULTI PURPOSE HALL 8.0 0.17 0.0 0.00 0
Space Loads and Airflows
Cooling Time Air Heating Floor
Zone Name / Sensible of Flow Load Area Space Space Name Mult. (kW) Load (L/s) (kW) (m²) L/(s-m²) G-RECEPTION HALL G-RECEPTION HALL 1 36.7 Jul 0900 3383 4.1 400.0 8.46 G-TOILET 05 G-TOILET 05 1 1.3 Jan 2300 82 0.0 43.0 1.90 G-MULTI PURPOSE HALL G-MULTI-PURPOSE HALL 1 27.2 Jul 2000 2508 3.5 392.0 6.40