Summer Internship Report 2024
Submitted by
Saurabh Mishra
.
M.Tech (Construction Technology & Management)
Visveswaraya National Institute of Technology
Nagpur, Maharashtra
AARVEE Associates INTERNSHIP REPORT
The first week of the internship began with Reporting to the Project manager
Mr. Avinash who is currently leading a team of experts in Chennai Metro Rail
Project Phase 2.A general introduction of the Company and its works performed
in previous and ongoing railway project was given by him ,
He explained me about the Scope of internship and the possible learnings i can
acquire based on tasks accomplished given to me.
Task performed :
Reading and understanding the PPR report of MRTS phase 3 rd metro Corridors
in Hyderabad
PPR report
A PPR or Preliminary Project Report, plays a vital role in mitigating risks and
ensuring a project's success in construction. Here's a breakdown of its function:
Task performed : :
Comparison and Change Analysis of Addendum 1 and 2 of CMRL- Phase II -
GC-1(NKAB) Staffing Schedule and Explain changes to Senior Vice President
In this i have thoroughly gone through two Addendums of Chennai metro rail
project ongoing project to find out the the parameters causing change in Total
billing Amount .
After carrying out thorough analysis i came into conclusion that basically two
parameters are the cause es of change in Total amount. Viz 1.Man Months
2.Bill rate
I tracked down changes for all position codes,Sorted in the order of Package
with respect to addendum 2
After analysis i prepared 6 different spreadsheets
1. Addendum Comparison Observation sheet
2. Increase in Man Months of positions of INR payments
3. Reduction in Man Months of positions of inr payments
4. Reduction in Man Months of positions of USD payments
5. New Job Positions in INR
6. New Job Positions in USD
7. Reduction in Total Billing Amount of Position (INR payment)
8. Reduction in Total Billing Amount of Position (USD payment)
after preparing these sheets i had explained them to Senior Vice President Mr
Shankram BB sir.
➢
. In this Week i was assigned the task of Manmonths Monitoring in CMRL
metro ongoing project.
I was given the Monthly Attendence sheets of Aarvee Associates and Urban
New employee positions deployed at CMRL project site.
Following operations were performed by me
Sorted the Positions in ascending order of employee codes so that it could
be easy to track.
Extracted data from monthly Attendence sheet of years 2022,2023 and 2024
and put them in a summary sheet for Comparison between CMRL attendence
data with respect to Aarvee to check if there is a discrepancy in recorded
data using commands of VLOOKUP, etc.
Checked for any Resignations and new deployment in place of those
Resignations.
Linked the yearwise overall Manmonths to the summary sheet and
Addendum sheets,so that any change input in yearly sheet should reflect in
Summary sheet and addendum sheet subsequently