Professional Documents
Culture Documents
Siemens -Report-VersionC
Siemens -Report-VersionC
Version C
Petroleum Pipeline Co.
Mostakbal City Pipeline
PM_TE_Report_en Ver.4.02
siemens.com/power-technologies
Petroleum Pipeline Co.
Mostakbal City Pipeline
Revision History
Table of Contents
Revision History ....................................................................................................................2
1 Introduction ...............................................................................................................7
3 Data ..........................................................................................................................10
3.1 Soil resistivity ............................................................................................................10
3.1.1 Measurement sequences .............................................................................10
3.1.2 Determination of apparent resistivity ...........................................................10
3.1.3 Determination of two layer soil model for conductive coupling ....................10
3.1.4 Soil resistivity for inductive coupling ............................................................11
3.2 Pipeline .....................................................................................................................11
3.3 Overhead lines ..........................................................................................................12
3.3.1 500 kV line...................................................................................................12
3.3.2 220 kV line...................................................................................................13
3.3.3 66 kV line.....................................................................................................14
3.4 Earth fault currents....................................................................................................14
3.4.1 500 kV line...................................................................................................14
3.4.2 220 kV line...................................................................................................15
3.4.3 66 kV line.....................................................................................................16
3.5 Maximum load currents.............................................................................................16
10 Summary ..................................................................................................................32
Literature.............................................................................................................................33
Appendix .............................................................................................................................34
List of Figures
Figure 3-1 Tower outline 500 kV ............................................................................12
Figure 3-2 Tower outline 220 kV and 66 kV............................................................13
Figure 3-3 Maximum 500 kV earth fault currents on the line section running in
parallel to the pipeline ..........................................................................14
Figure 3-4 Maximum 220 kV earth fault currents on the line section running in
parallel to the pipeline ..........................................................................15
Figure 6-1 Location of screening conductors ..........................................................23
List of Tables
Table 2-1 Limits for interference voltages depending on fault duration ..................8
1 Introduction
In the course of the development of Mostakbal City existing 500 kV, 220 kV and 66 kV over-
head lines are relocated. The new route of the overhead lines runs over a length of 6 km in
parallel to a 20” pipeline of Petroleum Pipelines Co.
Load and fault currents in the overhead lines induce voltages in the pipeline (inductive inter-
ference).
In case of an earth fault at a tower of a high voltage overhead line the pipeline is influenced
by conductive coupling.
The pipeline is laid underground. Therefore no capacitive coupling could occur.
To protect people and equipment permissible values for interference voltages have to be
kept. Calculation procedures, permissible limits and possible mitigation measures are given in
regulations such as:
• European standards [1], [2]
• CIGRE guide [3]
Siemens PTI was asked to study the pipeline interference due to inductive and conductive
coupling. In case of calculated voltages exceeding the permissible limits protective measures
are to be recommended.
For a fault duration ≤ 1.0 s for the 500 kV, 220 kV and 66 kV lines the permissible interference
voltage is:
430 V (rms value)
With respect to damages to the pipeline system the maximum interference voltage according
EN 50443 [1] is:
2000 V (rms value)
8 ⋅ UAC
IAC =
ρe ⋅ π ⋅ d
The maximum allowable a.c. voltage to comply with a limit of a.c. current density can be cal-
culated as follows:
With
IAC 30 A/m² limit of a.c. current density
ρe 70 Ωm soil resistivity of top layer (see chapter 3.1.3)
d 0.013 m diameter of a holiday or a probe with an area of 1 cm²
UAC = 11 V
As fault currents are of a short duration, they will not impact a.c. corrosion of the pipeline.
3 Data
1
ρA = n
1 1
∑
n i=1 ρ A i
The average values calculated for apparent soil resistivity are given in Appendix 11.
These soil model data match well with the measured soil characteristic values. This can be
concluded from Appendix 12, where the theoretical curve f (ρt, ρb, h) as well as the measured
curve are given.
3.2 Pipeline
The route of the pipeline is shown in Appendix 13
The following data are given for the 20” pipeline:
Based on these data the following electrical parameters of the pipeline are calculated with the
equations given in CIGRE TB95 [3]:
3.3.3 66 kV line
The two 66 kV systems run nearly over the full pipeline exposure length on the same towers
as the 220 kV systems (see Figure 3-2).
For the 66 kV double system overhead line the following data are given:
Phase wire: 1 x ACSR 380/50 per phase
Earth wire: OPGW (68.7 mm² Aluminum alloy / 42.4 mm² ACS)
Earth wire reduction factor: ke = 0.77
Based on these short circuit impedances at the line ends the maximum earth fault currents on
the line section running in parallel to the pipeline was calculated. The results are shown in
Figure 3-3.
Figure 3-3 Maximum 500 kV earth fault currents on the line section running in parallel to the pipeline
The maximum earth fault current at the line section running in parallel to the pipeline is:
IK1” = 13.89 kA
This value is considered for calculation of conductive coupling in case of an earth fault at a
tower close to the pipeline.
For inductive interference not the full earth fault current but only the partial zero sequence
fault current flowing via the overhead line in parallel to the pipeline is relevant. For an earth
fault at one end of the parallel section (left side in Figure 3-3) the zero sequence current via
the parallel line section is 4.53 kA. For a fault at the other end (right side in Figure 3-3) the
current via the parallel line section is 8.58 kA. The following zero sequence current is consid-
ered for calculation of inductive interference:
3·I0 = 8.58 kA
Based on these short circuit impedances at the line ends the maximum earth fault currents on
the line section running in parallel to the pipeline was calculated. The results are shown in
Figure 3-4.
Figure 3-4 Maximum 220 kV earth fault currents on the line section running in parallel to the pipeline
The maximum earth fault current at the line section running in parallel to the pipeline is:
IK1” = 22.21 kA
This value is considered for calculation of conductive coupling in case of an earth fault at a
tower close to the pipeline.
For inductive interference not the full earth fault current but only the partial zero sequence
fault current flowing via the overhead line in parallel to the pipeline is relevant. For an earth
fault at one end of the parallel section (left side in Figure 3-4) the zero sequence current via
the parallel line section is 4.16 kA. For a fault at the other end (right side in Figure 3-4) the
current via the parallel line section is 11.28 kA. The following zero sequence current is con-
sidered for calculation of inductive interference:
3·I0 = 11.28 kA
3.4.3 66 kV line
For the 36.5 km long 220 kV overhead line from Badr to EI‐Katamia the positive and zero se-
quence short circuit impedances at the two ends of the line were given:
Badr Busbar:
Positive sequence impedance: 2.577 Ω + j 10.496 Ω
Zero sequence impedance: 4.362 Ω + j 25.753 Ω
EI‐Katamia Busbar:
Positive sequence impedance: 0.482 Ω + j 3.062
Zero sequence impedance: 0.015 Ω + j 4.921 Ω
The earth fault current of the 66 kV system are clearly lower than of the 220 kV system. As
the systems of both voltage levels run on the same towers, earth faults in the 220 kV system
are relevant for the maximum inductive and conductive interferences to the pipeline.
Therefore only earth faults at the 220 kV systems are considered. If the calculated pipeline
interference voltages in case of a 220 kV earth fault comply with the permissible limits, the
limits are also kept in case of a 66 kV earth fault.
4 Calculation method
where
Ui induced longitudinal voltage (electromotive force)
kt is the reduction factor for screening conductors associated with the Pipeline (k t=1.0)
ke is the reduction factor of earth wires of the inducing overhead lines (see chapter 3.3)
3·I0 is the maximum zero sequence current flowing via the inducing line (see chapter
3.4)
n is the number of sections
ℓi is the length of the i-th section
Zi ’ is the coupling impedance per unit length of the i-th section
The induced longitudinal voltage in case of normal operation of the power line is calculated
as follows:
n k
Ui = k t ⋅ ∑ l i ⋅ ∑ Ij ⋅ Zi' ,j
i=1 j=1
where
Ui induced longitudinal voltage (electromotive force)
kt is the reduction factor for screening conductors associated with the Pipeline (k t=1.0)
n is the number of sections
ℓi is the length of the i-th section
k is the number of conductors of the power line (phase and earth wires)
Ij is the current of j-th conductor of the overhead line (see chapter 3.5)
Zij’ is the coupling impedance per unit length of j-th conductor and the i-th section
In case of a perfect insulation of the pipe from earth the maximum transverse voltage of the
pipeline is the induced longitudinal voltage Ui. In practice the coating of pipes buried in the
soil have small damages of the coating. For this reason the leakance of the pipe as well as
earth electrodes on the pipeline have to be considered.
Currents in the power line induce a longitudinal voltage into the pipe. This value is calculated
for sub-sections of approximately uniform spacing to the power line. The transverse voltage
of the pipeline caused by the longitudinal voltage of each sub-section is determined under
consideration of leakage current by using hyperbolic expressions [5]. Finally the results of the
sub-sections are superposed.
Ures = Uind
2
+ U2ohm
where
Ures interference voltage resulting from inductive and conductive coupling
Uind interference voltage caused by inductive coupling
Uohm interference voltage caused by conductive coupling
This resulting interference voltage is a transverse voltage between pipe and far earth. It is also
the voltage which stresses the pipeline coating.
5 Calculation results
This calculated maximum interference voltage is much higher than the permissible limit of
430 V for fault durations up to 1.0 s. Therefore mitigation measures have to be planned and
realized.
This calculated maximum interference voltage is much higher than the permissible limit of
430 V for fault durations up to 1.0 s. Therefore mitigation measures have to be planned and
realized.
Because of the higher fault currents and the lower distance of the overhead line to the pipe-
line the interference voltage in case of an 220 kV earth fault is clearly higher than in case of
an 500 kV fault.
For the two 220 kV as well as for the two 66 kV systems an identical phase arrangement of
the two systems is considered:
§ L1, L2, L3 from top to down in both 220 kV systems (see tower outline in Figure 3-2)
§ L1, L2, L3 from left to right in both 66 kV systems (see tower outline in Figure 3-2)
This assumption results in the maximum induced voltages in the pipeline. By changing the
phase arrangement of the two systems the induced voltage by the 220 kV and the 66 kV sys-
tems can be reduced significantly.
As the load current directions and phase angles are not defined also the phase angles of the
voltages, induced by the three voltage levels, are not defined. As worst case it must be as-
sumed that the induced voltages have the same phase angle and the voltages sum up. This
worst case assumption results in a resulting induced voltage under normal operation of the
power lines of:
Uind = 524 V
In case of normal operation of the high voltage systems no current flows via the tower earth-
ing systems to earth. Therefore no conductive coupling has to be considered and the resulting
interference is equal to the inductive interference.
This calculated maximum interference voltage is much higher than the permissible limit with
respect to personal safety of 60 V. Therefore mitigation measures have to be planned and
realized.
6 Mitigation measures
6.1 Principle
Because interference voltages at the pipeline are clearly higher than the limits mitigation
measures against short-time and long-time interference are required.
Principle mitigation measures at pipelines are [3] [4]:
§ Installation of concentrated earth electrodes at specific locations along the pipeline
(lumped earthing) and connection of these electrodes to the pipeline.
In case of a cathodic protected pipeline these connections between the pipeline and the
earth electrodes have to be equipped with a devise, able to block direct current of the ca-
thodic protection system (d.c.-blocking device).
§ Subdivision of the induced pipeline in a number of electrically disconnected sections.
In case of a cathodic protected pipeline each of these sections need a separate cathodic
protection system.
§ Installation of one or more screening conductors in parallel to the pipeline. Load and fault
currents in the power lines induce currents in theses screening conductors. These currents
in turn induce a voltage into the pipeline, which has a phase angle difference of nearly
180° compared to the voltage induced by the power line. As a consequence the resulting
induced voltage is reduced.
To reduce the high induced voltages to the permissible limits concentrated earth electrodes
with an earthing resistance of 0.1 Ω or less at both ends of the induced pipeline section and
at several locations within would be required. To get such a low earthing resistance earth
mats with an area of sum hundreds meter by some hundreds meter would have to be in-
stalled. Therefore installation of earth electrodes as single measure seems to be unrealistic.
Subdivision of pipeline into electrically disconnected section would require at least 16 sec-
tions to limit the induced voltage to the permissible limits in each of these sections. Every of
these sections would need an individual cathodic protection system. Therefore also this
measure seems to be unrealistic.
2 x 70 mm² copper
pipeline
0.800 m
0.900 m
Figure 6-1 shows the location of the screening conductors as considered for the following
calculations. A location of the copper conductor closer to the pipeline (e.g. by laying the cop-
per conductors in a depth of 1 m) would slightly increase the screening effect. Also an in-
creased spacing between the conductors (e.g. one in 0.5 m and the other in 1.0 m depth)
would slightly increase the screening effect.
The screening conductors have to be laid along the full exposure length of about 6 km and
should extend the exposure length at both ends by 1 km. This results in a total length of the
screening conductor of about 8 km (for each of the two conductors).
The screening conductors have to be connected to the pipeline at both ends of the induced
section. At both ends three connections with distances of 500 m in between are required. For
the simulation model connections between pipeline and screening conductors are considered
at the following pipeline – kilometers (for kilometer indication see Appendix 13):
Northern end: 0.5 km; 1.0 km; 1.5 km
Southern end: 7.0 km; 7.5 km; 8.0 km
In case of any touchable over ground structure of the pipeline (e.g. valves) within the induced
section additional connections between this structure and the screening conductor are pro-
posed.
To maintain the effectiveness of cathodic protection system all connections between pipe and
screening conductor have to be equipped with DC-blocking devices (e.g. anti-parallel set of
diodes). The blocking devices have to be selected according to the maximum continuous cur-
rent and the maximum short time current via the earth connection. These maximum currents
are calculated for every interference scenario and are given in the following chapters of the
report.
At the points of pipeline earthing, the two screening conductors have to be interconnected
and connected to the pipeline via one DC blocking device.
Ures = 140 V
This calculated maximum interference voltage is clearly lower than the permissible limit of
430 V for fault durations up to 1.0 s.
The calculation shows that the recommended mitigation measures are efficient and suffi-
cient.
For the maximum induced short-time AC current flowing via a DC blocking device in case of a
500 kV earth fault the following value is calculated:
Ishort = 380 A
Ures = 285 V
This calculated maximum interference voltage is lower than the permissible limit of 430 V for
fault durations up to 1.0 s.
The calculation shows that the recommended mitigation measures are efficient and suffi-
cient.
For the maximum induced short-time AC current flowing via a DC blocking device in case of a
220 kV earth fault the following value is calculated:
Ishort = 600 A
As worst case it must be assumed that the voltages, induced by the different high voltage
systems have the same phase angle and the voltages sum up. This worst case assumption
results in a resulting induced voltage under normal operation of the power lines of:
Uind = 17 V
This calculated maximum interference voltage is clearly lower than the permissible limit with
respect to personal safety of 60 V.
The calculated maximum interference voltage is slightly higher the a.c. voltage of 15 V given
with respect to a.c. corrosion. The voltage is also higher than the value of 11 V, derived from
the required a.c. current density of 30 A/cm² (see chapter 2.2). Nevertheless the corrosion risk
is very low because:
§ For the calculation absolutely worst case conditions are considered
- regarding the phase arrangement of the two 220 kV and the two 66 kV systems and
- regarding the phase angles of the voltages, induced by the 500 kV, 220 kV and 66 kV
systems.
§ The limits with respect to a.c. corrosion are average values over a representative period of
time (e.g. 24 h) [2]. The above given voltages are calculated for peak load conditions on-
ly. In practice load currents are changing with a daily load curve.
§ The above given voltages are calculated as potential differences between pipe and far
earth. Due to the potential grading effect of the screening conductor the potential of the
soil near to the pipeline is increased and the potential differences between pipe and sur-
rounding soil are lower than the above given voltages. Therefore also the corrosion risk is
lower.
For the maximum induced AC current flowing via a DC blocking device under maximum load
conditions the following value is calculated:
Icont = 43 A
8.1 Description
Safety of pipeline voltages is required also for the loss of one earth electrode respectively loss
of one connection between pipe and the parallel copper conductors.
For the modeled loss of one connection between pipeline and the parallel copper conductors
only the worst case short time interference by an earth fault is considered. Interference in
case of a 500 kV earth fault is not calculated because it is lower than in case of a 220 kV earth
fault.
Ures = 400 V
This calculated maximum interference voltage is lower than the permissible limit of 430 V for
fault durations up to 1.0 s.
The calculation shows that the recommended mitigation measures are efficient and sufficient
also in case of a possible loss of one of the six connections to the parallel copper conductors.
For the maximum induced short-time AC current flowing via a DC blocking device in case of a
220 kV earth fault the following value is calculated:
Ishort = 800 A
As worst case it must be assumed that the voltages, induced by the different high voltage
systems have the same phase angle and the voltages sum up. This worst case assumption
results in a resulting induced voltage under normal operation of the power lines of:
Uind = 22 V
This calculated maximum interference voltage is clearly lower than the permissible limit with
respect to personal safety of 60 V.
For the maximum induced AC current flowing via a DC blocking device under maximum load
conditions the following value is calculated:
Icont = 55 A
9.1 Description
Safety of pipeline voltages is required also for the loss of one screening conductor at one sec-
tion between connection points between pipe and these conductors. The worst case is the
loss of one of the two screening conductors of the long section between kilometer 1.5 and
kilometer 7.0 of the pipeline.
This will cause the following negative effects:
§ an increase of the screening factor from kt = 0.46 to kt = 0.58
§ an increase of the earthing resistance for the earthing connections at pipeline kilometer
1.5 and 7.0
For this modeled loss of one screening conductor only the worst case short time interference
by an earth fault is considered. Interference in case of a 500 kV earth fault is not calculated
because it is lower than in case of a 220 kV earth fault.
Ures = 355 V
This calculated maximum interference voltage is lower than the permissible limit of 430 V for
fault durations up to 1.0 s.
The calculation shows that the recommended mitigation measures are efficient and sufficient
also in case of a possible loss of one parallel copper conductor at one pipeline section.
For the maximum induced short-time AC current flowing via a DC blocking device in case of a
220 kV earth fault the following value is calculated:
Ishort = 900 A
As worst case it must be assumed that the voltages, induced by the different high voltage
systems have the same phase angle and the voltages sum up. This worst case assumption
results in a resulting induced voltage under normal operation of the power lines of:
Uind = 27 V
This calculated maximum interference voltage is clearly lower than the permissible limit with
respect to personal safety of 60 V.
For the maximum induced AC current flowing via a DC blocking device under maximum load
conditions the following value is calculated:
Icont = 63 A
10 Summary
In the course of the development of Mostakbal City existing 500 kV, 220 kV and 66 kV over-
head lines are relocated. The new route of the overhead lines runs over a length of 6 km in
close proximity to a 20” pipeline of Petroleum Pipelines Co.
By fault and maximum load currents high voltages would be induced in the pipeline. Voltages
up to 6500 V under fault conditions and up to 530 V under worst case load conditions are
calculated. Because these voltages are much higher than the permissible limits with respect
to safety of people mitigation measures are essential.
It is recommended to lay two screening conductor 70 mm² blank copper in parallel to the
pipeline. At the ends of the induced pipeline section this screening conductor has to be used
as earth electrode, the pipeline has to be earthed to.
To maintain the effectiveness of cathodic protection system these earth connections have to
be equipped with DC-blocking devices (e.g. anti-parallel set of diodes). DC-blocking devices
with rated continuous and short time currents (1 s) higher than the following calculated max-
imum currents have to be selected:
Maximum continuous current: 63 A
Maximum short time current (1 s): 900 A
Interference calculations with these mitigation measures show, that the recommended
measures are efficient and sufficient.
Literature
[1] EN 50443: Effects of electromagnetic interference on pipelines caused by high voltage
a.c. electric traction systems and/or high voltage a.c. power supply systems, December
2011
[2] EN 15280: Evaluation of a.c. corrosion likelihood of buried pipelines, August 2013
[3] CIGRE Technical Brochure 95: Guide on the Influence of High Voltage AC Power Systems
on Metallic Pipelines, Working Group 36.02, 1995
[4] NACE International, SP0177, Mitigation of Alternating Current and Lightning Effects on
Metallic Structures and Corrosion Control Systems, 2014-03-08
[5] CCITT – The international Telegraph and Telephone Consultative Committee: Directives
concerning the protection of telecommunication lines against harmful effects from
electric power and electrical railway lines.
Volume II – Calculating induced voltages and currents in practical cases, Geneva 1989
[6] NACE Report 327:AC Corrosion State-of-the-Art: Corrosion Rate, Mechanism, and Miti-
gation Requirements, 2010
Appendix
Appendix 1 Soil resistivity measurement – Diagram of measured values
sequence 1 ...........................................................................................36
Appendix 2 Soil resistivity measurement – Diagram of measured values
sequence 2 ...........................................................................................37
Appendix 3 Soil resistivity measurement – Diagram of measured values
sequence 3 ...........................................................................................38
Appendix 4 Soil resistivity measurement – Diagram of measured values
sequence 4 ...........................................................................................39
Appendix 5 Soil resistivity measurement – Diagram of measured values
sequence 5 ...........................................................................................40
Appendix 6 Soil resistivity measurement – Diagram of measured values
sequence 6 ...........................................................................................41
Appendix 7 Soil resistivity measurement – Diagram of measured values
sequence 7 ...........................................................................................42
Appendix 8 Soil resistivity measurement – Diagram of measured values
sequence 8 ...........................................................................................43
Appendix 9 Soil resistivity measurement – Diagram of measured values
sequence 9 ...........................................................................................44
Appendix 10 Soil resistivity measurement – Diagram of measured values
sequence 10 .........................................................................................45
Appendix 11 Soil resistivity measurement – Diagram of measured values –
average values ......................................................................................46
Appendix 12 Soil resistivity measurement – Comparison of determined values
with measured values ...........................................................................47
Appendix 13 Layout plan of pipeline and ohls............................................................48
Appendix 14 Induced pipeline voltages in case of a 500 kV earth fault.......................49
Appendix 15 Induced pipeline voltages in case of a 220 kV earth fault.......................50
Appendix 16 Surface potential in case of an 500 kV earth fault at tower M18 ............51
Appendix 17 Potential along the pipeline in case of an 500 kV earth fault at
tower M18 ............................................................................................52
Appendix 18 Surface potential in case of an 220 kV earth fault at tower BT15 ...........53
Appendix 19 Potential along the pipeline in case of an 220 kV earth fault at
tower BT15 ...........................................................................................54
Appendix 20 Induced pipeline voltages under normal operation of overhead
lines with maximum load currents ........................................................55
Appendix 21 Induced pipeline voltages in case of a 500 kV earth fault (with
mitigation) ............................................................................................56
Appendix 12 Soil resistivity measurement – Comparison of determined values with measured values
0 km
1 km
2 km
3 km
4 km
5 km
6 km
7 km
8 km
9 km
10 km
11 km
12 km
8000
7000
transverse voltage pipe - earth [v]
6000
5000
4000
3000
2000
1000
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
8000
7000
transverse voltage pipe - earth [v]
6000
5000
4000
3000
2000
1000
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
50 V - 100 V
100 V - 150 V
150 V - 200 V
200 V - 250 V
250 V - 300 V
> 300 V
Appendix 17 Potential along the pipeline in case of an 500 kV earth fault at tower M18
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
pipeline km
50 V - 100 V
100 V - 150 V
150 V - 200 V
200 V - 250 V
250 V - 300 V
> 300 V
Appendix 19 Potential along the pipeline in case of an 220 kV earth fault at tower BT15
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
pipeline km
Appendix 20 Induced pipeline voltages under normal operation of overhead lines with maximum load currents
600
300
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 21 Induced pipeline voltages in case of a 500 kV earth fault (with mitigation)
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 22 Induced pipeline voltages in case of a 220 kV earth fault (with mitigation)
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 23 Potential along the pipeline in case of an 500 kV earth fault at tower M18 (with mitigation)
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
pipeline km
Appendix 24 Potential along the pipeline in case of an 220 kV earth fault at tower BT15 (with mitigation)
500
Limit 430 V
450
400
transverse voltage pipe - earth [v]
350
300
250
200
150
100
50
0
2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
pipeline km
Appendix 25 Induced pipeline voltages under normal operation of overhead lines with maximum load currents (with mitigation)
70
Limit 60 V
60
transverse voltage pipe - earth [v]
30
20
10
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 26 Induced pipeline voltages in case of a 220 kV earth fault (with mitigation; loss of earth connections)
500
Limit 430 V
400
transverse voltage pipe - earth [v]
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 27 Induced pipeline voltages under normal operation (with mitigation; loss of earth connection at 7.5 km)
70
Limit 60 V
60
transverse voltage pipe - earth [v]
30
20
10
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 28 Induced pipeline voltages in case of a 220 kV earth fault (with mitigation; loss of screening conductor)
500
Limit 430 V
400
transverse voltage pipe - earth [v]
300
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km
Appendix 29 Induced pipeline voltages under normal operation (with mitigation; loss of one screening conductor)
70
Limit 60 V
60
transverse voltage pipe - earth [v]
30
20
10
0
0 1 2 3 4 5 6 7 8 9 10 11 12
pipeline km