Professional Documents
Culture Documents
Risk Assessment for Installation of Electrical Wiring Amp Cable Pulling
Risk Assessment for Installation of Electrical Wiring Amp Cable Pulling
Over Loading 3. Workers should away from the lifting area and
must be barricaded with caution signage and
Lifting Failure banksman must be active on work.
Unloading of cable Unstable support 4. Store yard/access to be inspected prior to activity.
drum using Forklift Operators,
Workers/ Supervisor,
Physical 5. Only 3rd party certified lifting gears/plant
3 Helpers 4 4 16 High 1 4 4 Low Foreman,
Injury/fatality equipment’s are to be used
Foreman Site Eng.
Poor illumination in 6. Ensure forklift must have reverse alarm and
night work beacon light.
Document Reference
AMC CONCOURSE BRIDGE PROJECT GEMC-ME-A-MST-013
Rev. No. Rev. Date
00 07/03/02019
Risk Assessment Record Assessed by Title Signature
Activity: Installation of Electrical Wiring & Cable Pulling Prabir
Safety
Officer
1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that risks have
well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these potential
high risks.
Likely (4) 4 8 12 16 20
Almost
RISK LEVEL: 5 10 15 20 25
Certain (5)