Professional Documents
Culture Documents
000.200.0350 Key Engineering Risks
000.200.0350 Key Engineering Risks
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
This practice defines the work process and tools to be used for reporting and tracking the Key Engineering
Risks.
2.0 APPLICATION
This practice applies to any Home Office project in the FEED and detailed engineering phases. The
Project Engineering Manager implements this practice and the Office Manager of Engineering makes sure
each Project Engineering Manager is performing this work.
It should be noted that the work process to define the Key Engineering Risks and load the risks into the
BRMF system is started during the proposal phase. It is the responsibility of the Engineering Manager
assigned to the proposal to initiate and implement the requirements of this practice during the proposal
phase to, at a minimum, identify the appropriate Key Engineering Risks and quantify those risks in concert
with the Proposal Manager and the office Risk Representative.
4.0 DEFINITIONS
See glossary at the end of this practice
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 1/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
6.0 REQUIREMENTS
6.1 The Project Engineering Manager will review the listing of key engineering risks and
identify those risks applicable to the project.
Twenty-nine key engineering risks that have the most impact on projects in the FEED and
detailed engineering phases have been identified. These key engineering risks are identified in
Attachment 01.
The Project Engineering Manager must review and address all 29 risks. Of the total 29 risks
shown on the list the first eighteen risks (risks 1 to 18) are considered mandatory for inclusion in
the BRMF, provided the risk topic applies to the project Scope of Work (FEED project risks will
differ from Detailed Design risks). In addition to the first 18 risks, the remaining eleven (risks 19
to 29) are to be analyzed and if applicable to the project scope, must be added to the BRMF. The
total of the risks judged to apply will be included in the Project’s business risk management
framework (BRMF). As additional engineering risks arise during the course of the project, the
Project Engineering Manager needs to inform the Project Manager and Project Risk
Representative for inclusion in the BRMF and for review during the next project BRMF review
session.
6.2 The Project Engineering Manager will develop mitigations for the identified key
engineering risks applicable to the project in cooperation with the Office Risk
Representative to develop mitigation strategies for each selected Key Engineering Risk
and then upload into the BRMF system.
The Project Engineering Manager, with the assistance of the Office / Project Risk Representative
will develop mitigation strategies for all the applicable identified engineering risks to be included
in the project BRMF. The work process provided in BRMF Practice 000.000.2000 section 6.2.5 is
used by the Risk Representative to guide the risk discussion. Included as Attachment 02, is a
snapshot of pertinent columns of the BRMF Engineering Risk input sheet used by the Project
Risk Representative to input the selected Engineering Risks into the project BRMF. This
Attachment 02 includes sample mitigation strategies for all of the 29 Key Engineering Risks that
should be considered by the Project Engineering Manager when developing their mitigations.
6.2.1 The Project Engineering Manager will develop the mitigations for the key
engineering risks with collaborative input from the Engineering Project Leads.
6.2.2 The Engineering Project Leads will incorporate the key engineering risk
mitigations into their execution plans and communicate the mitigation to their
functional teams.
6.2.3 The Project Engineering Manager will contact the Office Risk Representative and
the Project Risk Representative (if one is assigned) and provide the selected risks
and mitigation strategies for input to the project BRMF.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 2/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
6.2.4 The Project Risk Representative will facilitate the input of the selected risks and
the developed mitigation strategies into the project BRMF.
6.3 The Project Engineering Manager will attend monthly key engineering risks review
meetings with the Office Manager of Engineering to review the risks and mitigations.
The Office Manager of Engineering sets up monthly key engineering risks review meetings with
the office Project Engineering Managers to review the project Key Engineering Risks with the
Mitigation Strategies and Action Plans. This is the opportunity for the Project Engineering
Manager to present the selected Key Engineering Risks related to each project to the Office
Manager of Engineering and others attending this review. It is the opportunity to review the
critical engineering risk items and receive comments and guidance. To facilitate review and
discussion of the risks, BRMF generated reports need to be used. There are a number of reports
that can be easily generated from the BRMF system which present the BRMF information in a
number of ways (refer to BRMF Practice 000.000.2000 Attachment 05 for a list and description
of reports available). Exhibit AB (see Attachment 03), which contains the Project’s Key
Engineering Risks and mitigations, need to be used to review risks and mitigations. The Project
Engineering Manager can obtain a copy of the BRMF reports from the Office and/or Project Risk
Representative.
These meetings occur prior to the monthly office project status reviews. The Office Managers of
Engineering discuss the Risk issues with the Project Engineering Managers in detail outside of
PSR meetings to confirm appropriate mitigation actions are taken.
6.3.1 The Project Engineering Leads will communicate any issues with current key
engineering risk mitigations to the Project Engineering Manager for discussion in
the monthly key engineering risk meeting.
6.3.2 The Project Engineering Manager will communicate any updates or changes to
key engineering risk mitigations from the monthly meeting back to the Project
Engineering Leads for implementation.
6.4 The Business Line Risk Executive and the Office Risk Representative will attend the key
engineering risks review meetings on a quarterly basis at a minimum, or more frequently
as needed.
The Business Line and Office Risk Representatives attend the key engineering risk review
meetings set up by the Office Manager of Engineering on a quarterly basis to stay informed of
potential key engineering risk impacts on the projects in that office and to provide direct support
to the project for BRMF and risk issues.
In the event that the project engineering risk profile changes, or a key engineering risk is
manifesting on a project, the Office and Business Line Risk Representatives can be called to
attend key engineering risk meetings more frequently.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 3/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
6.5 The Project Engineering Manager will attend the PSR each month.
The Project Engineering Manager needs to attend and participate in the monthly office PSR
meeting. The Project Engineering Manager will present the PSR Key Engineering Risk slide. The
Key Engineering Risks PSR slide is found in 000.200.F0350. Not all the Risks identified on the
Key Engineering Risks PSR slide(s) need to be discussed. The only engineering risks to be
reviewed during PSR are those where the mitigation is not being supported by internal or
external influences increasing the probability the risk event will occur.
Note: The Key Engineering Risks slide mirrors the Engineering Risk information included in the
BRMF Exhibit AB and is prepared by the Project Controls group on the project. The PSR slide
includes the 18 key risks and mitigations. Additional sheets, if required, may be added by the
user to cover any of the remaining relevant Engineering Risks 19 through 29.
In the event the Project Engineering Manager is away from the office when PSR occurs the
Project Engineering Manager selects a delegate to attend on their behalf.
In addition, the Office Manager of Engineering attends the office Project Status Review (PSR)
each month. In the event the Office Manager of Engineering is away from the office when project
status reviews occur, the Office Manager of Engineering selects a delegate to attend on their
behalf.
6.6 The Project Engineering Manager will attend the initial Business Risk Management
Framework (BRMF) meeting and each subsequent BRMF update meeting.
The Project Engineering Manager is required to attend each project BRMF update session.
6.7 The Project Manager will verify the key engineering risks identified on the project are
included and updated in the BRMF.
The Project Manager has the responsibility to maintain the project BRMF throughout the life of
the Project.
6.8 The Project Engineering Manager will inform the engineering team that confidentiality
requirements exist for sharing BRMF information.
Fluor’s Business Risk Management Framework (BRMF) is a Company confidential program. The
documents generated from the BRMF system are designated as “ATTORNEY – CLIENT
PRIVILEDGED COMMUNICATIONS”. Fluor employees will not give Owners or Clients any
aspect of Fluor’s Business Risk Management Framework (BRMF) including risk practices, risk
bulletins, risk lists, BRMF reports or otherwise provide access to the software or the printed
materials, including the Key Engineering Risks Table in Attachment 01 of this document. If any of
the Engineering Team is approached by a Client to share the BRMF information, the Project
Engineering Manager should immediately inform the Project Manager of such request. There is a
specific Corporate Risk Practice that must be implemented by Senior Management to facilitate
the sharing of the BRMF information with Clients.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 4/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 5/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 01
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 6/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 01
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 7/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 8/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 9/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 10/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 11/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 12/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 13/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 14/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 15/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
DEFINITIONS
The following terms and acronyms apply to this practice.
Title Description
CA Contract Administrator
Criticality Rating (CR) A method of assessing the importance of an item with respect to various
categories such as its design, manufacturing routines, and the consequences
of failure. The criticality for equipment and materials is established on a scale of
1 to 4 with 1 being the most critical, 4 being the least critical. Form
000.200.F0077, Criticality Rating Form, has the standard categories and
definitions for criticality used on Fluor projects.
EI Energy Institute
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 16/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
Front End Engineering and A project planning document (UG Philosophy) produced prior to project
Design (FEED) initiation that serves as the basis for final EPC construction document
development.
Installation Work Package An Installation Work Package (IWP) is a portion of scope derived from a CWP.
(IWP) It is comprised of an Installation Code and a Sequence number, which contains
all necessary elements for a single construction crew to complete that portion of
the scope of work. It includes critical documents along with a detailed execution
plan. The WFP team will confirm that a released IWP will contain constraint free
work that can be executed by a single foreman and crew within a practical
construction timeframe (typically a 1-2 week shift).
LE Lead Engineer
Lessons Learned A Project Experience that is implemented into any Fluor numbered document
(e.g., practices or guidelines).
Model Review (MR) A plant design review with the Client and/or Licensor that uses an electronic 3D
model.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 17/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
Notified Body (NoBo) European Conformity Assessment Institute. This is the Authority Inspection
agency that conforms to Article 24 of the PED, accredited by the EU member
states and appointed by the Manufacturer, designated to assess conformity of
pressure equipment and piping to the essential safety requirements of the PED,
and to ensure consistent technical application of these requirements.
NTE Not-to-Exceed
Particular Material Appraisal A document that - for materials which are not listed in a harmonized standard
(PMA) nor have European approval - provides a statement that a material fulfills the
requirements of the ESR and are suitable for the proposed use and conditions.
It prescribes the physical and chemical properties of a material. PMA’s shall be
submitted by the Manufacturer to the Notified Body for approval.
PM Project Manager
Process Industry Practices Process Industry Practices is a process industries standards organization that
(PIP) issues practices suitable for purchase orders or contracts. The practices are
harmonized from non-proprietary best practices from member companies.
PU Package Unit
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 18/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
Purchase Order (PO) A PO is the Buyer's official notification to the seller of authority to manufacture,
supply, ship, and invoice for the goods specified in the order and Fluor’s
commitment to pay for the value of the goods ordered. It is a legal document
and should clearly and precisely cover the essential elements of the order in a
manner that will render misunderstandings improbable.
Request for Proposal (RFP) The Request for Proposal is assembled and prepared by the Contract
Administrator, and issued to Bidders.
Request for Quotation (RFQ) Taken to be synonymous with inquiry, it is the document used to obtain price
and delivery on a competitive basis for the goods required for projects.
S3D Smart 3D
Scope of Facilities (SOF) The Scope of Facilities is part of the Project Baseline Scope of work. It
describes the facilities that will be provided as part of the project.
Scope of Work (SOW) The Scope of Work is the Baseline Document for the project that includes the
Scope of Services (SOS) and Scope of Facilities (SOF) for the project.
Statement of Compliance (SOC)Document prepared by the manufacturer of a product (not being the “overall”
manufacturer) or their authorized representative which states compliance to the
PED of the pressure equipment considered based on examinations performed
by the Manufacturer’s Inspection/QA department and/or assigned Notified Body
according to the applicable Conformity Assessment Procedure.
Supplier Person or legal entity that is responsible for supply of goods or products.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 19/20
12/18/2019 000.200.0350 Key Engineering Risks.pdf
Practice 000.200.0350
Date 18Dec2019
Engineering Management
Full Practice Printed from Quality Requirements System Global Library
The Technical Control Plan A risk based quality control execution plan that emphasizes the critical and
(TCP) challenging technical aspects of the project and demonstrates the discipline-
specific criteria for preparing, checking and approving the critical deliverables
that require further validation above the standard discipline checking matrix.
UG Underground
Very Large Module (VLM) A VLM is a module weighing more than 600 tons. Generally, above 600 tons
requires nonconventional lifting / jacking and transporting methods.
Transportation is often by barge or heavy transport vessel (HTV). VLMs provide
an opportunity to maximize modular content. Construction of a VLM is often
segregated into stages in the module yard and the WBS level – Stage – is used
to define these boundaries.
Work Breakdown Structure Represents the way the project work will be defined, planned, managed, and
(WBS) controlled by subdividing the project scope of work into manageable segments
(elements). A WBS is a hierarchical framework (family tree), composed of
products and services that progressively and logically subdivides the entire
work content. It serves the control needs of a project by providing a structure
for performing work and defining how cost and schedule data are summarized
and reported. The WBS is developed from the project scope to a level of detail
that defines the framework for the organization and reporting of project
information, allowing for effective project control of costs and schedule.
Elements of the WBS serve as the foundation for the Project Execution Plan as
well as project control functions.
© 2019, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.200.0350%20Key%20Engineering%20Risks.pdf 20/20