Read Me

1)
Dear User, thank you for using my template. Please remove sample entries from the register

2)
Please make your data entries on the sheet "Estimation Sheet". Cells containing formulas or functions are protected, the password is blank
should you wish to modify anything.

3)
To avoid typing mistakes resulting in incorrect filter results, some entries are restricted. To modify acceptable values change entries on the
sheet "Validation".

4)
You downloaded this sheet free of charge from
http: project-management.magt.biz
You may use this sheet for your personal use and projects. However, selling the sheet is strictly prohibited.
protected, the password is blank

able values change entries on the

prohibited.
This template is downloaded from http://project-management.magt.biz

Project: [Project Name]


Sub-Project or Phase: [Sub-Project or Phase]
Activity Cost Estimation
Client: [Client] Project Mngr.: Printed on
Client's Representative: [Client's Representative] QA/QC Mngr.: Ref.-No.:
Contractor: [Contractor]
Activity Description: Excavation Process
Material Manpower Tools & Equipment
Total Man
Item UOM QTY Rate (QR) Total (QR) Name QTY/#of crew days hrs/day Rate (QR) Total (QR) Item UOM QTY Rate (QR) Total (QR)
Hours
A B C D E F G H I J K L M N O P Q R
0001 CM 115 150 17,250 Skilled Worker 2 11 8 176 1,375 242,000 Mobile working platform LS 1 15,000 15,000
- Drilling machine, cutting machine and other hand tools LS 1 3,000 3,000
- Painting utensils etc. LS 1 500 500
- - - Extension cord (50m) LS 1 500 500
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
Sub-Total Material (QR) 17,250 Sub-Total Human Ressources (QR) 242,000 Sub-Total Equipment and Tools (QR) 19,000

Grand Total Direct Cost (QR) 278,250

Estimation Class Range Lower Limit (QR) Upper Limit (QR)

Budget Estimation -10% 25% 250,425 347,813

Prepared by: Marc Arnecke,PMP


Order of Magnitude -25% 75% Currency: QR
Preliminary Estimation -15% 50%
Budget Estimation -10% 25%
Definitive Estimation -5% 10%