Professional Documents
Culture Documents
IEEE_Allocation Harmonic Emission Limit at HV&EHV on IEC 61000-3-6 under consideration of global and future installations
IEEE_Allocation Harmonic Emission Limit at HV&EHV on IEC 61000-3-6 under consideration of global and future installations
I N the recent years, various distorting installations producing Since these guidelines are created under simplifying
harmonics have been connected to High Voltage (HV) and assumptions, there is no guarantee that this approach will
Extra High Voltage (EHV) power transmission networks. always provide the optimum solutions for every harmonic
According to IEC standard, HV refers to voltage between situation [1]. Therefore, the recommended approach there
35 kV and 230 kV, while EHV is defined for voltage above should be used with flexibility and appropriate engineering
230 kV. In addition to electrical installations with judgment, when applying the given assessment procedure [1].
conventional nonlinear voltage-current characteristics such as As the reason mentioned above, this paper introduces some
arc furnaces and induction ovens, other significant sources of new concepts as the extension to the method proposed in
harmonics in modern power systems include power IEC 61000-3-6 [1] in order to achieve higher security in
electronics controlled devices for controlling input/output allocation of planning levels and at the same time to suite
voltages and currents. For example, High-Voltage Direct- network calculations practically. At the end of this paper, the
application of the presented method is demonstrated in a
calculation example and the results are discussed.
C. Amornvipas and L. Hofmann are with Institute of Electric Power
Systems, Division of Power Supply, Leibniz Universität Hannover,
Appelstrasse 9A, 30167 Hannover, Germany.
(e-mail: amornvipas@iee.uni-hannover.de; hofmann@iee.uni-hannover.de)
II. ASSESSMENT OF EMISSION LIMITS FOR THE CONNECTION OF distorting installations under consideration of not only
DISTORTING INSTALLATIONS TO HV AND EHV SYSTEMS harmonic emissions within the considered system, but also
According to IEC, distorting installation is defined as a from the neighboring systems at other voltage levels.
complete electrical installation (i.e. including distorting and Furthermore, sufficient emission limits should be reserved for
non-distorting parts), which can cause distortion of the voltage the future connection of distorting installations. Portions of
or current in the connected supply system [1]. Regarding planning levels for harmonic voltages known as harmonic
harmonic aspects, distorting installations in any HV or EHV voltage limits will be distributed to system nodes where
networks will be assessed before installation in accordance distorting installations will be connected.
with three evaluation stages as recommended in IEC 61000-3- The allocation concept is illustrated in Fig. 1. The idea
6 [1]. Those evaluation three stages can be applied in behind this concept is that when all distorting installations
sequence or independently. inject maximum harmonics regarding harmonic limits into
Stage 1: If power of the distorting installation compared to system, the total harmonic disturbance level anywhere in
the short circuit power at the point of connection is within the system should not exceed the planning level [1].
limits (0.2 %), the distorting installation is allowed to connect
to the system without detailed evaluation. IV. METHOD FOR SHARING PLANNING LEVELS FOR HARMONIC
Stage 2: Harmonic emission limits at every harmonic order VOLTAGES AT HV AND EHV LEVEL
for each distorting installation will be determined under In this section, the method for apportioning and allocating
consideration of system characteristics and network planning levels for harmonic voltages at every harmonic order
development. Harmonic emission limits can be normally to each distorting installation at HV and EHV under
interpreted as harmonic current limits since most of harmonic
consideration of system characteristics will be described. The
sources behave like harmonic current sources. However,
maximum acceptable harmonic voltage limits Ei (h) at the
planning levels for harmonic voltages are used by network
considered node i (where new distorting installation is
utilities as a basis for allocation of harmonic voltage limits.
Harmonic current limits from each distorting installation expected) for harmonic order h can be calculated as in (1).
connected at a node can be accordingly calculated from input This equation is analog to [1].
impedance and harmonic voltage limits at that node.
Harmonic voltages as well as currents have to be kept within 1/ α ( h )
⎛ S ⎞
the allocated limits. Ei ( h ) ≤ T ( h ) L ( h ) ⎜ * ti ⎟ (1)
⎜ S (h) ⎟
Stage 3: In exceptional cases, where the harmonic limits ⎝ ti ⎠
are exceeded, connection of distorting installations is still where
authorized by network utilities as long as no overall harmonic i node where the new distorting installation
problem in system occurs i.e. the total harmonic distortion of will be connected
voltage (THDU) for HV and EHV is lower than 3 % [1]. Sti fundamental frequency total distorting
power installed at node i in MVA
III. CONCEPT OF ALLOCATION OF PLANNING LEVELS FOR St*i ( h ) modified total distorting power at node i
HARMONIC VOLTAGES including influence of distorting installations
The planning level is set by network utilities to be equal to at other nodes for harmonic order h in MVA
or lower than the compatibility level, which is the reference α (h) summation law exponent
value for coordinating the emission and immunity of electrical T( h ) utilization degree of planning level
equipment connected to the system. L (h) planning level for harmonic voltage for
harmonic order h
in (7). Other installed non-distorting power as well as power Sti in (9) which could be calculated as shown in (10) is the
flow between nodes are neglected. total distorting power at node i at fundamental frequency.
currents will be neglected by setting to zero. This is due to the From this harmonic voltage limits, the harmonic emission
fact that the effects of local harmonic currents from the nearby limits will be accordingly calculated. In order to demonstrate
distorting installations have already been included in the the effect of global and future emission on the values of
previous step for calculating the harmonic nodal voltage limits harmonic emission limits in a simple way, the harmonic
E and should not be taken into account again. This concept is voltage limits in the following three scenarios will be
illustrated in Fig. 6. calculated by considering only (1) for the sake of simplicity.
Emission limits for the characteristic harmonic order 5, 7, 11
and 13 at node 5 will be determined in this example.
TABLE I
MODELING NETWORK ELEMENTS IN FIG. 7 AND THEIR PARAMETERS FOR
SIMULATIONS IN CALCULATION EXAMPLE
Scenario 1
In this scenario, global and future emissions will not be
taken into account. The planning level for harmonic voltage
′′ = 3 GVA
will be fully utilized under the current situation and therefore,
S k,3
the utilization degree T will be set to 1. This approach is used
in the calculation example given in IEC 61000-3-6 [1]. The
nodal admittance matrix of the test system will be built by
Fig. 7. 5-node test system at 110-kV level
taking equivalent network, but no nonlinear loads into
account.
One wind park (WP) of 50 MW operated with fully
controlled synchronous generators is planned to be connected
Scenario 2
to the system at node 5 in the near future. These wind
generators equipped with fully controlled inverters to control In this scenario, global and future emissions will be
output voltage and to match output frequency with system considered, but not simultaneously. Due to the future
operating frequency are known as harmonic sources injecting emission, the utilization degree T will be set to 0.9. This is the
harmonics into system. Thus, harmonic emission limits have sample value used for this example. The global harmonic
to be assigned to the point of connection (node 5) in the emission from the neighbouring network given in Table I
network planning phase and the wind park operator is (worst case upper values) will be applied to (14) and
responsible for keeping harmonic emissions within the therefore, the modified emission limits at node 5 under
allocated limits. Nonlinear loads as the existing distorting consideration of global emission will be obtained. The nodal
installations are found at node 1, 2 and 4. An equivalent admittance matrix of the test system will be built without
network at node 3 represents the downstream network. equivalent network and nonlinear loads.
For harmonic analyses in symmetrical systems, it is
recommended to apply the method of symmetrical Scenario 3
components. The sequence component has to be selected In this scenario, it is assumed that no detail about harmonic
according to the considered harmonic order [5]. Models of currents from the downstream network is available. However,
power system elements and their parameters for the positive the effect of global emission should be included in sharing
and zero sequence components used in test system are given planning levels. Therefore, global and future emissions will be
in Table I. Parameters for the negative sequence component simultaneously considered by assigning the utilization degree
are assumed to be identical to those for the positive sequence T to 0.7, which is lower than in scenario 2 due to the global
component. emission. The nodal admittance matrix of the test system will
The acceptable harmonic voltage limits at node 5 will be a be built without equivalent network and nonlinear loads as in
fraction of the 110-kV planning level LHV as given in Table II. scenario 2.
7
E (h)
HARMONIC CURRENT EMISSION LIMITS AT NODE 5 (IMAX,5) IN PERCENT OF THE
I max,5 ( h ) = 5 for scenario 1 and 3 FUNDAMENTAL RATED CURRENT OF WP ACCORDING TO SCENARIO 1, 2 AND 3
Z 55 ( h ) (ONLY RESULTS AT HARMONIC ORDER 5, 7, 11 AND 13)
VII. CONCLUSION EHV,” in Proc. IEEE PES Transmission and Distribution Conferences
and Exhibition, pp. 1158-1161, 2005/2006.
The effect of the global and future harmonic emissions [7] V. J. Gosbell, T. J. Browne, and S. Perera, “Harmonic Allocation Using
should not be neglected for allocation of harmonic planning IEC/TR 61000-3-6 at the Distribution/Transmission Interface,” in Proc.
levels. By considering the emission reserve through utilization 13th International Conference on Harmonics and Quality of Power
(ICHQP), 2008.
degree and global emission, the total disturbance level [8] T. J. Browne, V. J. Gosbell, S. Perera, D. A. Robinson, L. M. Falla, P. J.
anywhere in the system should not exceed the planning level Windle, and A. C. D. Perera, “Experience in the application of IEC/TR
when all distorting installations are injecting levels of 61000-3-6 to harmonic allocation in transmission systems,” CIGRE,
harmonic distortion equal to their emission limits. Paris, Paper C4-401, September 2006.
[9] G. Borloo, E. De Jaeger, M. Dussart, and A. Robert, “Practical
If the detail of harmonics flowing from downstream or implementation of IEC publications 61000-3-6 and 61000-3-7
upstream networks is available, the modified method for Experiences in Belgium,” in Proc. International Conference on
determination of the emission limits as proposed in this paper Harmonics and Quality of Power, Athens, pp. 449-454, 1998.
could be used as the alternative to determine emission limits. [10] M. Bollen, M. Häger, and M. Olofsson, “Allocation of emission limits
for individual emitters at different voltage levels: flicker and
The appropriate results could only be achieved, if the harmonics”, CIGRE Sessions, Paris, August 2010, paper C4.106.
reasonable value for the utilization degree is chosen. [11] M. H. J. Bollen, L. Yao, S. K. Rönnberg, and M. Wahlberg, “Harmonic
Therefore, further research in this direction is necessary. and Interharmonic Distortion due to a windpark,” in Proc. IEEE PES
The proposed method in this paper can be seen as the General Meeting, 2010.
[12] S. T. Tentzerakis, and S. A. Papathanassiou, “An Investigation of the
extension to the method proposed in IEC 61000-3-6 [1]. This Harmonic Emissions of Wind Turbines,” IEEE Transactions on Energy
concept can be directly applied by utilities for network Conversion, Vol. 22, No. 1, pp. 150-158, March 2007.
calculations without complicated algorithms. With the [13] S. Tentzerakis, N. Paraskevopoulou, S. Papathanassiou, and P.
presented method in this paper, higher security in allocation of Papadopoulos, “Measurement of Wind Farm Harmonic Emissions”, in
Proc. Power Electronics Specialists Conference PESC 2008, pp. 1769-
planning levels under consideration of global and future 1775, 2008.
emissions could be achieved. [14] J. Choma, Jr., Electrical Networks: Theory and Analysis, John Wiley &
All calculations will be performed under consideration of Sons Ltd, 1985.
system absorption capacity and system characteristics due to
possible system expansion i.e. the allocated harmonic limits IX. BIOGRAPHIES
will be valid for a specific period in the future. The owners of Chanchai Amornvipas (1977) was born in
distorting installations are responsible for maintaining their Bangkok/Thailand. He received the B.Sc. degree in
harmonic emissions within the allocated limits in order to electrical engineering from Chulalongkorn
University, Bangkok, Thailand in 1999 and the
avoid harmonic disturbance to neighboring installations,
M.Sc. degree in electrical power engineering from
electrical equipments in system and system operation. RWTH Aachen University, Germany in 2002. In
In practice, the allocated planning levels might be 2008, he received the Dr.-Ing. Degree from Leibniz
sometimes extremely low and exceeded for some harmonic Universität Hannover in Germany where he was a
orders at some locations in network, even though problems at research engineer and teaching associate at the
Institute of Electric Power Systems, Division of
that harmonic order are not so critical. Hence, it might not be Power Supply from 2003 to 2008. During 2008 and
reasonable to allocate too low planning levels to some 2009, he worked as a consultant at Power Technologies International, Siemens
harmonic orders without considering the actual harmonic AG in Erlangen, Germany. Since 2009, he continues doing researches and
propagation behaviour in the considered system and in teaching at the Institute of Electric Power Systems, Division of Power Supply
at Leibniz Universität Hannover. His research interests are modeling and
neighbouring systems. simulation of electric power systems, transient analyses, power system
No resonance situation is considered in this paper. If harmonics and power quality.
resonances are expected at the frequency range of interest
where extremely high influence coefficients occur, it is Lutz Hofmann (1968) was born in Bad
Oeynhausen/Germany. He received the degree
recommended to modify the influence coefficients with the Dipl.-Ing. as well as the degree Dr.-Ing. in 1994 and
reduction factor as stated in IEC 61000-3-6 [1]. 1997, respectively, from Leibniz Universität
Hannover. In 2002 he concluded his professorial
VIII. REFERENCES dissertation in electric power engineering. In 2002
and 2003 he worked as a project manager for the
[1] IEC/TR 61000-3-6: Electromagnetic compatibility (EMC) – Part 3-6: engineering and consultant company Fichtner in
Limits – Assessment of emission limits for the connection of distorting Stuttgart. From 2004 to 2007 he worked for the
installations to MV, HV and EHV power systems, Edition 2.0, 2008. german transmission system operator E.ON Netz
[2] IEC/TR 61000-3-6: Electromagnetic compatibility (EMC) – Part 3: GmbH, Bayreuth in the network planning
Limits – Section 6: Assessment of emission limits for distorting loads in department. Since 2007 he is Full Professor and Head of the Institute of
MV and HV power systems – Basic EMC publication, Edition 1.0, 1996. Electric Power Systems at Leibniz Universität Hannover, Germany. His
[3] IEEE Standard 519: IEEE Recommended Practices and Requirements current research interests are modeling and simulation of electric power
for Harmonic Control in Electrical Power Systems, 1992. systems, integration of renewable and decentralized energy sources and power
[4] IEEE Harmonics Model and Simulation Task Force, “Modeling and quality.
Simulation of the Propagation of Harmonics in Electric Power
Networks: Part I Concepts, Models, and Simulation Techniques,” IEEE
Transactions on Power Delivery, Vol. 11, No. 1, pp. 452-465, 1996.
[5] J. Arrillaga, N. R. Watson, and S. Chen, Power System Quality
Assessment, Chichester, England: John Wiley & Sons Ltd, 2000, pp.
171-228.
[6] M. McGranaghan and G. Beaulieu, “Update on IEC 61000-3-6:
Harmonic Emission Limits for Customers Connected to MV, HV, and