PROGRESS 12-07-24

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

"Construction of Six lane access-controlled Highway from Km 40+080 to Km 86+513

(Mator to Barodameo Section) of Paniyala – Barodameo ICR in the state of Rajasthan on


EPC Mode under Bharatmala Pariyojana. Package – 02"

A Details of Highway
Length/
S.No. Description Unit
Number

1 Total Length of Pakage -02 Km 46+433

2 Total Land available for work Km 27.000

3 Total available machinery at site

a) Excavator nos. 13
b) Dumper nos. 42
c) Roller nos. 9
d) Grader nos. 8

4 Work Progress

a) C & G Done Km 10.830


b) Earth work in progress Km 7.935

B Details of Structure

S.No. Description Unit Total number Work Take


up

1 ROB nos. 2 0
2 Major Bridge nos. 6 0
3 Minor Bridge nos. 10 0
4 SVUP nos. 7 1
5 Fly over nos. 2 0
6 Sub Way nos. 1 0
7 LVUP nos. 15 1
8 Interchange nos. 3 0
9 Culverts nos. 102 18
10 AUP nos. 23 0
11 TOLL PLAZA nos. 3 0