Download as pdf or txt
Download as pdf or txt
You are on page 1of 32

OPERATION AND MAINTENANCE MANUAL

TYPE GIS 36KV CUBICLE

Introduction, Specifications, Structural Details &


General Arrangement, Handling & Storage, Installation,
Commissioning, Maintenance & Inspection.

TAMCO SWITCHGEAR (MALAYSIA) SDN. BHD.


SUB LOT 24, LOT 1605, JALAN KELULI 1,
KAWASAN PERINDUSTRIAN BUKIT RAJA,
SEKSYEN 7, 40000 SHAH ALAM
SELANGOR DARUL EHSAN

GIS Cub Pub 1 (Rev. 10) 03/2019


GIS Cub Pub 1 (Rev. 10) 03/2019
TABLE OF CONTENT
CONTENTS PAGE
1.0 INTRODUCTION 1

2.0 SPECIFICATIONS 2

2.1 STANDARDS & OPERATING CONDITIONS 2


2.2 TECHNICAL DATA 2
2.3 NORMAL SERVICE CONDITIONS FOR INDOOR 3

3.0 STRUCTURAL DETAILS & GENERAL ARRANGEMENT 4

3.1 CUBICLE STRUCTURE 4


3.2 TYPICAL ARRANGEMENT 5-6
3.3 SF6 GAS SYSTEM 7-11

4.0 HANDLING & STORAGE 12

4.1 PACKING AND UNPACKING 12


4.2 TRANSPORT AND HANDLING 12
4.3 STORAGE 13

5.0 INSTALLATION 14

5.1 CHECK PRIOR TO INSTALLATION 14


5.2 FOUNDATION WORK 14-16
5.3 CUBICLE INSTALLATION 17-24
5.4 CONNECTING CONTROL WIRING 24
5.5 CONNECTING POWER CABLE 24-26
5.6 INSPECTION AFTER INSTALLATION 26

6.0 COMMISSIONING/TESTING 27

6.1 PRELIMINARY CHECKS 27


6.2 TESTING 27
6.3 START-UP 28
6.4 SWITCHING OPERATIONS 28-40

7.0 MAINTENANCE AND INSPECTION 41

7.1 FUNDAMENTAL PHILOSOPHY OF MAINTENANCE AND 41


INSPECTION
7.2 CLASSIFICATION OF MAINTENANCE AND INSPECTION 41-44

GIS Cub Pub 1 (Rev. 10) 03/2019


1.0 INTRODUCTION

This manual describes the fundamental


handling, operation & maintenance of
the GIS GV3 switchgear and its standard
handling procedures.
This metalclad Tamco SF6 Gas
Insulated Switchgear, GV3 with
all its devices housed within a
compact cubicle and gas
sealed is a type tested indoor
cubicle for rated voltages up to
36kV.

GV3
The cubicle is fitted with a
vacuum circuit breaker for
single or double busbar system.
The insulating medium is SF6
subjected to a minimum
pressure.

GIS Cub Pub 1 (Rev. 10) 03/2019 1


2.0 SPECIFICATION
2.1. STANDARDS AND OPERATING sealed with a minimum gas
CONDITIONS: pressure of 1.2kg/cm2
Applicable standard: IEC 62271-200, atmospheric at 20C for the
IEC 62271-100, IEC 62271-102. breaker, disconnecting switch,
IEC 60376 & IEC 60480. busbar and cable
Operating conditions: The GV3 SF6 compartment. It is suitable for
Insulating Gas cubicle is indoor application only.

2.2. TECHNICAL DATA:

TYPE GV3 (Single Bus) GV3D (Double Bus)


Voltage 36kV
Frequency HZ 50/60
Impulse level (kVp) 170/185*
Power Frequency 1 70/80
min (kV)
Busbar Rating
2000A/2500A
Short Time Current 25kA 31.5kA 25kA 31.5kA
3s
Peak Withstand
63 80 63 80
Current kA peak
Min Operating
Pressure (kg/cm2) 1.2kg /cm2 @ 20 deg C
Ratings

Rated operating
pressure (kg/cm2) 1.35kg/cm2 absolute @ 20 deg C
Rated gas density
7.8kg/m3
pressure (Kg/m3)
Max permissible
150ppm
moisture content
SF6 gas ml/l
Max permissible
- 10 º deg C
dew point temp at
normal pressure and
20C
Quantity of SF6/cub 10.5kg 17kg 20kg
Allowable gas
1.0 per year
leakage %
Circuit Breaker GV30M25 GV30M32 GV30P32 GV30M25D GV30M32D GV30P32D
GV30Q32 GV30Q32D
dimension
Cubicle

Width 600 800 800 600 800 800


in mm

Depth 2410 2610


Height 2140 2600
weight in
Approx.

1700 kg 2000 kg
kg

Table 1: Technical Data * Higher rating available upon request

GIS Cub Pub 1 (Rev. 10) 03/2019 2


2.3. NORMAL SERVICE
CONDITIONS FOR INDOOR

1) Ambient air temperature 3) Humidity


- -10C ~ +40C - average value of the
- maximum 24 hr average  relative humidity over 24hr
35C < 95%
- minimum ambient air - average value of vapor
temperature is -10C pressure over 24hr < 22
mbar
- maximum ambient air
temperature  40C - average value of the
relative humidity over a
2) The altitude does not month < 90%.
exceed 1000m sea level

GIS Cub Pub 1 (Rev. 10) 03/2019 3


3.0 STRUCTURAL DETAILS &
GENERAL ARRANGEMENT
3.1. CUBICLE STRUCTURE
The substation facility comprises 1) Buswire
3 or 4 (double bus system) 2) Control Circuit Compartment
compartments sealed with a 3) Front Door
1.35 kg/cm2 rated pressure SF6 4) Bus Isolator
gas and a control circuit 5) Busbar
compartment fitted with control 6) 3-position Isolator
devices mechanism and a gas 7) Test Bushing
monitor device. 8) Isolator Mechanism
9) Vacuum Circuit Breaker
The main circuit live section is 10) VCB Operating Mechanism
divided into a bus isolator 11) Current Transformer
compartment in which the bus 12) Cable Bushing
running through all the cubicles 13) Power Cable
and the isolator connected to 14) Insulator
this bus are installed. A load-
15) Pressure Gauge and in/out
side device compartment
valve
consists of a vacuum circuit
16) Earthing Bus
breaker, CTs and VTs. The bus
17) Voltage Transformer
isolator and the load-side
18) VT Disconnecting Switch
device compartments are gas-
sectionalized from each other.

3
17

2
14

18
3
R&B
Y

15
11
VCB 9
PG 10
7
2 12

Y
5
6
ON
B
8 E OFF
13

16
4

Figure 1: Sectional View for Single Bus Cubicle

GIS Cub Pub 1 (Rev. 10) 03/2019 4


3.2. TYPICAL ARRANGEMENT OF SINGLE BUS CUBICLES

R&B
Y
PG VCB

Y
ON
B
E OFF

Figure 2: Sectional View For Single Bus Cubicle

Figure 3a: Typical Single Bus Cubicle Arrangement

GIS Cub Pub 1 (Rev. 10) 03/2019 5


TYPICAL ARRANGEMENTS FOR DOUBLE BUS CUBICLES

NP1 NP1
R
R

Y 7
Y
B
B

CONTROL MODULE CONTROL MODULE

9
NP2 NP2 R
R

Y
Y
B
VCB B

R
R

Y 6
Y
ON
ON B
B
E OFF
E OFF
BUS-SECTION TRANSITION PANEL 8

NP3 NP3

FRONT VIEW SECTIONAL VIEW FOR TRANSITION PANEL


SECTIONAL VIEW FOR BUS-SECTION PANEL

NP1
R
E OFF
Y
9 ON
5
17 B

CONTROL MODULE
R&B

VCB

Y
ON
B
E OFF

NP3

FRONT VIEW SECTIONAL VIEW FOR BUS-COUPLER

Figure 3b: Typical Double Bus Cubicle Arrangement

GIS Cub Pub 1 (Rev. 10) 03/2019 6


3.3. SF6 GAS SYSTEM The pressure can also be
The gas-tight compartments checked with the pressure gauge
and the gas seals ensure long mounted to the equipment
service life. ensure that the pointer is on the
green line, as shown in figure 5.
A gas density monitor which is
temperature compensated Option: 2 stage alarm is available
provides accurate readings on at customer’s request.
the internal gas condition of the
switchgear. The pressure dial has 3 zones
3.3.1. GAS DENSITY
MONITOR - if the pointer falls in the
Each compartment is sealed green zone, it means that
with 1.35kg/cm2 (at 20 C) of the internal gas pressure is
SF6 gas, which is continuously good.
monitored by a density monitor
with a pressure switch. - if the pointer falls on the
upper red zone it means that
the internal pressure is below
the normal operating
pressure.

- if the pointer falls on the


lower red zone, it means that
the acceptable pressure is
exceeded.

Figure 4: Detail of Density Monitor

When the internal pressure


decreases to 1.25kg/cm2, the
density monitor operates its
internal contact which issues an
alarm signal to an external
lamp or buzzer. When the gas is
refilled and the internal pressure Figure 5: Detail of Pressure Pointer
exceed 1.25kg/cm2, the switch
is automatically reset.

GIS Cub Pub 1 (Rev. 10) 03/2019 7


3.3.2. THREE TYPE OF GAS MOLECULAR SIEVES
SEALING VALVE For proper working condition of
1) In/Out valve. the SF6 insulated switchgear, the
2) Temporary valve. moisture content of the gas must
3) Blanking plate valve. be kept below 150ppm.
Condensation within the gas
Each In/Out valve is attached compartment is taken care of by
with a nameplate carrying the molecular sieve, which
information on the compartment absorbs moisture.
to which the valve is mounted,
and on the normal state of the
valve. It is used for filling SF6 gas 3.3.4. GAS FILLING
to the breaker compartment Vacuuming Procedure
before despatching.
1) Replace all temporary valves
valves TV1 and TV2 (Fig 6a) at the
front of the panel with blank
plates. As you do so the Nitrogen
in the panel will be released.
IN/ OUT VALVE
BKR. COMPARTMENT

2) Open the blanking covers


Figure 6: Gas Sealing Valve from the IN/OUT valves V2, V3 and
V4 (Fig 6b) of the main busbars
Temporary valve is used for filling LHS and RHS and reserve busbars.
N2 gas to the busbar
compartment in the factory. It 3) Connect the coupling tubes
will be replaced by SF6 gas and from the gas servicing trolley (Fig
blanking plate after installation 6b)to the IN/OUT valves V2, V3
at site. and V4 (Fig 6a) of the main
busbar LHS, RHS and reserve
3.3.3. PRESSURE RELIEF DISC busbar. Make sure that they have
The bursting disc is located on been securely fastened.
the top of the breaker chamber
of every panel. For the bus 4) Check the reading on the
compartment, it is located at the GIS pressure gauge P2, P3, P4. (Fig
bus section/coupler with an 6c) shows the pressure gauge
arcing chute for the main busbar reading to be less than 1 bar at
direct arcing produced to the approximately. Temperature of
top. When the gas pressure in 30C.
the compartment exceeds
3.5kg/cm2 during an arc fault, 5) Open the IN/OUT valves V2,
this disc will burst. V3 and V4 of the main busbar LHS
and RHS and reserve busbar.

GIS Cub Pub 1 (Rev. 10) 03/2019 8


6) Rotate the selector switch ‘S’ 4) Open the SF6 gas cylinder
to position 1, so that it will be valve ‘CV’ and read the gas
connected to the vacuum pump. pressure on the cylinder pressure
gauge ‘HP’. The cylinder pressure
7) Turn the vacuum valve ‘VV’ has to be more than 10 bar. Note:
To the ON position and switch ON If the pressure is about 40 bar then
the vacuum pump ‘VP’. Now the SF6 gas cylinder is full.
vacuuming begins.
5) Loosen the coupling from the
8) Keep vacuuming until the IN/OUT valves V2, V3 and V4 of
pressure gauge reading on P2, P3, the main busbar LHS and RHS and
P4 reads less than zero (figure 6d). reserve busbar. Sufficient
loosening is necessary for the
9) After it reaches that level unwanted air to escape during
continue to vacuum for a purging.
minimum of 15 minutes. Note: the
total time for vacuuming will 6) Open the gas filling control
depend on the number panels to valve ‘GV3’ slowly. Open GV3 in
be vacuumed. such a way that the filling pressure
gauge ‘LP’ reads about 1 bar in
10) Close the IN/OUT valves V2, the beginning and increase it to
V3 and V4 of the main busbar LHS 1.4 bar. Purge the unwanted air
and RHS and reserve busbar. Turn trapped inside the tubes. Purge
the vacuum valve ‘VV’. Stop the for 5 sec and stop.
vacuum pump ‘VP’.
7) Tighten all the couplings for
11) Switch over to gas filling gas sealing. Open the IN/OUT
Immediately by rotating selector valves V2, V3 and V4.
switch ‘S’ to position 2.
8) Fill gas until the pressure
3.3.4. GAS CHARGING gauge on the GIS panel P2, P3, P4
Gas Filling Procedure reached 1.4 bar (Fig. 6e). Note:
While gas is being filled, some
‘POP’ sound may be heard. This is
1) Connect the SF6 gas cylinder
due to the sheet metal in
to the gas servicing trolley.
chamber adjusting to the increase
in pressure.
2) Rotate the selector switch ‘S’
to position 2. So that GIS will now
9) Close the IN/OUT valve V2,
be connected to SF6 Gas
V3 and V4 of the main busbar LHS,
cylinder.
RHS and reserve busbar.
3) Open the valve ‘GV1’ and
10) Close the valves ‘CV’, ‘GV1’,
valve ‘GV2’
GV2’, GV3’.

GIS Cub Pub 1 (Rev. 10) 03/2019 9


Note: If change of SF6 gas cylinder is required then close the IN/OUT valves
followed by the closing of the Gas Filling Control Valve ‘GV3’ repeat the Gas
Filling procedure (from Step 1 to Step 10).

Figure 6a: Typical General Arrangement

GIS Cub Pub 1 (Rev. 10) 03/2019 10


Figure 6b: Gas Servicing Trolley
Arrangement

Figure 6c Figure 6d Figure 6e

GIS Cub Pub 1 (Rev. 10) 03/2019 11


4.0 HANDLING AND STORAGE
4.1. PACKING AND 2) Check the packed items
UNPACKING against the packing list
attached to the crate. Any
4.1.1. SHIPPING CONDITION shortages or damage to the
The GIS panel is packed in the components should be
following crates. reported within two weeks
accompanied with a full
1) Cubicle Body ~ In principle, description of the
one or two cubicles in one missing/damaged items. Any
packing delay in making the claims will
not be entertained.
2) Foundation framework and
fastening bolts
4.2. TRANSPORT AND
3) Busbars and Aluminium Joint HANDLING
plates c/w accessories The following precautions
should be taken in moving the
4.1.2. PRECAUTIONS FOR unpacked GIS.
UNPACKING
4.2.1. PRECAUTIONS FOR
1) Unpacking should be done MOVING
carefully near the installation The equipment may be moved
site before installation. either by suspending it with a
Panel to be lifted
lifting apparatus or by hauling
with four holes with lifting trucks. The following
provided precautions should be
observed.

1) The suspension eye-bolts on


the ceiling of the cubicle may
be used for transport by cranes.
The lifting rope angle at the
hook should not be more than
120 degrees. Appropriate
strength of the rope is to be
used.

Figure 7: Lifting The Cubicle

GIS Cub Pub 1 (Rev. 10) 03/2019 12


2) When the equipment is
hauled on manual lifting truck,
be sure that the pallet is of
sufficient loading capacity.
Furthermore, do not lower the
cubicle on its edge as this may
result in mechanical damage.
The cubicle is provided with a
transportation channel base to
accommodate the fork of the
pallet truck.

3) Rollers may be used for


single units of single bus
cubicles. Use rollers more than
1.0 meter long with equal
diameters. Move the cubicle
1 meter length
carefully so that it will not tip
over.
Figure 8: Using Roller To Move Cubicle

4.3. STORAGE
The type of packing depends
on the duration and nature of
storage.

The standard cubicle packing is


meant for indoor storage where
there is no possibility of
condensation. If the equipment
after being unpacked is to be
left as it is or stored for some
period of time until the
installation commences or the
equipment after having been
installed is left idle. The cubicle
should be covered to avoid
contamination on cubicle
surface.

Figure 9: Moving of Cubicle With Pallet


Truck

GIS Cub Pub 1 (Rev. 10) 03/2019 13


5.0 INSTALLATION
5.1. CHECKS PRIOR TO
INSTALLATION
Check the order of cubicle
arrangement, quantity and
external dimensions of the
cubicle and foundation frame
according to the drawing
provided.

5.2. FOUNDATION WORK


Hack out the floor cement
surface out to a level of 50mm
below the floor level as in Figure
11a. The framework is then
seated on the sunken floor and
is anchored to the floor by Figure 11: Foundation Frame For 3 Panels
angle iron brackets. The
quantity and location as shown
in the Figure 11b.

Adjustment on the M12 anchor


bolts is required to level the
frame on which the switchgear
is to be installed. Levelling must
be done with an accurate level Figure 11a
gauge. If not level, the GIS
switchboard may be distorted,
leading to eventual failure of
the installed equipment.
Installation should be done in
the following order so that the
level errors are within an
allowable range.

Figure 11b: Foundation

GIS Cub Pub 1 (Rev. 10) 03/2019 14


5.2.1. ORDER OF
ARRANGEMENT
1) The unit of the foundation
frame is for one to three
cubicles. The frame can be
combined for a larger housing.
Any jointing of the framework
must be done only after the
leveling of both the frames is
satisfactory as detailed in
Clause 5.2.2 and the frames
are horizontally aligned as in
Clause 5.2.3.
Figure 12: Arrangement Of Foundation Frame
2) The installation of
foundation frame should begin
at the center of the cubicle
array, moving progressively
toward the left and right side
Figure 12.

3) Fastening between the


Figure 13: Level errors (front view)
cubicle and the foundation
frame is done at four
prepunched locations for each
H1: Height difference between
cubicle. The foundation frame
the frames arranged in the
is supplied with M12 foundation
cubicle width direction
bolts.
....H1 = < 0.5 mm
5.2.2. LEVELLING ERRORS H2: Height difference between
DURING INSTALLATION the left and right ends of
The foundation frame should one frame.
be installed so that the level H3: Height difference between
errors of installed bases fall the left and right ends of
within the range shown in another frame.
Figure 13 & 14. H2 < 1 mm when L < 3,000
mm
1) Front View of Foundation
Frame.  H2 + H3 < 2 mm when
the frames are
L: Length of frame in the arranged in the
cubicle width direction. cubicle width
H: Height from the level direction.
reference point to the
upper surface of the
frame to be installed first
......H + 1mm

GIS Cub Pub 1 (Rev. 10) 03/2019 15


A: Distance from the reference
point to the cubicle
installation start point
........................A < 1mm
Figure 14: Level errors (side view)
B: Distance from the reference
point to the front side of the
F: Exposed height from the frame..............B < 1 mm
floor surface to the upper
surface of the frame C: Longitudinal deviation (in the
......F < 2 front and back direction)
between the frames arranged
2) Side View of Foundation in the cubicle lateral direction
Frame. ........................C < 1 mm

H4: Height difference between D: Gap between the laterally


front and rear frames arranged, adjacent frames
....... H4 < 2mm. .........................D < 1 mm

5.2.3. HORIZONTAL 5.2.4. FOUNDATION FRAME


DEVIATIONS After the foundation frame
Horizontal deviations of frames installation is completed, fill the
in the lateral and longitudinal hollowed floor around the
directions should be within the perimeter of the frame with
range shown in Figure 15a. cement as in Figure 16.

Figure 15a: Longitudinal deviations (top Figure 15b: Cement Filling


view)

GIS Cub Pub 1 (Rev. 10) 03/2019 16


5.3. CUBICLE INSTALLATION Note the difference in thickness
between the transportation
5.3.1. LOCATION OF cover (8mm) and the actual
(12mm thick) side covers.
FASTENINGS
6) Check before mounting that
GIS is divided into unit cubicles.
the O-ring surface is neither
Parts (bolts, nuts, etc) used for
scoured nor is any foreign
installation are packed in a vinyl
matter adhering to it. Any
bag with a tag and attached
trapped foreign substance may
to the cubicle body.
result in the leakage of SF6 gas.
Apply a thin film of gel onto the
5.3.2. ORDER OF groove of the Aluminium plate
INSTALLATION and then insert the O-ring into
this groove making sure that no
1) Draw cubicle reference line sand or dirt is deposited onto
on the foundation frame. These the plate. Affix this plate onto
reference lines will serve a the side opening of the busbar
guide for more accurate compartment and then
alignment of the cubicle. proceed in the same manner
for the side opening in the
2) Remove the transportation adjacent cubicle. Fasten the
bolt on the top of the cubicle. cubicle together using M12
bolts (with a fastening torque of
3) Start installing the GIS from 450 kg-cm) making sure that
the center and moving there is a maximum gap of
outwards, toward the left and 1mm in between plate and
right. After the cubicle is cubicle. Refer to figure 17.
moved to the desired center Repeat the same procedure as
position. in item 5 & 6 for the main bus.

4) Locate the first panel onto 7) Next, using the interpanel


the centre position with the aid coupling bolts, fasten the
of a hydraulic jack, making sure lowermost jointing portions.
that its front base channel is After arranging all cubicles in
aligned to the reference line. If this way, fasten the remaining
the alignment is good, the four coupling bolts (with a fastening
foundation bolts can be quite torque of 450 kg-cm). Fasten
easily inserted into the the cubicle body to the bases.
framework holes.
8) Tighten the M12 foundation
5) Remove the transportation bolts to the appropriate torque.
seal covers from the busbar
compartment to access the
compartment for work.

GIS Cub Pub 1 (Rev. 10) 03/2019 17


5.3.3. BUSBAR COMPARTMENT SEGREGATION CUBICLE PREPARATION
AND COUPLING
Before coupling of busbar compartment segregation cubicle, the bushings must
be assembled as per the following steps:

STEP 1: The bushings must be assembled in the busbar compartment segregation


cubicle that is fitted with studs (refer Figure 16a for details) for assembly of the
bushings.

Fig 16a: Rear view of busbar compartment segregation cubicle

STEP 2: Assemble the bushings using the o-rings with the studs (refer Figure 16b) of
the cubicle using M12 hardwares (washer, spring washer & nut). Check before
mounting that the O-ring surface is neither scoured nor is any foreign matter
adhering to it. Any trapped foreign substance may result in the leakage of SF 6
gas. Apply a thin film of gel onto the groove of the bushings and then insert the
O-ring into this groove making sure that no sand or dirt is deposited onto the
bushings.

GIS Cub Pub 1 (Rev. 10) 03/2019 18


Fig 16b: Rear view of busbar compartment segregation cubicle

While assembling the bushings it needs to be ensured that the flat surface of the bushing
conductor is perpendicular to the respective phase conductors and distances are maintained as
mentioned in Figure 16c below.

Fig 16c: Bushings assembly checks.

GIS Cub Pub 1 (Rev. 10) 03/2019 19


STEP 3: After assembling the bushings, assemble the coupling flange using inner
and outer o-rings as shown in Figure 16d. Check before mounting that the O-
rings surfaces are neither scoured nor any foreign matter adhering to it. Any
trapped foreign substance may result in the leakage of SF 6 gas. Apply a thin film
of gel onto the groove of the Aluminium plate and then insert the O-ring into this
groove making sure that no sand or dirt is deposited onto the plate.

Fig 16d: Rear view of busbar compartment segregation cubicle

STEP 4: Couple the bus segregation cubicle (refer Figure 16e) as per the
instruction provided in section 5.3.2.

Fig 16e: Coupling of busbar compartment segregation cubicles

GIS Cub Pub 1 (Rev. 10) 03/2019 20


Assembly of busbar for busbar compartment segregation cubicles

The assembly of busbar for busbar compartment segregation cubicles needs to


be carried out along with the main busbar assembly. While assembling the
busbar it needs to be ensured that the flat surface of the main busbar flushes
with the flat surface of the bushing conductor and the respective phase
conductors to avoid any undue torsional stress on the bushings after assembly.

Fig 16e: Busbar assembly of busbar compartment segregation cubicles

GIS Cub Pub 1 (Rev. 10) 03/2019 21


Figure 17: Connecting the Adjacent Panel

5.3.4. CONNECTING BUSES manner as described in 5.3.2


Buses are provided at the back items 6, and mount the cover to
of each cubicle. After the the bus compartment opening
cubicle coupling is complete, by fastening M12 nuts on the
connect the buses as below. studs with a fastening torque of
450kg-cm.
1) Ensure that the connecting
surfaces of the buses are 5) After completely sealing the
cleaned with a dry & clean lint bus compartment, connect a
free cloth. Cleanliness of the vacuum pump to the gas pipe
internal parts is essential to at the front of the cubicle.
problem-free operation in Evacuate the cubicle and then
service condition. supply the specified amount of
SF6 gas into the cubicle
2) Connect the jointing portions (1.35kg/cm2).
with bolts (M12)and nuts with a
fastening torque of 450 kg-cm. 6) After SF6 gas is sealed, check
This applies for 1250A cubicle that there is no gas leakage from
coupling to 2000A/1250A the sealed portion by applying
cubicles. soap suds or using a halogen
leakage detector.
3) Before closing the covers,
conduct a further check on 7) On site test for the gas-filled
tightness of joints with contact compartments should include
resistance measurement of the the following:
complete bus. a) Hipot test of the main circuits.
b) Moisture content of gas one
4) Attach the O-ring to the seal day after gas filling.
cover for the rear bus
compartment in the same

GIS Cub Pub 1 (Rev. 10) 03/2019 22


Figure 18a: Main Busbar Fitting Figure 18b: Connecting the Buses

5.3.5. CONNECTING THE 1) The earth terminal is provided


EARTHING BUS at the left-end unit of the cubicle
The earthing bus is provided at array. Draw out the earthing
the lower back of each wire from here.
cubicle. After the cubicle and
busbar coupling is completed, 2) Determine the earthing wire
connect the earthing buses. drawout position according to
The GIS is divided into unit the separate GIS floor plan.
cubicles for easy transport as
shown in figure 20 and the 3) The earthing wire should have
earthing bus is likewise divided a minimum of 180mm2 stranded
at the same positions. bare hard copper wire.

GIS Cub Pub 1 (Rev. 10) 03/2019 23


Figure 19 : Viewed from the back

Figure 20: Assembly of The Earthing Bus

5.4. CONNECTING 5.5. CONNECTING POWER


CONTROL WIRING CABLE
The multicore cable termination Termination and connection of
for the control cable is provided the power cable should follow
at the front on the right side. the instructions of cable
Connection should be made termination manufacturer.
according to the connection
diagram given.

Precautions:

The terminals must be tightly


fastened.
Check the tightness of all
terminals before energizing.

GIS Cub Pub 1 (Rev. 10) 03/2019 24


Remove the dummy cable plug
covers from the socket.
Terminate power cable. Ensure
correct phase coordination.
Insert termination cables into
sockets located at the rear
compartment and secure with
screws. Align cable and
support cables properly to
avoid tension.
Figure 21: Lead-in Terminal Block

R
OFF
Y
ON
B

R&B

VCB

Y PLUG-IN TYPE
POWER CABLE
ON
B
E OFF

Figure 22: Plug in Method Power Cable Termination

GIS Cub Pub 1 (Rev. 10) 03/2019 25


7Theprocedure for fixing the 5.6. INSPECTION AFTER
gland plate is as below: INSTALLATION
a) The gland plate can be cut
5.6.1. GENERAL INSPECTION
into two for easy installation.

b) Measure the diameter of the 1) Check that the door can


cable. be smoothly opened and
closed.
c) Cut a semicircle on each
half of the gland plates to 2) Make sure that the bolts
match the cable diameter. and nuts that were tightened
during installation are not loose.
d) Adjust the position of the
power cable and mount the 3) Factory-tightened bolts
cable gland plates onto the and nuts are torque-marked
welded studs at the cubicle with a black paint. Check that
base plate. Tighten the nuts the marks on these fastenings
securely. are not shifted.

e) If there is any gap between 4) Check that the earthing


the power cables to fill the bars are correctly connected
gap with sealing and that the earth is connected
compound. at one point to the substation
earthing.
f) The cable screen should be
properly connected to the 5) Inspect all protection
panel earthing. relays and meters. Remove
shipping stops, if any.
Note : Connect only one end
of the cable earth and not
both. For single core cables,
there should be a gap between
the split plates and the same to
be sealed with compound. This
is to prevent eddy current
circulation.

GIS Cub Pub 1 (Rev. 10) 03/2019 26


6.0 COMMISSIONING.
This section is a guide to the 8) Check the general
minimum checks and tests that condition of the switchboard for
should be performed on site any abnormalities that will
prior to energising the affect operations.
equipment.
9) Check external equipment
6.1. PRELIMINARY CHECKS such as remote controls,
auxiliary power source and
Preliminary inspections should substation condition.
be carried out prior to the
connection of the high voltage 10) Conduct gas tightness
supply: test and measure gas condition
(dew point).
1) Check the mechanical
and electrical interlocks for 6.2. TESTING
correct operation.
Connections for pressure test
2) Check that the and primary current injection as
switchboard is earthed to the shown below. Details of the
station earthing. tests are not covered in this
section.
3) Check the gas monitors
for correct operating pressure
within the green zone.

4) Check that the control


power is on.

5) Conduct a primary
current injection on the
protection relay to ensure
functional operation with
proper test set.

6) Perform a dielectric test


on the power cables to
appropriate standards.

7) Conduct an operational
test on the panel's control and Figure 23: Pressure Test
protection system.

GIS Cub Pub 1 (Rev. 10) 03/2019 27


The cable side may be earthed
through the circuit breaker. It
can be electrically and
mechanically interlocked with
an associated circuit breaker.
For details, refer to the relevant
instruction manual.

Manual operation: Please refer


to the attached manual (and
the caution plate on the
operating device) for the
Figure 24: Primary Current Injection
operation of the Disconnecting
Switch .
6.3. START-UP
Electrical operation: As a
1) During start-up, safety
precaution for electrical
regulations should be observed.
operation, the manual
operation handle must be OUT.
2) Ensure that all the switch-
After the interlock is cancelled,
disconnectors and circuit
turn the handle of the isolator
breakers are in off position.
control switch on the front door
panel. Only one disconnecting
3) Remove any connecting
switch can be operated at any
or shorting links used during the
one time.
preliminary tests.

4) Energise the switchboard 6.4.2. Interlocks between


step-by-step, observing all signals VCB and 3-Position
and indicators. Disconnecting Switch.
The disconnecting switch
5) Check the phasing of the cannot interrupt load current .
incomers. Hence, the switch can only be
operated when the breaker is
6) Watch for any abnormalities. OFF.

6.4 SWITCHING OPERATIONS When the breaker is ON, the


mechanical and electrical
interlocks prevent the
6.4.1. 3-POSITION ISOLATION
disconnecting switch from
The 3-position disconnecting
being operated.
switch selects one of three
positions-ON, OFF and Earth by a
pair of blades.

GIS Cub Pub 1 (Rev. 10) 03/2019 28


In addition, closure of breaker is For double bus design, it is not
not possible when the possible to earth the cable if the
disconnecting switch operation is other switch is connected to the
in progress. Operation of the bus.
switches or breaker is not possible
with the shutter of the switch Motorised version of the earth
opened. switch is provided as standard
package.
PRECAUTION: The interlock system
may differ from case to case. Unless specified, only a manual
Refer to the operating system in earth switch is allocated. Any
the schematic drawings. special interlocks for earthing
operations will be shown in the
6.4.3. CIRCUIT BREAKER technical project drawings.
OPERATION
Manual operation: Refer to the
Breaker Installation Manual and
the caution plate of the operating
device for the operation of the
breaker.

Electrical operation: Turn the


local breaker control switch (TNC)
handle on the front door panel to
OFF or ON or remotely switch the
breaker. The status of the device
can be checked with the
indicators located at the front
door.

6.4.4. EARTHING OF BUS AND


SWITCHES
An interlock allows the bus to be
earthed when all the feeder
switches are disconnected from
the bus (Dead Bus Check).

This is to ensure the respective bus


is dead before earthing. This
applies to both single and double
bus design.

GIS Cub Pub 1 (Rev. 10) 03/2019 29

You might also like