S.no. Description / Items No.

Of items Length(m) Width (m) Depth (m) Total Quantity


1 Trees Falling
Girth 400 mm 4 4

2 Clearing & Grubbing 1 650 17.76 11544

3 Embankment As same as Your Total Quantity of Earthwork Calculation 2500

4 Sub Grade 500 mm


1 650 14.76 0.5 4797
Total Qty. of Sub- Grade 4797

5 GSB 150 mm
1 650 13.46 0.15 1312.35
Total Qty. of GSB 1312.35
6 Prime Coat
1 650 13.16 8554
Total Qty. of Prime Coat 8554
6 WMM
WMM -I (Bottom) 100 mm
1 650 10.6 0.1 689
WMM -II (Top) 100 mm
1 650 10.3 0.1 669.5
Total Qty. of WMM 1358.5

7 Prime Coat
1 650 10.3 6695
Total Qty. of Prime Coat 6695

8 Tack Coat
1 1000 10.3 10300
Total Qty. of Tack Coat 10300

9 DBM 50 mm
1 650 10 0.05 325
Total Qty. of Dense Bitumious Macadam 325

11 Bituminous Concrete 25 mm
1 650 10 0.04 260
Total Qty. of Bitumious Concrete 260

12 Seal Coat
1 650 10 6500
Total Qty. of Seal Coat 6500

13 Earthen Shoulder
Total Quantity of Road
1 650 12.58 0.29 2371.33
above GSB
Total Quantity of actual
1943.5
WMM, DBM & BC
Total Qty. of Earthen Shoulder 427.83
Unit

Each

Sqm

Cum

Cum
Cum

Cum
Cum

Sqm
Sqm

cum

Cum
Cum

Sqm
Sqm

Sqm
Sqm

Toe Width =Carriage way +Shoulders+( (Total Crust Layer Above it * Horizontal Slope)*2)
Cum
Cum

Cum
Cum

Sqm
Sqm
Sqm

Cum

Cum
Cum
Data L.H.S/RHS Total
Carriage way 3.5 7
Paved Shoulder 1.5 3
Earthen Shoulder 1 2
Bitumious Concrete 0.04 0.04
Dense Bitumious Macadam 0.05 0.05
WMM II 0.1 0.1
WMM I 0.1 0.1
GSB 0.15 0.15
Sub -Grade 0.5 0.5

Total Width Extended offset


Items
(L.H.S/ R.H.S) Width
Total Width

Bitumious Concrete 5 0 10
Dense Bitumious Macadam 5 0 10
WMM II 5 0.15 10.3
WMM I 5 0.3 10.6
Width Top Bottom
GSB 13.16 13.76
Sub -Grade 13.76 15.76

Crust Thickness
Bitumious Concrete 0.04
Dense Bitumious Macadam 0.05
WMM II 0.1
WMM I 0.1
GSB 0.15
Sub -Grade 0.5
Horizontal Slope 2

Toe Width =Carriage way +Shoulders+( (Total Crust Layer Above it * Horizontal Slope)*2)
S.no. Description / Items No. Of items Length(m) Width (m) Depth (m)
1 Trees Falling
Girth 400 mm 65

2 Clearing & Grubbing 1 550 17.3

3 Embankment As same as Your Total Quantity of Earthwork Calculation

4 Sub Grade
Layer -1 500 mm
1 550 14.55 0.5
Total Qty. of Sub- Grade

5 GSB 150 mm

1 550 13.575 0.15


Total Qty. of GSB

6 Dry Lean Concrete 150 mm


1 550 11 0.15
Total Qty. of Dry Lean Concrete
PVC Seperation
7
Membrane
1 550 11
Total Qty. of PVC Seperation Membrane

Pavement Quality
8 300mm
Concrete
1 550 10 0.3
Total Qty. of Pavement Quality Concrete

9 Earthen Shoulder
Total Quantity Without
Deduction of DLC and 1 550 12.675 0.45
PQC
Total Quantity of DLC
and PQC
Total Qty. of Earthen Shoulder
Tie Bars at
10 Longitudinal Joints
(16mm)
520 0.8
Total Qty. of Tie Bar
Dowel Bars at
Transversal Joints
11 (38mm)
4865 0.5
Total Qty. of Dowel Bar
12 Grove Cutting
Longitudial Cutting
L.H.S 1 550
R.H.S 1 550
Transversal Joints
137 10
Total Qty. of Grove Cutting
13 Sealant
Longitudial Cutting
L.H.S 1 550
R.H.S 1 550
Transversal Joints
137 10
Total Qty. of Sealant
Total Quantity Unit

65 Each Data
Carriage way
9515 Sqm Paved Shoulder
Earthen Shoulder
7572 Cum Pavement Quality Concrete
Dry Lean Concrete
GSB
Sub -Grade
4001.25 Cum Horizontal Slope
4001.25 Cum

Items

1119.9375 Cum Pavement Quality Concrete


1119.9375 Cum Dry Lean Concrete
Width
GSB
907.5 cum Sub -Grade
907.5 Cum

6050 Sqm Crust


6050 Sqm Pavement Quality Concrete
Dry Lean Concrete

GSB

1650 Cum Sub -Grade


1650 Cum

Toe Width =Carriage way +Shoulder+ ((Total Cru


3137.0625 Cum

2557.5 Cum

579.5625 Cum

416 M
416 M

2432.5 M
2432.5 M

550 M
550 M

1370 M
2470 M

550 M
550 M

1370 M
2470 M
L.H.S/RHS Total
3.5 7
1.5 3
1 2
0.3 0.3
0.15 0.15
0.15 0.15
0.5 0.5
1.5

Total Width (L.H.S/ Extended offset


Total Width
R.H.S) Width
5 0 10
5 0.5 11
Top Bottom
13.35 13.8
13.8 15.3

Thickness
0.3
0.15

0.15

0.5

Carriage way +Shoulder+ ((Total Crust Layer Above it * Horizontal Slope)*2)