ISOLATION PLAN – LP T&I AND CONSTRUCTION RECOMMENDED BEST PRACTICE

PURPOSE OF THIS BEST PRACTICE IS TO STANDARDIZE THE PREPARATION OF ISOLATION PLANS AND TO VERIFY THAT ALL MINIMUM ISOLATION
REQUIREMENTS ARE UNDERSTOOD AND IMPLEMENTED
SCOPE: ISOLATION PLANS SHALL BE DEVELOPED FOR MAJOR EQUIPMENT OR VESSELS WITH MULTIPLE CONNECTIONS AND SEVERAL LOW POINTS WHERE
HAZARDOUS MATERIALS MIGHT REMAIN TRAPPED, AS WELL AS FOR EQUIPMENT OPERATED AT HIGHER THAN 240V.
THIS ISOLATION PLAN SHALL BE PREPARED AND PRESENTED TOGETHER WITH LP BLIND LIST BEST PRACTICE.
NOTE: EACH BOX SHALL BE MARKED WITH AN  WHERE APPLICABLE, AND WITH AN X WHERE NOT APPLICABLE.
SECTION 1 – JOBSITE DESCRIPTION SECTION 2 – TYPE OF ISOLATIONS
Department/Plant/Project: □ Locked switch/breaker □ Mechanical block □
__ASL__________________________________________________________ Block valve
Facility/Equipment: __________Reboiler □ Single block & bleed □ Double block & bleed □
2D_________________________________________ Blinding
□ Disconnect □ Other
□ Columns □ Vessels □ Tanks/Spheres □ HEX □ FIN-FAN □ Pipeline □
_____________________________
Others___________
SECTION 3 - WORK DESCRIPTION / SCOPE – in Case of Projects, prepare an additional plan
Date: ________________ Duration: _______________________________
Describe the work to be done:
_______________________________________________________________________________________________________

____________________________________________________________________________________________________________________
_____________
SECTION 4 – ISOLATION STRATEGY (Select all that apply)
□ Regular LO/TO procedure □ Group Lockout.
□ T&I Isolation method (as per GI 6.012 Supplement #3 -
Not applicable to T&Is of Storage Tanks, Surge Vessels or Cross-Country Pipelines
SECTION 5 – EQUIPMENT ISOLATION PACKAGES AND SITE PREPARATIONS: List all T&I isolation packages.

□ Depressurizing □ Draining □ Flushing □ Purging □ Proper Disposal □ Covering sewers □ Electrical (LOCK, TAG, CLEAR and TRY)
□ Other_________
SECTION 6 – ISOLATION TRAINING REQUIREMENTS: Operations and maintenance organizations, and each contractor responsible for
implementing the isolation and lockout procedures, shall train personnel in all elements of the organization’s isolation, lockout, and use of hold
tag process – All boxes must be checked
□ LO/TO (classroom) BET #40069962 □ LO/TO (e-learning) □ Specific Organization’s LOTO and Isolation Procedures □ Other:

Saudi Aramco: Company General Use LP – Isolation Plan – Best Practice – v2 - November 2022
ISOLATION PLAN – LP T&I AND CONSTRUCTION RECOMMENDED BEST PRACTICE

______________________
SECTION 7 – ISOLATION/BLINDING EQUIPMENT: SA organizations and contractors involved with isolations activities shall provide necessary
equipment to personnel.
□ Lockable devices □ Lock/Keys □ Tags (SA Form 525) □ □ Rated Blinds (Slip, Flange, Spectacle) □ Blind Gaskets
Lockout Boxes □ Chains □ Lockout Clip □ Others: □ Fabricated Blinds (approved by local engineering) □ Others:
__________________ _________________
SECTION 8 – SHUTDOWN & START-UP PROCEDURES REFERENCES: Provide document (i.e. OIM, RIM, TIM) number and approval dates.

SECTION 9 – SAFETY CONSIDERATIONS (Select all that apply and provide specific
Description
requirements)
□ All line breaking/ equipment opening must comply with GI 2.100 – Equipment Opening /
Line Break Permit
□ Obtain all necessary work permits prior to starting the job.
□ Adhere to all steps of LOTO procedures as per GI 6.012 - Isolation, Lockout and use of hold
tags.
□ Use required PPE for the task to be performed.
□ Always use the right tools for the job, inspect them before use, and dispose them properly
if damaged.
□ Scaffold platforms used for this activity must comply with GI 8.001 – Scaffolding.
□ Any Crane used to support isolation activities must comply with GI 7.028 – Crane lift: types
and procedures.
□ All confined space entries must have a stand by man and fire watch trained and certified as
per Confine Space Entry (CSE) work permit.
□ Prepare Credible Scenarios and Perform emergency drills - i.e. Fall from heights, H2S
exposure, Confine space rescue, Fire due to pyrophoric material
SECTION 10 – P&ID DIAGRAM: General Unit/Equipment P&ID, detailed diagrams must be provided with blind list.

Saudi Aramco: Company General Use LP – Isolation Plan – Best Practice – v2 - November 2022
ISOLATION PLAN – LP T&I AND CONSTRUCTION RECOMMENDED BEST PRACTICE

SECTION 11 – PREPARATION, REVISIONS, AND APPROVALS


Name Badge # Position & Signature Date
Prepared by SA Engineering / Contractor
Reviewed by SA Operations / PMT
Reviewed by Contractor Management
Approved by SA Operations / PMT
Approved by T&I Director (as per
Supplement #3, section 2)

THIS BEST PRACTICE DOES NOT WAIVE OTHER REQUIREMENT AS PER SAUDI ARAMCO GI 6.012 OR CONSTRUCTION SAFETY MANUAL.

Saudi Aramco: Company General Use LP – Isolation Plan – Best Practice – v2 - November 2022