Shiaba Brian Final Project

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 48

PROPOSED CONSTRUCTION OF A TWO STOREY

MEN’S HOSTEL AT RAMOGI INSTITUTE OF


ADVANCED TECHNOLOGY

BRIAN SHIABA

7371010490

PRESENTED TO THE KENYA NATIONAL


EXAMINATION COUNCIL IN PARTIAL FULFILMENT
FOR THE AWARD OF DIPLOMA IN CIVIL
ENGINEERING
TABLE OF CONTENT
DECLARATION……. I
ACKNOWLEDGMENT…… ii

DEDICATION…… iii
ACKNOWLEDGMENT……. IV
ABSTRACT……… v

CHAPTER ONE: SURVEYING AND SOIL INVESTIGATION


SECTION A. : REPORT ON SOIL INVESTIGATION

SECTION B. : REPORT ON TOPOGRAPHICAL SURVEY

CHAPTERTWO : BULDING TECHNOLOGY


SECTION A. : PLANS

: FOUNDATION PLAN

: GROUNDFLOOR PLAN

: UPPER FLOOR PLAN

: ROOF PLAN

SECTION B. : ELEVATIONS : FRONT ELEVATION

: REAR ELEVATION

: RIGHT ELEVATION

: LEFT ELEVATION

: SECTION THROUGH THE BULDING and SCHEDULES

CHAPTER THREE: STRUCTURES


SECTION A. SLAB DESIGN

SECTION B. COLUMN DESIGN

SECTION C. STAIRE CASE

CHAPTER FOUR: MEASUREMENT ESTIMATION AND COSTING


SECTION A SUBSTUCTURE OF WORKS

SECTION B SQURE AND ABSTRUCT

SECTION C COST ESTIMATION

CHAPTER FIVE: MANAGEMENT


SECTION. A Critical path analysis

SECTION. B Hierarchy of management

SECTION. C Roles of different parties in management


DECLARATION

STUDENT DECLARATION

I hereby declare that this is my original work and it has never been presented to any other examination
body and should never be copied by anyone else as this is a partial fulfillment for an award of diploma
certificate in Civil Engineering.

SIGN……………………………. DATE………………………………..

BRIAN SHIABA

7371010490

BUILDING AND CIVIL DEPARTMENT

DECLARATION BY THE SUPERVISOR

The project is presented for the partial fulfillment of the requirement for the acquisition of a Diploma in
Civil Engineering submitted with my approval as project supervisor.

The project is the original work of the student and has never been submitted for examination ever before.

SIGN……………………………… DATE…………………………………

MR. TOM ONDIEK

PROJECT SUPERVISOR

BUILDING AND CIVIL DEPARTMENT

RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY


i

DEDICATION

This project is dedicated to my entire family, whom through their financial support has made this project

possible.

Second, I dedicate it to my lectures, friends who have also supported through giving a hand during the

research period.

May God bless you all.


ii

AKNOWLEGMENT

I thank God Almighty for enabling me to come this far and for his provision in the three years of college.

Secondly I want to thank my family for all support they have given me throughout all this years

I also extend my special appreciation to all my lectures, supervisor Mr. Tom Ondiek who has truly helped
me in coming up with this project up to its completion.

Thank you all.


ABSTRACT

The main purpose of this project is to construct a modern student hostels in order to solve problem
experience by students due to lack of enough accommodation.

This project comprises of the following.

a) ARCHITECTURAL DRAWING: - Drawing work schedule, plot plan, titles, legend sheets, foundation
plan, floor plan and its section plan.

b) STRUCTURAL DRAWING: - Foundation designs, column designs, staircase designs, ramp design and
suspended floors designs.

c) ESTIMATION AND COSTING: - Contains all the projects quantities.

SURVEYING: - Soil investigation and the area topography


LIST OF FIGURES

b - width of the section

d- effective depth of the tension reinforcement

h- overal depth of section

x- depth of neutral axis

z- lever arm

f- depth to the compression reinforcement

e- effective span

c- nominal cover to reinforcement

fk- characteristic load

(gk, Gk)-characteristic dead load

Qk- characteristic live load

fcu- characteristic compressive cube strength of concrete

fy- characteristic tensile strength of reinforcement

yf- partial safety factor for load

ym- partial safety factor for material strength

K- co-efficient M/fcubd^2

K'- coefficient M/fcubd^2=0.156 when resistance has not exceed 10%

M- design ultimate moment

Mu- design ultimate moment of resistance

As- Area of tension reinforcement


CHAPTER ONE
1 .0 INTRODUCTION
1 .1 BACKGROUND OF THE STUDY
The proposed project is mainly concerned with coming up and adopting the new ways
of construction.to help in designing students hostels in our institution. Inadequate
accommodation is greatest challenge in the RAMOGI INSTITUTE.

1 .2 PROJECT DEVELOPMENT
In this stage we now put in process and features that may affect the operation in the
construction so as to come up strong, spacious durable and decent structure that will last
for long periods.

1 .3 SITE INVESTIGATION
The proposed site was first visited by the project committee , the financier of the
project in order to determine soil analysis, locally available material the site location
was swampy and the ground was slightly sloping therefore dewatering must be done
first bi construction commence.

1 .4 THE TERRAIN
The topography in sited place appear to be sloping and be this require proper survey
leveling to be carried out so as to enhance proper channeling of drainage that can
allow free flow of water to avoid failures.

1. 5 OBJECTIVES
1 .5.1 GENERAL OBJECTIVES
To compare the proposed modern student hostels with the existing one and
those constructed on other nearby institution.
To determine sustainable building technologies currently used Kisumu.
To establish types building design that can be used in the institution and can be
easily adopted by student taking building technology.
To design and construct student hostel that is spacious enough.

1 .5.2 SOIL
The type of soil which was found at this location is cotton soil which by has a high
be amount of water by and be relatively weak. The Investigation involved test analysis
where we dug up a pit and realized that there was plenty of underground beneath soil
surface that lead to caving of the by pit. Despite this problem foundation will be
constructed using pad foundation I method which allows transmission of weight down
to the firm base.

CHAPTER TWO
2.0 ADVANTAGES
Help in solving any incident of difficult task in the field.
Provide more improvement in student’s communication and collaboration skills. Advances
on student’s ability to think and work independently.

2.1 DISADVANTAGES.
A lot of money is needed for construction of this project.
Time wastage, this is because ground was swampy so dewatering must be done.
Scarcity of construction materials such as sand, aggregate and cement

2.2 OBSTACLES
The exact place that the proposed project was to be erected is busy. These trees and
shrubs must be cut before setting out of the project. The area is also swampy, hence it
affects the bearing capacity of the soil.

2.2 PROBLEMS PATAINED


Since the materials required are expensive and workmanship needed is of high
standards. It will there make institution spend a lot of money when constructing this
students hostels.
The soil particles was also weak therefore constructing drainage and erecting
formwork on lose soil particles need quality personnel which is quite expensive.
Hording the site area may cover wide space in order to provide enough ground for the moving
plants hence it is recommended to have fixed plant at the site.
2.3 SITE LOCATION

Proposed students hostels are located at the far end of the institution.

2.4 CONSTRUCTION PROCESS

2.4.1 SUBSTRUCTURE
Site clearance was done first to remove trees and shrubs that was on site location
area, then 2.4.2 Setting out of building.
Excavation of the foundation trench is supposed to be dug till it reaches the firm
level since the top soil is weak. To stabilize ground around the foundation wall, a
retainingwall around it to prevent the foundation from damage by water since it’s
swampy.
The foundation trench should be dug at a depth of 1 500mm and width of 900mm
including working space. The ground beam will be introduced at the ground level to the plinth
height which two feet high.
Pits for these column bases will be dug at a specified depth since the ground is not
even stable beneath upon reaching the specific depth we shall fill a layer marram and
compact it before concrete blinding is done. Column bases will be by placed on top of
the concrete blinding then base will be covered with concrete mix 1 :2:3; leaving the column
reinforcement bars projecting upwards above the ground level.
Columns will be casted to the ground level then a beam will be introduced linking all the
columns together to form a strong foundation that will bear the loads uniformly
without failures.
The beam will rise one and half feet above the ground level, backfilling will be done
using marram then compaction around the foundation area.
Leveling will be done in the Chambers left in between linking beam before hardcore
filling is done. Blinding with marram then placement of DPM then BRC. Formwork will
beconstructed outside circumference of the foundation. After all these prepared
concrete casting will be done for the oversight slab.

2.5 SUPERSTRUCTURE
The above ground external walling will be done using natural dressed quarry stones.
The whole structure will be constructed of concrete frame. The internal partitioning will be
constructed using aluminum framing with glazing intersection for separation of internal rooms.
These will help to reduce the dead load of the building.
The upper floor will be constructed using hollow blocks. This is just done to reduce the dead
weight that is to be subjected to the ground by this building. The floor finish is to be of
terrazzo.
The roofing is to be constructed using steel for its framing and covered with corrugated iron
sheets.

2 .5.1 SURVEY AND SITE ORGANIZATION


The existing features are;
Trees
Building, examples is the old students hostels
Fish ponds
Concreting drive way to the old student hostel
The swamp and it's plantation
The student hostel building will be erected facing the direction of the classes.

CHAPTER THREE

3 .0 METHODOLOGY
3.1 MATERIAL SAMPLING AND PREPARATION

3.1 .1 CEMENT
Pozzolana cement (nguvu cement) 32.5N (N-normal setting)) complying with EN1
97part 1 was used in casting of beams .no preparation and testing was to be
necessary for the cement.

3 .1 2 River sand
Natural River sand from local rivers in Kisumu town was used in mixing the concrete
for casting the beam. Particles distribution of sand be was determined by sieze
analysis within the laboratory (BS 41 0 --- 200).

3.1 .3 NATURAL CRUSHED AGGREGATE.


Since the aggregate was not variable in the study, natural crushed from local quarry
was used for construction of all the beams (BS EN 1 2620:201 3).
3.1 .4 CONCRETE MIX DESIGN
Normal mix (C20) with the ratio of 1:1 .5:3 (BS EN206 part 1) one package of cement tone and
half package of sand to three packages of ballast.

3.2 MATERIALS PROPERTIES/TEST

3.2.1 Gradation test


Size analysis was carried out on River sand to ensure that they conform to BS EN
1 2620 ---1 997. Random sand of the aggregates was done to obtain sample sizes that
were a representative of the whole stock pile of aggregates.

3.2 .2 Compressive test


The Compressive test was carried out on concrete samples from the concrete used for
costing the beam. The Compressive test for the concrete cubes was carried according
to BSEN1 2390 3:2002
3.2.3 Slump of concrete mix
The slump of the fresh concrete was carried out according to BSEN1 2350 2:200.

3.3 THE DESIGN DEVELOPMENT.


The student hostel is designed of two floors, the ground and one upper floor. The ground floor
will accommodate 20 rooms fitted with wardrobes and study tables, reception, manager’s
office,common room, the store, laundry area and washing lines. The upper floor will include
the students rooms fitted with wardrobes and study table, washing line and laundry area. All
the waste will be discharged to manhole is then channeled to the waste storage or to public
sewer line.
All external walls will be designed to be constructed using natural block then rendered, there
will molding projections all-round the Windows. A window sill will be placed below all the
windows to help shades away the rain water.
All internal doors will be made of steel with clear glass glazing. The internal walls will be
constructed using aluminum steel glazed with clear glasses.
The building will be painted with bright white color. The white coloring will be broken out by
pink color that will be painted bellow the window sills, this is done to make it look more
attractive. Window frames are made of aluminum then glazed.
Ventilations shall be provided at the tops of window and door frame. This will cater for the air
circulation within the offices since the glasses will be fixed .The external doors will be
constructed using steel to enhance the strength of these doors hence offering
enough security.
The framed structure of this building shall be constructed of reinforced concrete which will be
thoroughly cured until it gains its final working strength. The ceiling will be done using ceiling
boards of greater thickness in order to help maintain the transmission of heat from the roof hence
maintain temperature within the rooms.
The roof will be constructed of steel framing then covered with galvanized corrugated
iron sheets .Internal painting will done using soft white paints and then plumbing and
electrical shall be done the same time as planned by electrical engineer and
mechanical engineer.

3.4 LANDSCAPING
The ground around the building shall be leveled, well compacted .flowers will be planted at
specific location around the building Grass will
also be planted at selected location within this compound.

3.5 CIVIL WORK


All the driveways and the lighting will be done correctly by preferred materials. The
driveways from main gate shall be tarmacked, guidelines marks shall be well drawn.
The car parking and all areas around the building shall be tarmacked as well. The
driveways and security lighting will be well positioned. All rain water goods will be
constructed well to ensure water collected from the roof is channeled down to drains.

3.5.1 SECTION OF THE BUILDING.


Sections of the building through the critical point for the length, side of the

building and roof details for the trusses.


CHAPTER ONE: SURVEYING AND SOIL INVESTIGATION

RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY


SUBJECT: SURVEYING SHEET
PREPARED BY:BRIAN SHIABA
PROJECT: PROPOSED CONSTRUCTION OF STUDENT HOSTELS.

SURVEYING WORKS
This was general measurement of relative position of natural and man-made features on
earth’s surface.
RECONNAISSANCE SURVEY
Reconnaissance was carried out to determine the nature of the site and its conditions etc.
This was solely to determine the problems that may arise during the construction process and
hence improvising ways of minimizing those problems.
Site investigation was done by walking around the site followed by taking the levels by using a
chain, tape and fixing pegs.
Offsets were taken by measuring instruments like chains, ranging rods, driving hammer, nails,
pegs, field book, calculator, eraser and pencil.
The area of the site was set out by use of 3.4.5 confirmed by building square method to
ascertain that the corners are at right angle.

LEVELING AND CONTOURING


This was followed by dividing the plot into grids of 10m x 10m length and width respectively.
Readings were recorded at each inter site.
The recordings were then reduced by rise and fall method with levels transferred from station
to the site location by taking back sight and foresight readings.
Interpolation was then carried out and contour map drawn using a scale of 1:100

FINDINGS
The following data was obtained as per the nature of the site:
The site seemed to be of gentle slope
The data was filled on site and recorded as 1000.00
The vegetation had some grass and rocky.

TOOLS AND EQUIPMENT USED


1. Ranging rod
Used for aligning points on the same line on a straight line

2. Theodolite
To take reading on different levels on site

3. Field Book
Include paper and pencil for recording data obtained from the readings taken on the site.
4. Tripod Stand
Used for entering the instrument of correct and convenient height.

RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY


SUBJECT: SURVEYING SHEET
PREPARED BY: BRIAN SHIABA

B.S I.S F.S RISE FALL R.L REMARKS


0.48 100.00 BM=100.00
1.12 0.64 99.36
0.90 0.22 99.58
1.84 0.39 0.51 100.09 C.P
1.26 0.58 100.67
0.81 0.45 101.12
2.26 0.40 0.41 101.53 C.P
1.12 0.14 102.67
0.75 0.37 103.04
0.22 0.57 103.57 End Point
4.48 5.96 1.01 4.21 0.64
Arithmetic checks
(B.S – F.S) = last R.L – 1st R.L = ∑Rise -∑Fall

(4.48 – 1.01) = (103.57-100.00) = (4.21-0.64)


3.57 3.57 3.57

REPORT ON SOIL INVESTIGATION

PROJECT
GEOTECHNICAL INVESTIGATION FOR PROPOSED HOSTEL FOUNDATION LOCATED AT RIAT
KISUMU

CLIENT
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY

PROJECT NO 0001\2020
TABLE OF CONTENT
Introduction

1 Sub surface exploration


2 Lab testing

3 Discussion on field and lab testing


4 Safe bearing capacities

5 Conclusions and recommendations


6 Bore log

7 Summary of test results


8 Safe bearing calculations

INTRODUCTION
Sub surface investigation and lab testing for proposed hostel project was referred by MTRD

[Materials Testing Research Division]. The objective of the work done was to determine the

Bearing soil capacity of the two story building .The machines used include drilling machine and

Also CBR machine for testing soil samples.

SUB SURFACE EXPLORATION


The actual investigation work was done on 18/02/2020 and completed on 19/02/2020

DRILLING
One borehole of 150mm diameter is drill up to a depth of 10m where caving of the borehole

Occurred, shutters were put to keep the bore hole stable.

DISTURBED SAMPLES
Disturbed representative samples were collected logged and placed in bags.

UNDISTURBED SAMPLES
They were collected in 100mm diameter thin walls from the borehole.
METHOD OF SAMPLING
Sampler is coupled together with a sampler head to form a sampling assembly. The sampler Head provide a non
–flexible connection between the sampling tube and the drill rods.

Vent holes are provided in the sampler head to allow escape of water from the top of the sampler Tube during
penetration. The sampling tubes are made free from dust and rust, coating of oil is applied on both sides, to
obtain undisturbed sample in best possible manner.

The sampler is then lowered inside the borehole on a string of rods and driven predetermined level. The

sample is first rotated with the borehole to shear the soil sample the recorded. The soil at the lower End of

the tube to a distance about 10-20 mm .After cleaning and inserting an impervious disc at each End, both

ends are sealed. If there is any air space in the sampler, it is filled with moist soil and end covered with

tight wrapper. The identification mark is made on each sample.


LABORATORY TESTS
Lab tests where started done after sampling

The following lab tests were conducted to determine physical and engineering properties of the soil;

1. particle size distribution

2. Dry density and moisture content

3 .Atterberg’s limit

4. Shear tests

FIELD DRY DENSITY


The weight of the undisturbed soil sample is done after removing paraffin, wax and loose soil. The total

Length of the soil sample is determined after deducting empty length from the total length of the sample. The
volume of the soil mass retained in the sampler is thus determined from the unknown.

The soil mass is then removed and average moisture content is determined . The empty weight of

The sampler is determined, from the empty weight of the sampler with the soil mass, the weight of the
sampler is deducted. Field dry density is then found out.

Field [Bulk] density = weight of soil mass/volume of soil

FDD = Field bulk density

1+w
PARTICLE SIZE DISTRIBUTION
The particle of sample is weighed then separated through fractions by sieve through the following sieves

100mm, 75mm, 19mm and 4.75mm.

ATTERBERGS LIMIT
Liquid and plastic limits are determined and the results are given in result sheet.

A cone penetrometer is used to determine the plasticity index of the soil

The penetration of the soil is determined by the formula

W LL =WX +0.01 [25-W][WX +15]

SPECIFIC GRAVITY
It is determined by a 50ml density bottle specific gravity = [w2-w1]/[w3-w4]

SHEAR TESTS
Tri-axial tests are done to determine the shear parameters

DISCUSSIONS ON FIELD AND LAB TEST


Sub-soil stratification

The proposed site is having a major single layer up to the depth of investigation

Layer [i] brownish yellow silt loamy soil

Layer [ii] brownish yellow loam with medium

[PI] Layer [iii] yellow hard loamy soil

SAFE BEARING CAPACITY


Looking at the soil condition and the sub-stratification and type of proposed project RCC foundation pad
is recommended along with safe bearing capacity at certain depth.

SBC based on shear


The ultimate net capacity is evaluated after taking into consideration of the shape factor and the depth
factor for the foundation. The net bearing capacity is worked out using the following equation
Q= CNcSc dc+ Q [N-1]Sqdq +0.5 By SR dr

Where c= cohesion b= width of the footing

Q = overbearing pressure Nc Nq Nr = bearing capacity

factor Y = density ScSqSr = shape factor

Dc dqdr depth factor

CONCLUTIONS AND RECOMMENDATIONS


Sub-soil stratifications of the proposed site up to the depth of the investigation is bellow

from 0.0-0.3 brownish black silt loam of high plasticity index with little gravel

From 0.3- 5.1 brownish yellow loamy soil with medium [PI]

From 5.1 m -10m brownish yellow very stiff loam soil with low

[PI] Water table was considered in the analysis of the SBC

Looking for the product RCC pad foundation is recommended along with safe bearing capacity of 2.5

Suitability of soil for backfilling. The top layer of soil has high swelling characteristics which is
not suitable for backfilling.

BORE LOG PLATE NO 1

TYPE OF BORING ; MECHANICAL DATE OF START

DIAMETER OF BORING; 150 MM, DEPTH 10 M DATE OF STOP


SECTION B
TOPOGRAPHIC REPORT
TABLE OF CONTENT

1 . Introduction

2 Application of the standard

3 Definitions

4 Research and investigation

5 The survey

6 The published result

7 Data

INTRODUCTION
Surveying works was carried at the proposed site to determine where the student hostel was to be built.
This is to determine the levels of the ground .Surveying will be carried out the position and the relevant
location of point on the earth surface .This will be accomplished by a number of ways example; chain
surveying, compass surveying and pain table surveying .The determination of areas of measurements of
directions of construction lines is achieved through traversing.

APPLICATION OF THE STARDARD


This is to show the contour of the earth surface and the positions of fixed objects. The proposed project is
to be constructed on RIAT College which is located at RIAT hills .In site we used grid method because
the site was relatively small with no obstacles and was not much undulating .The site was to be
demarcated in to grids and sports heights taken.
DEFINITIONS
The surveyor was to provide ; the main floor elevations of the building ,locations and elevations of
drainage of the surveyed parcel , description ,location and elevation of benchmark used in surveying

.Also utilities and services provided example electrical power and sewer.

RESEARCH AND INVESTIGATION


This is carried out to determine the elevation and datum of all benchmarks to be used in surveying of
the area for the proposed project.

THE SURVEY
The topographical survey was performed on the ground to obtain the full information required. The
equipment used was a theodolite and the procedure was selected by the surveyor.

DATA
The following information is to be shown on the topographical map-Existing contour lines indicating the
shape and elevation of the land

-Location of permanent structures including culverts

-The official road way names and streets

-North arrow and scale drawing

THE PUBLISHED RESULT


The topographical map should be prepared to scale, size and accuracy to clearly show the result.
CHAPTER TWO: BUILDING TECHNOLOGY

SECTION A: FOUNDATION PLAN


SECTION. B: GROUND FLOOR PLAN
SECTION. C: UPPER FLOOR PLAN
SECTION. D: ROOF PLAN
SECTION. E : ELEVATIONS

SECTION. F : SECTION THROUGH THE BUILDING.


SECTION. G: DOOR AND WINDOW SCHEDULE

CHAPTER THREE: STRUCTURES


SECTION A: SLAB DESIGN.
SECTION C: STAIR CASE DESIGN
STRUCTURAL DRAWINGS
CHAPTER FOUR: MEASURMENT ESTIMATING AND COSTING

ITEM DESCRIPTION UNIT QTY RATE AMOUNT CENTS


ELEMENT NO 1 COUNTD
A Planking and strutting ITEM 12, 000 00
Allow provision and
subsequent removal of
planking and strutting to
uphold and maintain all
faces
Concrete walls
Blinding concrete class is
mix (1:4:8) as described.
B 50mm trick to foundation SM 392 700 274, 400 00
strip
C 50mm trick to column SM 139 700 97, 300 00
bases
Removed concrete class
2020 to
D Foundation strips CM 78 8, 000 624, 000 00
E Column bases and vertical CM 27 8, 000 216, 000 00
columns
F 150mm thick floor slab SM 1089 1000 1, 089, 000 00

Formwork as described to:

G Sides of strip footing SM 784 400 313, 000 00


H Sides of column bases SM 280 400 112, 000 00
I Sides of vertical columns SM 174 400 69, 600 00
J Edges of vertical slab 75- LM 138 200 27, 600 00
150mm wide
Steel reinforcements to Bs
A482 as described
K 8mm diameter KGS 1148 150 172, 200 00
L 10mm ditto KGS 1412 150 211, 800 00
M 12mm ditto KGS 1345 150 201, 750 00
N BRC mesh A 142 SM 1072 150 160, 800 00
O 16mm diameter KGS 1089 350 381, 150 00
TOTAL CARRIED TO
COLLECTION 3, 963, 200 00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT CENTS

ELEMENT NO1
COUNTD
A 1000g proof membrane SM 1089 120 130, 680 00

B 200mm truck natural SM 981 1, 200 1, 177, 200 00


stone foundation
walling on cement sand
mortar (1:3)
C 200mm wide damp LM 654 150 98, 100 00
proof course
Painting and
decoration
Render mix 1:3 as
described
D 12mm thick cement SM 124 350 43, 400 00
render to plinths
Prepare and apply tree
coats of bituminous
paint as described:
E Rendered wall SM 124 300 37, 200 00
TOTAL CARRIED TO 1, 486, 580 00
COLLECTION
COLLECTION
Brought forward from 1, 218, 550 00
page 1
Brought forward from 3, 963, 200 00
page 2
Brought from above 1, 486, 580 00

TOTAL FOR
SUBTRUCTURE WORKS
CARRIED TO THE MAIN 6, 668, 330 00
SUMMARY
CHAPTER FIVE: MANAGEMENT

SECTION A
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY

SUBJECT: MANAGEMENT SHEET

PREPARED BY: BRIAN SHIABA

MANAGEMENT

Critical path analysis works out sheet

Events Activity Duration Description

0-1 A 5 Site clearance

1-2 B 2 Excavation

1-3 C 3 Substructure works

2-3 D 4 Curving

3-4 E 4 Superstructure

4-5 F 12 Curing

3-6 G 3 Formwork to column

5-7 H 2 Walling

5-8 I 3 Roof elevation

6-7 - - Dummy
6-11 Y 2 Stone work

7-10 K 4 Eaving and painting

8-9 L 2 Painting and steel work

9-10 - - Dummy

9-13 M 3 Fittings and finishing

10-12 N 6 Floor/ceiling finishing

11-13 O 3 Plastering

12-13 P 5 Painting including internal finish

13-14 Q 4 Finish -water disposal

SECTION. B
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY

MANAGEMENT SHEET

SUBJECT: HIERARCHY OF MANAGEMENT

PREPARED BY: BRIAN SHIABA

CLIENT

LOCAL AUTHORITY ARCHITECTURE


STRUCTURAL
ENGINEER

CLERKS OF WORK QUANTITY SURVEYOR

CONTRACTOR

Sub-contractor Supplier Technician


SECTION. C
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY

MANAGEMENT SHEET

SUBJECT: ROLES OF DIFFERENT PATIES IN HIERARCHY

PREPARED BY: BRIAN SHIABA

CLIENT

Finances the project


Approve stages of construction in any scope of work
Controls the project resources
Arrange the maintenance of the complete building

LOCAL AUTHORITIES

National construction authority (NCA)


Architectural association of Kenya (AAK)
Kenya bureau of standard (KEBS)

NATIONAL CONSTRUCTION AUTHORITY

Assist in the exploitation construction services


Prescribe the qualification for registration under the government act
Promote and stimulate, improve and expansion of construction industry

ARCHITECTUAL ASSOCIATION OF KENYA

Create revenue generating construction services


Publish document and publication for the benefit of member of the association
Create public awareness by marketing the services of members profession
KENYA BUREAU OF STANDARD

Promote standardization in industries and commerce


Test goods destined for export for the purpose of certification
Prepare frame or armed specification and codes of practice

ARCHITECT

Access the client


Prepare a plan sketch
Prepare final working drawing
Acquire construction team

STRUCTURAL ENGINEER

Concern with the strength and stability and economy of the project
Prepare structural working drawing for the project

QUANTITY SURVEYOR

Check tender for accuracy


Prepare bill of quantity from the working drawing
Prepare payment certificate
Caries out monthly evaluation of the project progress

RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY

MANAGEMENT SHEET

SUBJECT: SUBJECT: ROLES OF DIFFERENT PATIES IN HIERARCHY

PREPARED BY: BRIAN SHIABA

CLERK OF WORKS
Represents the client on the site

CONRACTOR/BUILDER

Interprets plan and ensure the construction project is done as architect


requirements
Ensure all payments is done to the operatives
Handed over the key to the client upon completion of the construction project

SUPPLIER

Vendors who contract to supply the material for the project within the project
specification and schedule.

SUB-CONTRUCTOR

Specialty contractor who contracts with the prime contractor to conduct specific
portion of the project with the overall project schedule

TECHNICIAN

Operate and help in repair of the machine/plants i.e. mixer plant

OPERATIVES

Skilled and unskilled labors that carry out different duties on site i.e. plumbers,
electricians, masons, carpenters and helpers.
RECOMMENDATION

I hereby recommend that this project of proposed student


hostels is appropriate to be established in the suggested site
that had been proposed with RAMOGI INSTITUTE OF ADVANCED
TECHNOLOGY. This will ensurethat there will be enough
accommodation within the institution.

You might also like