Professional Documents
Culture Documents
Shiaba Brian Final Project
Shiaba Brian Final Project
Shiaba Brian Final Project
BRIAN SHIABA
7371010490
DEDICATION…… iii
ACKNOWLEDGMENT……. IV
ABSTRACT……… v
: FOUNDATION PLAN
: GROUNDFLOOR PLAN
: ROOF PLAN
: REAR ELEVATION
: RIGHT ELEVATION
: LEFT ELEVATION
STUDENT DECLARATION
I hereby declare that this is my original work and it has never been presented to any other examination
body and should never be copied by anyone else as this is a partial fulfillment for an award of diploma
certificate in Civil Engineering.
SIGN……………………………. DATE………………………………..
BRIAN SHIABA
7371010490
The project is presented for the partial fulfillment of the requirement for the acquisition of a Diploma in
Civil Engineering submitted with my approval as project supervisor.
The project is the original work of the student and has never been submitted for examination ever before.
SIGN……………………………… DATE…………………………………
PROJECT SUPERVISOR
DEDICATION
This project is dedicated to my entire family, whom through their financial support has made this project
possible.
Second, I dedicate it to my lectures, friends who have also supported through giving a hand during the
research period.
AKNOWLEGMENT
I thank God Almighty for enabling me to come this far and for his provision in the three years of college.
Secondly I want to thank my family for all support they have given me throughout all this years
I also extend my special appreciation to all my lectures, supervisor Mr. Tom Ondiek who has truly helped
me in coming up with this project up to its completion.
The main purpose of this project is to construct a modern student hostels in order to solve problem
experience by students due to lack of enough accommodation.
a) ARCHITECTURAL DRAWING: - Drawing work schedule, plot plan, titles, legend sheets, foundation
plan, floor plan and its section plan.
b) STRUCTURAL DRAWING: - Foundation designs, column designs, staircase designs, ramp design and
suspended floors designs.
z- lever arm
e- effective span
K- co-efficient M/fcubd^2
1 .2 PROJECT DEVELOPMENT
In this stage we now put in process and features that may affect the operation in the
construction so as to come up strong, spacious durable and decent structure that will last
for long periods.
1 .3 SITE INVESTIGATION
The proposed site was first visited by the project committee , the financier of the
project in order to determine soil analysis, locally available material the site location
was swampy and the ground was slightly sloping therefore dewatering must be done
first bi construction commence.
1 .4 THE TERRAIN
The topography in sited place appear to be sloping and be this require proper survey
leveling to be carried out so as to enhance proper channeling of drainage that can
allow free flow of water to avoid failures.
1. 5 OBJECTIVES
1 .5.1 GENERAL OBJECTIVES
To compare the proposed modern student hostels with the existing one and
those constructed on other nearby institution.
To determine sustainable building technologies currently used Kisumu.
To establish types building design that can be used in the institution and can be
easily adopted by student taking building technology.
To design and construct student hostel that is spacious enough.
1 .5.2 SOIL
The type of soil which was found at this location is cotton soil which by has a high
be amount of water by and be relatively weak. The Investigation involved test analysis
where we dug up a pit and realized that there was plenty of underground beneath soil
surface that lead to caving of the by pit. Despite this problem foundation will be
constructed using pad foundation I method which allows transmission of weight down
to the firm base.
CHAPTER TWO
2.0 ADVANTAGES
Help in solving any incident of difficult task in the field.
Provide more improvement in student’s communication and collaboration skills. Advances
on student’s ability to think and work independently.
2.1 DISADVANTAGES.
A lot of money is needed for construction of this project.
Time wastage, this is because ground was swampy so dewatering must be done.
Scarcity of construction materials such as sand, aggregate and cement
2.2 OBSTACLES
The exact place that the proposed project was to be erected is busy. These trees and
shrubs must be cut before setting out of the project. The area is also swampy, hence it
affects the bearing capacity of the soil.
Proposed students hostels are located at the far end of the institution.
2.4.1 SUBSTRUCTURE
Site clearance was done first to remove trees and shrubs that was on site location
area, then 2.4.2 Setting out of building.
Excavation of the foundation trench is supposed to be dug till it reaches the firm
level since the top soil is weak. To stabilize ground around the foundation wall, a
retainingwall around it to prevent the foundation from damage by water since it’s
swampy.
The foundation trench should be dug at a depth of 1 500mm and width of 900mm
including working space. The ground beam will be introduced at the ground level to the plinth
height which two feet high.
Pits for these column bases will be dug at a specified depth since the ground is not
even stable beneath upon reaching the specific depth we shall fill a layer marram and
compact it before concrete blinding is done. Column bases will be by placed on top of
the concrete blinding then base will be covered with concrete mix 1 :2:3; leaving the column
reinforcement bars projecting upwards above the ground level.
Columns will be casted to the ground level then a beam will be introduced linking all the
columns together to form a strong foundation that will bear the loads uniformly
without failures.
The beam will rise one and half feet above the ground level, backfilling will be done
using marram then compaction around the foundation area.
Leveling will be done in the Chambers left in between linking beam before hardcore
filling is done. Blinding with marram then placement of DPM then BRC. Formwork will
beconstructed outside circumference of the foundation. After all these prepared
concrete casting will be done for the oversight slab.
2.5 SUPERSTRUCTURE
The above ground external walling will be done using natural dressed quarry stones.
The whole structure will be constructed of concrete frame. The internal partitioning will be
constructed using aluminum framing with glazing intersection for separation of internal rooms.
These will help to reduce the dead load of the building.
The upper floor will be constructed using hollow blocks. This is just done to reduce the dead
weight that is to be subjected to the ground by this building. The floor finish is to be of
terrazzo.
The roofing is to be constructed using steel for its framing and covered with corrugated iron
sheets.
CHAPTER THREE
3 .0 METHODOLOGY
3.1 MATERIAL SAMPLING AND PREPARATION
3.1 .1 CEMENT
Pozzolana cement (nguvu cement) 32.5N (N-normal setting)) complying with EN1
97part 1 was used in casting of beams .no preparation and testing was to be
necessary for the cement.
3 .1 2 River sand
Natural River sand from local rivers in Kisumu town was used in mixing the concrete
for casting the beam. Particles distribution of sand be was determined by sieze
analysis within the laboratory (BS 41 0 --- 200).
3.4 LANDSCAPING
The ground around the building shall be leveled, well compacted .flowers will be planted at
specific location around the building Grass will
also be planted at selected location within this compound.
SURVEYING WORKS
This was general measurement of relative position of natural and man-made features on
earth’s surface.
RECONNAISSANCE SURVEY
Reconnaissance was carried out to determine the nature of the site and its conditions etc.
This was solely to determine the problems that may arise during the construction process and
hence improvising ways of minimizing those problems.
Site investigation was done by walking around the site followed by taking the levels by using a
chain, tape and fixing pegs.
Offsets were taken by measuring instruments like chains, ranging rods, driving hammer, nails,
pegs, field book, calculator, eraser and pencil.
The area of the site was set out by use of 3.4.5 confirmed by building square method to
ascertain that the corners are at right angle.
FINDINGS
The following data was obtained as per the nature of the site:
The site seemed to be of gentle slope
The data was filled on site and recorded as 1000.00
The vegetation had some grass and rocky.
2. Theodolite
To take reading on different levels on site
3. Field Book
Include paper and pencil for recording data obtained from the readings taken on the site.
4. Tripod Stand
Used for entering the instrument of correct and convenient height.
PROJECT
GEOTECHNICAL INVESTIGATION FOR PROPOSED HOSTEL FOUNDATION LOCATED AT RIAT
KISUMU
CLIENT
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY
PROJECT NO 0001\2020
TABLE OF CONTENT
Introduction
INTRODUCTION
Sub surface investigation and lab testing for proposed hostel project was referred by MTRD
[Materials Testing Research Division]. The objective of the work done was to determine the
Bearing soil capacity of the two story building .The machines used include drilling machine and
DRILLING
One borehole of 150mm diameter is drill up to a depth of 10m where caving of the borehole
DISTURBED SAMPLES
Disturbed representative samples were collected logged and placed in bags.
UNDISTURBED SAMPLES
They were collected in 100mm diameter thin walls from the borehole.
METHOD OF SAMPLING
Sampler is coupled together with a sampler head to form a sampling assembly. The sampler Head provide a non
–flexible connection between the sampling tube and the drill rods.
Vent holes are provided in the sampler head to allow escape of water from the top of the sampler Tube during
penetration. The sampling tubes are made free from dust and rust, coating of oil is applied on both sides, to
obtain undisturbed sample in best possible manner.
The sampler is then lowered inside the borehole on a string of rods and driven predetermined level. The
sample is first rotated with the borehole to shear the soil sample the recorded. The soil at the lower End of
the tube to a distance about 10-20 mm .After cleaning and inserting an impervious disc at each End, both
ends are sealed. If there is any air space in the sampler, it is filled with moist soil and end covered with
The following lab tests were conducted to determine physical and engineering properties of the soil;
3 .Atterberg’s limit
4. Shear tests
Length of the soil sample is determined after deducting empty length from the total length of the sample. The
volume of the soil mass retained in the sampler is thus determined from the unknown.
The soil mass is then removed and average moisture content is determined . The empty weight of
The sampler is determined, from the empty weight of the sampler with the soil mass, the weight of the
sampler is deducted. Field dry density is then found out.
1+w
PARTICLE SIZE DISTRIBUTION
The particle of sample is weighed then separated through fractions by sieve through the following sieves
ATTERBERGS LIMIT
Liquid and plastic limits are determined and the results are given in result sheet.
SPECIFIC GRAVITY
It is determined by a 50ml density bottle specific gravity = [w2-w1]/[w3-w4]
SHEAR TESTS
Tri-axial tests are done to determine the shear parameters
The proposed site is having a major single layer up to the depth of investigation
from 0.0-0.3 brownish black silt loam of high plasticity index with little gravel
From 0.3- 5.1 brownish yellow loamy soil with medium [PI]
From 5.1 m -10m brownish yellow very stiff loam soil with low
Looking for the product RCC pad foundation is recommended along with safe bearing capacity of 2.5
Suitability of soil for backfilling. The top layer of soil has high swelling characteristics which is
not suitable for backfilling.
1 . Introduction
3 Definitions
5 The survey
7 Data
INTRODUCTION
Surveying works was carried at the proposed site to determine where the student hostel was to be built.
This is to determine the levels of the ground .Surveying will be carried out the position and the relevant
location of point on the earth surface .This will be accomplished by a number of ways example; chain
surveying, compass surveying and pain table surveying .The determination of areas of measurements of
directions of construction lines is achieved through traversing.
.Also utilities and services provided example electrical power and sewer.
THE SURVEY
The topographical survey was performed on the ground to obtain the full information required. The
equipment used was a theodolite and the procedure was selected by the surveyor.
DATA
The following information is to be shown on the topographical map-Existing contour lines indicating the
shape and elevation of the land
ELEMENT NO1
COUNTD
A 1000g proof membrane SM 1089 120 130, 680 00
TOTAL FOR
SUBTRUCTURE WORKS
CARRIED TO THE MAIN 6, 668, 330 00
SUMMARY
CHAPTER FIVE: MANAGEMENT
SECTION A
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY
MANAGEMENT
1-2 B 2 Excavation
2-3 D 4 Curving
3-4 E 4 Superstructure
4-5 F 12 Curing
5-7 H 2 Walling
6-7 - - Dummy
6-11 Y 2 Stone work
9-10 - - Dummy
11-13 O 3 Plastering
SECTION. B
RAMOGI INSTITUTE OF ADVANCED TECHNOLOGY
MANAGEMENT SHEET
CLIENT
CONTRACTOR
MANAGEMENT SHEET
CLIENT
LOCAL AUTHORITIES
ARCHITECT
STRUCTURAL ENGINEER
Concern with the strength and stability and economy of the project
Prepare structural working drawing for the project
QUANTITY SURVEYOR
MANAGEMENT SHEET
CLERK OF WORKS
Represents the client on the site
CONRACTOR/BUILDER
SUPPLIER
Vendors who contract to supply the material for the project within the project
specification and schedule.
SUB-CONTRUCTOR
Specialty contractor who contracts with the prime contractor to conduct specific
portion of the project with the overall project schedule
TECHNICIAN
OPERATIVES
Skilled and unskilled labors that carry out different duties on site i.e. plumbers,
electricians, masons, carpenters and helpers.
RECOMMENDATION