Professional Documents
Culture Documents
Daisy Ochieng Final Project.
Daisy Ochieng Final Project.
1|
|Page
Table of Contents
DECLARATION ................................................................................................................................................... 4
DEDICATION ...................................................................................................................................................... 5
ACKNOWLEDGEMENT ....................................................................................................................................... 6
PREFACE ............................................................................................................................................................ 7
ABSTRACT ......................................................................................................................................................... 8
CONCLUSION ................................................................................................................................. 17
INTRODUCTION ......................................................................................................................... 18
CHAPTER ONE................................................................................................................................ 19
Temperature starting from 2018-2021 ..................................................................................... 20
INVESTIGATION ................................................................................................................. 21
SOIL INVESTIGATION ................................................................................................................. 22
ATTERBERG LIMIT.................................................................................................................. 22
PROCTOR COMPACTION TEST .............................................................................................. 22
BENCHMARK ......................................................................................................................... 22
ARCHITECTURAL DESIGN AND CONSTRUCTION Feasibility Test .......................................... 23 b)
2|Page
|Page
Roofing
.............................................................................................................................. 23
e) Ventilation ........................................................................................................................
23
f) Lighting
.............................................................................................................................. 24
3
FRONT ELEVATION ........................................................................................................................ 27
RIGHT ELEVATION ......................................................................................................................... 28
SECTION......................................................................................................................................... 29
3|Page
|Page
Appendix ............................................................................................................................... 77
DECLARATION
I declare that this project is my own work and that no part of this work should Be
duplicated or transmitted either by electronic method or by photocopying.
Name DAISY ANYANGO OCHIENG
Index 737101/0469
Signature………………………………………………….
Date…………………………………………….
BUILDING AND CIVIL ENGINEERING
Supervisor: I declare that work done by the candidate was done under my supervision.
Signature ………………………………………….
Date…….………………………………………
Name MR TOM ONDIEK
BUILDING AND CIVIL ENGINEERING
4|Page
|Page
DEDICATION
I dedicate this project to my dad, my Mum and my Daughter AALIYAH
FANCY HADASSAH
for their support throughout the course
5|Page
|Page
ACKNOWLEDGEMENT
I give my sincere gratitude’s to my project supervisor Mr. Tom Ondiek for
his tireless efforts and guidance during the preparation of this project. I
6|Page
|Page
PREFACE
The main objective of this project is to present what I have learnt throughout the course
(Diploma in Civil Engineering) for the last three years and practical aspect In building and
construction field. It involves a wide field of economics and design
7|Page
|Page
ABSTRACT.
The proposed project is to be constructed at Ramogi Institute of Advanced
Technology. The structure will be constructed to curb overpopulation, to provide
comfortable learning environment for the Students within Riat community.
1 .2 PROJECT DEVELOPMENT
At this stage we put into consideration the processes and features
that may hinder the construction operation process. All the necessities
shall be put into consideration to ensure that the structure is strong
spacious durable, decent and also meet the standard limit.
SURVEYING WORKS. This is the accurate measuring of relatively large
scale of earth’s surface. It uses geometry to measure angles on the earth’s
surface
8|Page
|Page
CHAPTER ONE
SURVEYING WORK
Introduction
The project is located 1.5KM off Kisumu-Kakamega highway. The client require a two
storey library.
SITE SURVEYING
Trees
Landscape
Adjacent buildings
OBJECTIVES
1. To establish a building complex that set a standard within the entire region and Kenya at
large.
2. To compare the proposed modern library based on the competency based curriculum
which has been newly adopted by the government of Kenya.
3. To determine sustainable building technologies currently used by new curriculum 4. To
establish types building design that can be used in the institution and can be easily adopted
by student taking building technology.
9|Page
|Page
5. To design and construct block that is spacious enough, accessible and well located.
6. To meet my expectations as an engineer
10 | P a g e
Page
SCOPE
This has been done through research in laboratory and interviews among professionals
who really assisted in the research.
Due to rapid growth of population in Riat college the client has seen it worth to put up an
advanced library to curb the overcrowding.
LOCATION
The proposed project will be located within Riat College which is 1.5KM off
KisumuKakamega highway.
TOPOGRAPHY
P e
11 |
|Page
Rainfall in MM
12 | P a g e
|Page
The temperature range from 24Co-29Co during the day time and 6Co-11Co during the
night.
SITE INVESTIGATION
The proposed project was first visited by the project committee and the financier of the project in
order to determine soil analysis.
P e
The ground was swampy hence dewatering must be done before construction commence using
appropriate method.
ag
22
SOIL INVESTIGATION
The exercise commenced with excavation of trial pits which was done manually
whereby four trial pits were excavated to the depth of 1m spread within the actual
spot around the selected construction site.
The top vegetable soil was stripped off to a depth of 200mm and then the
SOIL CLASSIFACATION
13 |
|Page
SIEVE ANALYSIS
The main objective for this test was to quantitavely determine the particle size, distribution in the
sample often dried soil.
ATTERBERG LIMIT
It is the upper and lower limits of the range of water content over which the solid exhibit referred
to as liquid and plastic limit respectively.
PROCTOR COMPACTION TEST
It is a method of soil compaction done to reduce the air voids by packing together the soil particles.
BENCHMARK
A temporary benchmark was established by using the survey benchmark by Kenya Survey.
Benchmark and the height above the sea level was 1000M. We started by a temporary
benchmark of 5M away from the main corner of the site.*-+
23
14 | P a g e
|Page
The site was fairly leveled hence only vegetation cover was removed thus no much
expenses were incurred.
a) Foundation
b) Ground Floor
The design is based on the function of the structure thus the following were adapted to wear and
tear;
• Approved DPM
P e
c) Walling
Solid concrete blocks with wall plates reinforcements every three courses
d) Roofing
• Timber has been adapted for all roofing members with the designed various sizes coated
with anti-termite paste.
• Pre-painted galvanized corrugated iron sheets have been adopted spanning tussles for
their fabrications.
e) Ventilation
• Ventilation pipes with mosquito and insects traps have been provided in all a g
openings on the walls.
24
15 |
|Page
f) Lighting
• Structures of lighting have been positioned in such a way to access natural light through its
openings.
g) Thermal Insulation
Solid concrete block walls adopted to minimize the passage of heat from the picture face of the
interior part of the buildings.
h) Sound Insulation
• The solid concrete slab prevents the transfer of sound from one floor to another. Also the
200mm solid concrete way ward a sound insulate. i) Finishes
• Ceramic tiles sizes 150*150*6mm thick to be a height of 1.2m above to be provided in the WCS.
16 | P a g e
|Page
25
CHAPTER TWO
17 | P a g e
|Page
26
18 | P a g e
|Page
REAR ELEVATION
27
19 | P a g e
|Page
FRONT ELEVATION
LEFT ELEVATION
20 | P a g e
|Page
28
RIGHT ELEVATION
21 | P a g e
ROOF PLAN
Page
29
|P e
SECTION
mortar 1:3
2 9
. 100 ag
30 |
ROOF PLAN
Page
|P e
30 ag
|P e
|P e
|Page
32
CHAPTER THREE
3
|Pag
4
|Pag
5
|Pag
33
6
|Pag
7
|Pag
35
8
|Pag
9
|Pag
10
|Pag
11
|Pag
12
|Pag
13
|Pag
310
ge
14
|Pa
ge
15
|Pa
16
|Pa
17
|Pa
312
ge
18
|Pa
19
|Pa
313 g e
20
|Pa
21
|Pag
517 | P a e
|Pag
315
|Pag
516 | P a
Task 2 structural working drawings
FOUNDATION PAD
Column
|Pag
519 | P a e
516
Beam
Suspended slab
|Pag
518
Stair case
|Pag
521 | P a e
522 | P a e
519
CHAPTER FOUR
MEASUREMENT
BILL OF QUANTITY
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
(Ksh)
523 | P a e
|Pag
524 | P a e
ELEMENT NO. 1 PROPOSED
RIAT LIBRARY
SUBSTUCTURES
SUBSTRUCTURES(ALL
PROVISIONAL)
Excavations
Clear site of all vegetation and
burn all the arising
Excavate over site to reduce
levels average 150mm deep
and cart the soil away from site
A Excavate for strip foundation
commencing from reduced SM
B level not exceeding 1.50m
deep.
CM
Excavate for column pits
commencing from reduced
level and not exceeding 1.50m
C deep.
Extra over for excavation in 2080
rock. CM
300 40
Disposal of excavated
83,200.00
materials
D 270
CM 81,000.00
Return fill and ram selected
170
excavated materials around
foundation
Remove excavated materials 200
E from as directed 34,000.00
CM
200
180 36,000.00
F
CM 15
age
2000 30,000.00
55 300 16,500.00
525 | P a e
|Pag
CM
G
5 7| 80 250 20,000.00
P
526 | P a e
521 |Pagag
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
527 | P a e
528 | P e
APPROVED HARDCORE
C Approved hardcore compacted and 290 1100 319,000.00
watered in layers 150mm. CM
Concrete works
Mass concrete class 15(1:3:6) mix as 162 600 97,200.00
described in; SM
50mm thick building under strip
footing
I
162 700 113,400.00
Ditto column bases SM
Carried to collection
835,650.00
KSHS
529 | P e
522 |Pagag
ALL PROVISIONAL
Supply and fix steel reinforcement KG 150 345 51,750.00
F including cutting, bending, hooking,
tying and supporting as required.
G High yield tensile square twisted bars SM 120 300 36,000.00
to B.S
4461
H Assorted reinforcement bars of
various sizes Mesh fabric SM 155 250 38,750.00
I reinforcement to B.S 4483 set in
concrete with 300mm side end slab
J
High yield tensile square twisted bars SM 120 350 42,000.00
K B.S 4461
SM 150 400 60,000.00
SAWN TIMBER FORMWORK
To: 150 400 60,000.00
SM
Side of strip foundation
89 89 7,921.00
LM
Side of column bases
Side of columns
60 ag
61 Page
Carried to collection
4,486,921
Collection Page
61 ag
|P e
63 | P a g e
62 ag
CALCULATION AMOUNT
|P e
64 | P a g e
SH CTS
EXCAVATIONS
Build up unit rates (m) for exc commencing from stripped level and not
exceeding 1.5m for substructure work
TOTAL EXCAVATIONS
CALCULATION AMOUNT
63 |
Pa
g
e
66 | P a g e
|P e
67 | P a g e
SHS CTS
¾ to be machine excavation
¼ to be manual excavation
Soln
Value of excavation by machine
=3/4 *71400=m535.5
68 | P a g e
CALCULATION AMOUNT
64 |Page
69 | P a g e
SHS CTS
Actual output
535.5/1000 x 24=12.852m2/hr
535.5/12.852 =41.666hrs
Hire rate/hr
=500+400 =900/=
|Page
70 | P a g e
=192,780+37,503=230,283
66
71 |
CALCULATION AMOUNT CTS
Duration 2days
67
CALCULATION AMOUNT
P e
|
72 | P a g e
Cement
1m x1982.458=800/50 =31719.309
68 ag
CALCULATION AMOUNT
|Page
73 |
P age
48,848 15
Total ratio 1+4+8=13
2x2 x 100=400
640+400=1040
69 P e
ag
CALCULATION AMOUNT
|
74 | P a g e
SHS CTS
TOTAL COST OF MATERIAL AND LABOUR
=1040 +250 1290
Add 30% overheads and profits 387 00
30/100 x 1290 =387
Mixing 8 hoisting
Hiring cost for a mixer and a hoister = 15,000 per day for both. Working
8hrs/day.
15000/8=1875
Running cost
-Assume 20liters of fuel per day@ 100
-Lubricant 3Kg/day@ 400
2275 00
70 ag
CALCULATION AMOUNT
P e
|Page
75 |
SHS CTS
Total hiring plus running cost output of mixer. Assume it to be 0.2m3 per
cycle
1 cycle=2mm
? 60mm
60/2=30
0.2 x 30 =6m3
380 00
2275/6 =379.17
Formwork
CALCULATION AMOUNT
71
|
76 | P a g e
SHS CTS
Solution:-
Length=300
Total area 300 x 1.5=450
Area of timber -200/1000x750/1000=0.015
Total 4000+3,000,000=3,004,000
72
CALCULATION AMOUNT
SHS CTS
|Page
77 | P a g e
Labor
2skilled@100
2unskilled@50
Total =300
Reinforcement
Assorted sizes(418+440+632)=1490Kg
Assume 1Kg@150
73
|Page
78 | P a g e
Site organization
Is a detailed and well thought out process which ensures a healthy and a safe construction site throughout its
build.
Site layout- it shows a detailed layout of the whole site and the relationship of the proposed work
with the boundary of the property, nearby road and neighboring building.
|Page
79 | P a g e
74
Plan, coordinate and oversee the technical and engineering activities of the organization.
Provide supervision and guidance to other engineers Oversee efficient running of the
project
They create a buying strategy that takes into account the company’s budget and necessary
supplies and then find matching vendor.
Oversees the project’s revenues and expenses to ensure its stays within the budget.
They provide input to management for how the organization can improve its operation to
meet its needs.
Support smooth running of offices by carrying out clerical tasks and projects.
|Page
80 | P a g e
2. Disposal of water planking and Manually two skilled and 1 Commence after
strutting four unskilled excavation
|Page
81 | P a g e
10. Formwork to slab side S.S.W and apply Two skilled and 2
mould oil manually eight unskilled
76
12. Ground floor block work Machinery and Ten unskilled, 4
manually two operators
and one tilting
drum mixer
Appendix
2. Cone –concrete
3. Fwk –formwork
6. exc –excavation
7. fdn –foundation
9. B.S-Back site
|Page
82 | P a g e
77 78
|Page