Water supply liine juma Gabool
Water supply liine juma Gabool
= 3477938
PART A
Total = 120398
4 Add contigency
2% x 120398 = 2408
Total = 122806
CONSTRUCTION / INSTALLATION OF TUBEWELL FOR DRINKING
PURPOSE IN JUMA KHAN GABOOL UCSANN TALUKA MANJHAND
DISTRICT JAMSHORO.
PART A
TubeWell Boring
1 Boring for tube well in water bearing soil from G.I upto 100'ft
or 30.05 m depth i/c sinking and with drawing of casing pipe
(P.H.S.I No:1,P/36)
6 inch
2 Boring for tube well in water bearing soil from depth 100 to 200'ft
or 30.51 to 61 m below ground level including sinking with drawing
of casing pipe (P.H.S.I No:2,P/36)
6 inch
3 Boring for tube well in water bearing soil from depth 200 to 300'ft
or 60.01 to 91.50 m below ground level including sinking with drawing
of casing pipe (P.H.S.I No:3,P/36)
6 inch
TOTAL 101347
CONSTRUCTION / INSTALLATION OF TUBEWELL FOR DRINKING
PURPOSE IN JUMA KHAN GABOOL UCSANN TALUKA MANJHAND
DISTRICT JAMSHORO.
Part B
3 Add Premiu 1
Total = 886802
4 Add contigency
2% x 886802 = 17736
Total = 904538
Construction/ installation of tube well for drinking purpose in
village Juma Khan Gabool UC Sann Taluka Manjhand District
Jamshoro
PART B
TubeWell Boring
1 Boring for tube well in water bearing soil from G.I upto 100'ft
or 30.05 m depth i/c sinking and with drawing of casing pipe
(R.A IS ATTACHED)
15 inch dia
1 X 100.00 RFT = 100
2 Boring for tube well in water bearing soil from Ground level 100 to 200'ft
or 30.51 to 61 m depth including sinking with drawing of casing pipe
(R.A IS ATTACHED)
15 inch dia
3 Boring for tube well in all water bearing soil from Ground level 200 to 300'ft
or 60.01 to 91.50 m below ground level including sinking with drawing
of casing pipe ( R.A IS ATTACHED)
15 inch dia
5 Taking & preserving in box 2 Ibs (1 kg) sample of strats from bore holes
(P.H.S.I No:7,P/3)
300 / 10 = 30
6 Taking samples of water from bore holes and placing in two separate bottles.
(P.H.S.I No:7,P/36)
7 Providing and installing PVC 8 inch dia blind pipe C class 9 bar best and
approved quality and make including necessary socket etc complete
R.A IS APPROVED
8 Providing and installing PVC 8 inch dia blind pipe C class 9 bar best and
approved quality and make including necessary socket etc complete
(R.A Approved)
9 supplying and installing 6 inch dia nominal ball plug 5 ft long complete including
casing and cap and concrete plug (R.A APPROVED)
5 X 890180 = 4854
Total 872300
13
7 supply and installing PVC 8" strainer pipe"C" class 9 bar approved design
quality and make i/c necessary socket etc:complete (R.A Attached
13 S/I weLl head casing & security camps 15" dia 4'feet M.S well
casing (price of m.s blind pipe) (p.H.S.I.No:11(f)P/37)
400+4454
5x890/80 = 4854
15 cartage of pVc pipe of any class by mechanical transport i/c loading unloading and
stacking at site
(p.H.S.I.No:4'P/6)
8 inch dia
100 Nos Each 89.65 = 90
1 Excavation for pipe lines into trenches and pits in soft soils including
trimming and dressing sides to true alignment and shape leveling of beds
of treches to correct level and great cutting joint holes and disposal of surplus
earth within a one chain as directed by engineer incharge providing fence guards \
lights flags and temporary crossing for non vehicular traffic wherever required
lift upto 5 ft and lead upto one chain.
6 inch dia
2 cutting and jointinz with Z joints with one rubber rings including testing with
water to head of 61 metr or 200 ft
6 inch dia
1 x 1 x 1 x 1 x 4000.00 x = 4000
3 inch dia
1 x 1 x 1 x 1 x 3000.00 x = 3000
90 Angle
1 x 1 x 1 x 1 x 1.00 x = 1
45 Angle
1 x 1 x 1 x 1 x 1.00 x = 1
5 Manufacturing supplying M.S flanges of different dia made out of M.S sheet
of various thickness including cutting drilling holes and welding flanges with
MS Pipe etc
6 inch dia
1 x 1 x 1 x 2 x 4.00 x = 8
8 x 3.14 x P.Rft 25
6 PVC Z joint
Socket
3 inch dia
1 x 1 x 1 x 1 x 8.00 x = 8
7 C.I.T unequal
6 inch to 6 inch
1 x 1 x 1 x 1 x 2.00 x = 2
6 inch to 3 inch
1 x 1 x 1 x 1 x 5.00 x = 5
8 Supplying and fixing air value double acting 3 inch to 1 inch imported.
1 x 1 x 1 x 1 x 1.00 x = 1
1 x 1 x 1 x 1 x 1.00 x = 1
6 inch dia
1 x 1 x 1 x 1 x 8.00 x = 8
6 inch dia
1 x 1 x 1 x 1 x 1.00 x = 1
12 Jointing C.I / M.S flange pipes at special flanged inside a trenches including
supplying rubber packing of the requried thickness nuts bolts with washers and
etc and other tools required for jointing and testing the joints to specified
pressure etc complete
6 inch dia
1 x 1 x 1 x 1 x 4.00 x = 4
13 Making to joint PVC special including laying of the required diameter and testing
the joints along with Asbestos cement pressure pipe line to the specified pressure
and making good to all leaky joints etc complete.
6 inch dia
1 x 1 x 1 x 1 x 4.00 x = 4
14 Providing chamber 2.5 inch x 2.5 inch inside dimension 4.5 deep as per approved
design for sluce wall 3" x 12" diameter with 18" diameter inside cost iron cover
and frame (WT= 1 cwt 3 fixed in RCC 1:2:4 thick 9 " thick brick masonary wall
set in 1:6 marter 6" thick cement concrete 1:3:6 in foundation 1" thick cement
concret 1:2:4 floooring thick cement plaster 1:3 to inside all wall surface and top
including providing and fixing M.S foot beyond 2.5" foot depth rest at every one 1 ft
beyond 2.5 depth curring excavation back filling and disposal of surplus earth etc.
1 x 1 x 1 x 1 x 2.00 x = 2
15 Refilling the excavated stuff in trenches 6 " thick layer including watering ramming
to full compaction etc complete
6 inch Dia
1 x 1 x 1 x 1 x 4000.00 x = 4000
3 inch dia
1 x 1 x 1 x 1 x 3000.00 x = 3000
Total 1304738
Providing and installing of Diesel Oil Engine KVA Generating at
Remaining work of water . Supply scheme at village Juma Gabol
UC Sann Taluka Manjhand District Jamshoro.
PART F
3 INCH DIA 40 FT
1 X 40 Rft = 40
3 Manunfacturing supplying M.S Pipe of different dia made out of M.S Steel of
various thickness i.e cutting drilling holes and welling of flange with M.S Pipe
etc: (P.H.S.I No. D(i)P/32)
3 INCH DIA
2X2X2X16= 128
4 C.I Tapper flate bottomed or central tapered flanged ends with holes including
turning and acting tuning and facing of flanges for all size (P.H.S.I.No.9 p/11).
100 kg
1 X 100 KG = 100
6 Jointing C.I / M.S lange pipe and specials flanged and in side a trenches i
including supplying rubber packing of the required thickness nuts and bolts
with washer etc and other required for jointing testing the specified pressure
etc. complete (P/35 item 1)
TOTAL 1464947
SUMMARY OF COST
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
LSR Tanks
4 Difference of cement
46 x 205.00 = 9407
5 Difference of steel
Total = 137926
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
TOTAL 15618
ESTIMATION
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
LSR TANK
1 Excavtion in foundation of bulding, bridges and other structure including dag belling
reflling around strecture with excavated earth watering and ramming. lead upto
upto 5ft(b) in hard Soil or soft murum.
(S.I.NO.18 (b)/C-1
LSR
2 Cement concrete brick or stone ballast1.5 inch to2 inch guage.(b) Ratio 1:4:8.
(S.I.No.4 (b) /C-4).
1 x 2 x 8.75 x 2.00 x 0.50 = 18
1 x 2 x 2.75 x 2.00 x 0.50 = 6
Under Bed
LSR Inside 1 x 1 x 6.00 x 4.00 x 0.50 = 12
Drain of Lsr 1 x 2 x 20.00 x 2.00 x 0.50 = 40
75.00
2688
75.00 x 3584.10 %Cft =
3
Pacca brick work in foundation and plinth in cement sand mortar ratio 1:6.
(S.I.NO.4( I )/E/C-5) .
Ist Step
1 x 2 x 8.75 x 1.13 x 0.50 = 10
1 x 2 x 2.75 x 2.00 x 0.50 = 6
2ndStep
1 x 2 x 8.75 x 1.13 x 0.50 = 10
1 x 2 x 2.75 x 1.00 x 3.00 = 17
= 42
1615
42 x 3865.15 %Cft
4
Rcc work including all labour and material except the cost of steel reinforcment and its labour for bending
and binding which will be paid seperatively. This rate also includes all kinds of forms moulds lifting, shuttering
curing rendering and finishing the exposed surface
work in roof slab,beams, columns,rafts,lintels and other structural members laid in situ or pre cast laid in
position . Complete in all respects.( I ) Ratio 1:2:4 90 lbs.( S.I.No.6 (a) /I /C-4)
S.I.No.6 (a) /I /C-4)
Plinth Beam
Bottom Slab
Walls
Slab
5
fabrication of Miled Steel Reinforcement for Cement Concrete including cutting, bending,
laying in position, making joints and fastly including cost of binding wire (also includes \
removal of rust from bars
6
Filling watering and ramming earth in floors with surplus earth from foundation lead upto
one chain and lift upto 5 ft.
( S.I.No.21 /C-1)
Qty same as item no 01
1 x 1 x 212 x 2 / 3 = 141
91
141.33 x 641.30 x O%Cft =
8
Supplying and filling sand under floors and plugging in walls.
(S.I.NO.29/C-5)
9 Pacca brick work in ground floor inculding stricking of joints in cemend sand mortar raio 1:6.
Ist Step
1 x 2 x 8.75 x 1.13 x 7.00 = 138
1 x 2 x 2.75 x 1.13 x 7.00 = 44
= 182
182 x 4246.30 x Cft = 7725
13
Cement plaster 1:6 upto 20 height (b) 1/2" (S.I.No.13(b)/C-19)
14
Cement plaster 1:4 upto 20 height (a) 3/8" thick (S.I.No.11(a)/C-9)
= 322
Qty same as item NO(15) 1726
322 x 536.14 x %Sft =
15 Providing construction joint in concrete work of 9" wide (1:6) corrugated PVC water stopper with bulb
i/c cutting cost of material and labour
(P.H.S.I No:5 P/45)
16 providing and fixing C.I man holes cover with frame i/c cost of material etc
(P.H.S.I No:11 P/23)
17 providing G.I pipes & special and climbs, etc i/c fixing cutting and fitting complete with and i/c the cost
of breaking through walls and roof making good etc painting 2 coats after cleaning the pipe etc
with white/zinc paint with pigment to match the color and testin with water to a pressure head of 200'ft
and handing
3 Inch Dia
20 x 308.75 x P. Rft = 6175
18 manufacturing and supplying M.S flanges of different dia made out of M.S sheet of various thickness i/c
cutting weiding holes and weiding of flange with M.S pipe etc complete
3 Inch Dia
25 x 462.40 x P. Rft = 11560
22 providing and fixing C.I ventilator (weight not be less than 90 Ibs/each in tank of roof or approved
design with water light joint i/c painting etc complete (P.H.S.I No.4 p/36)
Ventilator
1 x 1884.45 x P. Rft = 1884
23 providing fixing in position in cerment concrete in foundation (1:3:6) M.S ladder Of M.S angle iron
2"x 2"x1/4" 1'-0" a part painting 3 caost of anticorrosive paint ect complete (P.H.S.I No:4 P/36)
Ms Ladder
10 x 342.90 x P. Rft = 3429
24 supplying C.I sluicc valve heavy pattern test pressure 21 kg/sq cum or 300 Ibs/inch
3 Inch Dia
1 x 2500.00 x P. Rft = 2500
Total 83870.5
SUMMARY OF COST
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
Pump room
4 Difference of cement
93 x 205.00 = 19020
5 Difference of steel
Total = 238185
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
ITEM QTY CEMENT HILL SAND CRUSH STONE STEEL Bricks SAND
1 CC 1:4:8 110 11 53 106
3 CC 1:3:6 30 4 14 28
5 Fabrication 13 0.64
TOTAL 43525
Cartage Material
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
Name of work: Construction of three span culvert / CC block/ well/ under ground Tank/
water supply line @ village juma Khan Gabool Uc sann
Taluka manjhand District Jamshoro
PUMP ROOM
1 Excavtion in foundation of bulding, bridges and other structure including dag belling
reflling around strecture with excavated earth watering and ramming. lead upto
upto 5ft(b) in hard Soil or soft murum.
(S.I.NO.18 (b)/C-1
Room
2 Cement concrete brick or stone ballast1.5 inch to2 inch guage.(b) Ratio 1:4:8.
(S.I.No.4 (b) /C-4).
Long walls Room 1 x 2 x 14.75 x 2.00 x 0.50 = 30
Short walls room 1 x 2 x 8.75 x 2.00 x 0.50 = 18
Steps 1 x 1 x 4.00 x 1.50 x 0.50 = 3
Under Bed
3 Pacca brick work in foundation and plinth in cement sand mortar ratio 1:6.
(S.I.NO.4( I )/E/C-5) .
Ist Step
Long walls Room 1 x 2 x 13.88 x 1.13 x 3.00 = 94
Short walls Room 1 x 2 x 9.62 x 1.13 x 3.00 = 65
= 159
4 Rcc work including all labour and material except the cost of steel reinforcment and its labour for bending
and binding which will be paid seperatively. This rate also includes all kinds of forms moulds lifting, shuttering
curing rendering and finishing the exposed surface
work in roof slab,beams, columns,rafts,lintels and other structural members laid in situ or pre cast laid in
position . Complete in all respects.( I ) Ratio 1:2:4 90 lbs.( S.I.No.6 (a) /I /C-4)
S.I.No.6 (a) /I /C-4)
Plinth Beams
Lintels
Roof Beams
Long walls Room 1 x 2 x 14.75 x 0.75 x 2.00 = 44
Short walls Room 1 x 2 x 8.75 x 0.75 x 2.00 = 26
Slab
Room 1 x 1 x 13.50 x 11.50 x 0.50 = 78
= 262
5 fabrication of Miled Steel Reinforcement for Cement Concrete including cutting, bending,
laying in position, making joints and fastly including cost of binding wire (also includes \
removal of rust from bars
6 Filling watering and ramming earth in floors with surplus earth from foundation lead upto
one chain and lift upto 5 ft.
( S.I.No.21 /C-1)
Qty same as item no 01
1 x 1 x 191 x 2 / 3 = 127
9 Pacca brick work in ground floor inculding stricking of joints in cemend sand mortar raio 1:6.
10 First class deodar wood rought, joinry in doors and windows etc fixed in position including chowkats,
hold fasts, hinges, iron tower bolts, chowks, cleates, handles and cords with hookd etc. Deodar panelled
or panelled and glazed or fully glazed, (b) 1.75" thick (S.I.NO.7(b)/C-10).
11 Providing and fixing Galvanized iron frames/chowkats of size 7" x 2" or 4.5" x 3" for doors using 20 guage
G.I sheet including welded hinges and fixing at site with necessary hold fasts, filling with cement sand
slurry of ration 1:6 and repairing the jams. The cost also include all carriage, tools and plants used in making
and fixing (S.I.NO.29/C-17).
12 Providing and fixing Galvanized iron frames/chowkats of size 7" x 2" or 4.5" x 3" for Window using 20 guage
G.I sheet including welded hinges and fixing at site with necessary hold fasts, filling with cement sand
slurry of ration 1:6 and repairing the jams. The cost also include all carriage, tools and plants used in making
and fixing (S.I.NO.29/C-17).
1007 - 33 - = 974
NET QUANTITY
974 x 531.41 x %Sft = 5178
15 Cement concret plan including placing, compacting, finishing and curing complete (including screening
and washing of stone aggregate without shuttering). (H) Ratio1:3:6 (S.I.NO.5 (H) /C-4 ).
16 Providing and laying topping cement concrete 1:2:4 including surface finishing and dividing into panels
© 2" thick (S.I.No.16©/C-8
19 Painting new surface © preparing surface and painting of doors and windows any type including
edges (I and II) 3 coats (S.I.No.5© /I and II / C-11).
(S.I.No.5© /I and II / C-11).
Total 122884
)
ROOM 12 X10