ITEM NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST
PART A: GENERAL REQUIREMENTS
A.1 Mobilization and Demobilization l.s. 1 ₱ 100,000.00 ₱ 100,000.00
A.2 Safety Requirements l.s. 1 ₱ 100,000.00 ₱ 100,000.00
A.3 Delivery of Materials l.s. 1 ₱ 50,000.00 ₱ 50,000.00
A.4 Project Supervision l.s. 1 ₱ 120,000.00 ₱ 120,000.00
A.5 Clearing and Hauling of Debris l.s. 1 ₱ 100,000.00 ₱ 100,000.00
Subtotal for General Requirements: ₱ 470,000.00
PART B: STRUCTURAL & RETROFITTING WORKS
B.1 Earthworks
B.1.1 Clearing and Site Preparation sq.m. 540 ₱ 212.63 ₱ 114,817.50
B.1.3 Removal of Structures and Obstruction sq.m. 540 ₱ 311.85 ₱ 168,399.00
B.1.4 Structure Excavation cu.m. 50 ₱ 485.10 ₱ 24,255.00
Subtotal (PART B.1): ₱ 307,471.50
B.2 Concreting Works (Class A, 28 days)
B.2.3 Slab on Fill cu.m. 5 ₱ 9,125.70 ₱ 45,628.51
B.2.4 Columns cu.m. 8 ₱ 9,808.31 ₱ 78,466.50
B.2.7 Suspended Slab cu.m. 12 ₱ 12,879.56 ₱ 154,554.75
B.2.9 Septic Tank (Bottom and Top Slab) cu.m. 5 ₱ 9,808.31 ₱ 49,041.56
B.2.10 Steel Deck l.s. 1 ₱ 50,000.00 ₱ 50,000.00
Subtotal (PART B.2): ₱ 377,691.32
B.3 Rebar Works
B.3.1 Reinforced Steel (Deformed) Grade 40 kgs 846 ₱ 97.29 ₱ 82,307.41
B.3.2 Reinforced Steel (Deformed) Grade 60 kgs 635 ₱ 100.38 ₱ 63,743.72
Subtotal (PART B.3): ₱ 146,051.13
B.4 Forms and Falseworks
B.4.1 Forms & Falseworks (Two-Five Storey Building) sq.m. 200.00 ₱ 1,016.17 ₱ 203,233.37
Subtotal (PART B.4): ₱ 203,233.37
B.5 Steel Jacketing
B.5.1 Beams and Girders unit 8 ₱ 15,100.00 ₱ 120,800.00