DATE: Monday, June 24, 2024

PROJECT TITLE: FIT OUT GPL BUILDING


LOCATION: CALOOCAN, METRO MANILA
OWNER: MANILA CENTRAL UNIVERSITY

QUOTATION
ITEM NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST
PART A: GENERAL REQUIREMENTS
A.1 Mobilization and Demobilization l.s. 1 ₱ 100,000.00 ₱ 100,000.00
A.2 Safety Requirements l.s. 1 ₱ 100,000.00 ₱ 100,000.00
A.3 Delivery of Materials l.s. 1 ₱ 50,000.00 ₱ 50,000.00
A.4 Project Supervision l.s. 1 ₱ 120,000.00 ₱ 120,000.00
A.5 Clearing and Hauling of Debris l.s. 1 ₱ 100,000.00 ₱ 100,000.00
Subtotal for General Requirements: ₱ 470,000.00
PART B: STRUCTURAL & RETROFITTING WORKS
B.1 Earthworks
B.1.1 Clearing and Site Preparation sq.m. 540 ₱ 212.63 ₱ 114,817.50
B.1.3 Removal of Structures and Obstruction sq.m. 540 ₱ 311.85 ₱ 168,399.00
B.1.4 Structure Excavation cu.m. 50 ₱ 485.10 ₱ 24,255.00
Subtotal (PART B.1): ₱ 307,471.50
B.2 Concreting Works (Class A, 28 days)
B.2.3 Slab on Fill cu.m. 5 ₱ 9,125.70 ₱ 45,628.51
B.2.4 Columns cu.m. 8 ₱ 9,808.31 ₱ 78,466.50
B.2.7 Suspended Slab cu.m. 12 ₱ 12,879.56 ₱ 154,554.75
B.2.9 Septic Tank (Bottom and Top Slab) cu.m. 5 ₱ 9,808.31 ₱ 49,041.56
B.2.10 Steel Deck l.s. 1 ₱ 50,000.00 ₱ 50,000.00
Subtotal (PART B.2): ₱ 377,691.32
B.3 Rebar Works
B.3.1 Reinforced Steel (Deformed) Grade 40 kgs 846 ₱ 97.29 ₱ 82,307.41
B.3.2 Reinforced Steel (Deformed) Grade 60 kgs 635 ₱ 100.38 ₱ 63,743.72
Subtotal (PART B.3): ₱ 146,051.13
B.4 Forms and Falseworks
B.4.1 Forms & Falseworks (Two-Five Storey Building) sq.m. 200.00 ₱ 1,016.17 ₱ 203,233.37
Subtotal (PART B.4): ₱ 203,233.37
B.5 Steel Jacketing
B.5.1 Beams and Girders unit 8 ₱ 15,100.00 ₱ 120,800.00

Subtotal (PART B.5): ₱ 120,800.00

Subtotal for Structural & Retrofitting: ₱ 1,155,247.32


PART C: ARCHITECTURAL AND FINISHING WORKS
C.1 Masonry Works
C.1.5 Cement Plastering sq.m. 420.00 ₱ 288.94 ₱ 121,355.29
Subtotal (PART C.1): ₱ 121,355.29
C.2 Fabricated Materials
C.2.1 Door Accessories set 40 ₱ 6,970.78 ₱ 278,831.11
C.2.3 Wooden Panel Door sq.m. 5 ₱ 7,087.50 ₱ 35,437.50
C.2.7 Aluminum Glass Window installation set 262 ₱ 1,820.31 ₱ 476,920.24
Subtotal (PART C.2): ₱ 791,188.85
C.4 Painting Works
C.4.1 Concrete Painting sq.m. 250.00 ₱ 408.77 ₱ 102,191.66
C.4.3 Steel/Metal Painting sq.m. 510 ₱ 793.54 ₱ 404,705.53
Subtotal (PART C.4): ₱ 506,897.19
C.5 Ceiling & Dry Walls
C.5.2 Ceiling sq.m. 1100 ₱ 2,614.28 ₱ 2,875,705.78
C.5.3 Dry Wall sq.m. 320 ₱ 5,008.04 ₱ 1,602,572.96
Subtotal (PART C.5): ₱ 4,478,278.74
Subtotal for Archetectural: ₱ 5,897,720.07
PART D: PLUMBING WORKS
D.1 Sewer Line Works l.s. 1 ₱ 124,509.66 ₱ 124,509.66
D.2 Waterline Works l.s. 1 ₱ 166,074.30 ₱ 166,074.30
D.3 Plumbing Accessories l.s. 1 ₱ 55,650.34 ₱ 55,650.34
D.4 Septic Tank with Waterproofing l.s. 1 ₱ 50,000.00 ₱ 50,000.00
Subtotal for Plumbing: ₱ 396,234.30
PART E: ELECTRICAL WORKS
E.1 Conduit, Boxes, and Fittings l.s. 1 ₱ 131,648.90 ₱ 131,648.90
E.2 Wires and Wiring Devices l.s. 1 ₱ 835,116.58 ₱ 835,116.58
E.3 Power Load Center, Switchgear and Panel l.s. 1 ₱ 225,446.29 ₱ 225,446.29
E.4 Data Cabling l.s. 1 ₱ 350,000.00 ₱ 350,000.00
Subtotal for Electrical: ₱ 1,542,211.76

A. Total Construction Cost: ₱ 9,461,413.45


B. 10% Overhead, Contingencies, & Miscellaenous: ₱ 946,141.34
C. 12% VAT: ₱ 1,135,369.61
D. 10% RET: ₱ 946,141.34

GRAND TOTAL ₱ 12,489,066

TERMS AND CONDITIONS:


Scope: The quotation covers the specified work detailed in the project description.
Variations: Any changes to the scope require a written approval and will be considered as change order.
Project Duration: 4 months
PAYMENT TERMS:
50% Downpayment Upon Contract Signing
50% Progress Billing

Prepared by: Noted by:

ENGR. JOHN DALE IBALE MR. PAUL R. ESCUBIO


Project Engineer Owner