Professional Documents
Culture Documents
Escalation Process
Escalation Process
Escalation Process
To From
Date
May 13 2011
Escalation Procedure
All rights reserved. No part of this publication may be made public or reproduced, stored in a data processing system or transmitted in any form by means of print, photocopy or in any other manner whatsoever without the prior written permission of the director of Getronics Nederland BV. Company
Table of Contents
1. 1.1 1.2 1.3 1.4 1.5 1.5.1 1.5.2 1.5.3 1.5.4 Escalation Procedure CUSTOMER GPS III Rollout project 3 Introduction 3 Scope 3 Glossary Error! Bookmark not defined. Participants Roles and Responsibilities 3 Escalation Process Approach 3 Identification and Notification of Escalation 3 Joint Escalation Discussions 4 Escalation to Higher Level 4 Resolution and Closure 4
Escalaiton Procedure for BASF GPS III Rollout project May 13 2011
1.
1.1
1.2
Scope
The Escalation Process identifies the procedures used to coordinate the discussion and resolution of critical items 24*7*365. In addition to documenting the approach to escalation, the process covers who participates in escalation, and how resolutions are documented.
1.3
1.4
1.4.1
Several Processes may trigger the escalation process including issue tracking, contract management and risk management. This process assumes that prior attempts have been made to resolve the item and the appropriate parties cannot reach a solution. When an item is escalated, the appropriate participants are notified by formal letter which includes the date of the scheduled meeting. The meeting must be scheduled within five days of the notification of escalation. The notice of escalation includes a summary of the concern/issue and the analysis of each parties position. The participants must review the analysis and concerns prior to the scheduled meeting. If an action item does not already exist to track the item, action is opened on the SharePoint to track the progress of the resolution. All correspondence is stored in SharePoint.
Escalaiton Procedure for BASF GPS III Rollout project May 13 2011
1.4.2
The involved parties meet to discuss the item. The participants discuss the item, each others position (if appropriate), the impacts of not resolving the item, and the key points of the issues or disagreement. Meeting minutes are documented and representatives from both sides must sign the minutes. If the item is resolved at the meeting, the Project Manager sends a letter to the other party indicating the proposed resolution and the detailed discussion of the key points. Both parties work together to implement the resolution and the action item is closed in the SharePoint. If the item cannot be resolved at the meeting, the committee may call for another meeting or may escalate the item to the next level if they cannot resolve the item.
1.4.3
Ten days after the notice of escalation was received (or sent), the Escalation Process moves to the next level of management. Note that the project must move to the next level of management if the time limit expires. On the tenth day the Project Manager send the Notification of Escalation to the participants in the next level of escalation and schedules the meeting. The process is the same as described in the previous section. Only the participants are different.
1.4.4
When a resolution is reached between the project office and the other party, a detailed discussion of the resolution and the decision is documented, store on the SharePoint and referenced in the action item. The appropriate parties (including sponsor, users and stakholders) are notified of the resolution and work together to perform the resolution. Upon completion of the resolution the action item on the SharePoint is closed.
CUSTOMER REQUIREMENTS: 1 Escalation Procedures Rollout Provider shall develop with CUSTOMERs review and approval, implement and maintain escalation procedures to be followed during the Project. Such procedures shall at a minimum: Set forth standards for triggering escalation which provide for escalation upon request from a designated CUSTOMER representative. On a Service-by-Service basis where appropriate: (a) Describe procedures for escalating problems 24x7x365 (b) Set forth the maximum period of time before a problem is escalated to the next higher severity level (c) Describe the consequences of escalation that is, the steps Rollout Provider will take at each severity level and the personnel it will involve (d) describe the process for notifying and involving Rollout Provider Management at each severity level Identify, by category of Service, Rollout Provider personnel who have responsibility at each severity level; provide directions for contacting such personnel, including pager, mobile phone, after-hours and holiday telephone numbers as available; and provide the name and phone numbers for their alternates in the event such personnel cannot be reached when required under the procedures.
Escalaiton Procedure for BASF GPS III Rollout project May 13 2011
As part of its response to the RFP, Rollout Provider shall provide an organization chart that sets forth all levels of Rollout Provider management and shows the reporting obligations of Rollout Provider personnel to whom issues are escalated.
FromL Schedule_A___Service_Requirements
Escalaiton Procedure for BASF GPS III Rollout project May 13 2011