Professional Documents
Culture Documents
Fuzzy Logic Algorithm For Unit Commitment Problem
Fuzzy Logic Algorithm For Unit Commitment Problem
INTRODUCTION
the UCP.
HERE have been several mathematical programming techniques proposed so far to solve unit commitment problems. They include Priority List, Dynamic Programming, Branch and Bound, Lagrangian Relaxation, Simulated Annealing, Expert Systems, Artificial Neural Networks [3]. The more commonly used method being simple and fast by electricity utilities is the priority list method. This method is used to rank generating units in a heuristic with increasing operation cost. Fuzzy Logic Algorithm provides a solution to UCP by working with a population of individuals each representing a possible solution. Together with a set of the main genetic operators of crossover and mutation this method provides a powerful global search mechanism, whose computation code is simple.Fuzzy logic (FL) is useful in reducing the need for complex mathematical models in problem solving. Fuzziness is used to describe uncertainty, which is applicable to the UCP. Loading of generators, start up cost, incremental cost and production cost are considered to be fuzzy variables with the UCP. Fuzzy logic (FL) is useful in reducing the need for complex mathematical models in problem solving. Fuzziness is used to describe uncertainty, which is applicable to the UCP. Loading of generators, start up cost, incremental cost and production cost are considered to be fuzzy variables with
D. P. Kadam is with the K. K. Wagh Institute of Engineering Education a& Research, Nashik, Maharastra, India as a Assi. Professor Pune university E-mail: dpkadam@gmail.com P. M. Sonwane is with the K. K. Wagh Institute of Engineering Education a& Research, Nashik, Maharastra, India as a Assi. Professor Pune University E-mail: vapron@rediffmail.com Dr. B. E. Kushare is with the K. K. Wagh Institute of Engineering Education a& Research, Nashik, Maharastra, India as a Head & Professor of Electrical Engg. Department E-mail: be_kushare@rediffmail.com
Manuscript received on April 24, 2009.
Authorized licensed use limited to: Sanjivani Rural Education Society's. Downloaded on February 10, 2010 at 03:14 from IEEE Xplore. Restrictions apply.
2.4 Exponential function STi = b1 [l -exp (-b3*Xi)] + b2. ----------------(3) bl, b2 and b3 are start-up cost parameters and Xi the number of consecutive hours for which the unit i has been down [4]. 2.5 Objective function The objective (or cost) function (OF) of the UCP is to determine the state of the units Uih (0 or 1) at each period H, so that the overall operation cost is a minimum within the scheduling time span. H N Min OF= Uih(FCi)Pih+STiUih(1-Ui,h-1)+SDi Ui,h-1 (1Ui,h) ----------------------------------------------------(4) h=1 i =1 Subjected to the constraints i. Total power generated should meet the load requirement and system losses, N Uij Pij = PDj -----------------------------------------(5) j = 1, 2, , H i=1 where PDj is power demanded at hour j. ii. Spinning reserve at each hour (SRj) must be satisfied to cover any shortfall in generation, N PDj + SRj = Uij Pimax , j ----------------------------(6) j = 1, 2, , H i=1 iii. Each generator must operate within its minimum and maximum power output imits, Pimin Pij Pimax i = 1, 2, , N iv. The consecutive number of hours for which a generating unit must remain on (minimum up time, MUT) or off (minimum down time, MDT) should not get violated, Uij = 1 for Tion < MUTi and Uij = 0 for Tioff < MDTi where, Tion and Tioff is the consecutive number of hours for which the unit is on and off till the end of last hour respectively.
I. C.
Start Up Cost
b1 350
b2 158
b3 0.4
1 2 3 4
80 250 300 60
3 2 2 1 4 2 2 3
-1 -2 1 -4
0 0 0 0
where IC: Initial condition of unit ( - sign indicates that unit is down for hours otherwise +).
3 TEST SYSTEM
In order to prove effectiveness of Fuzzy Logic for solving UCP, it is applied to test system of eight units (n = 8) over time period of eight hours (t = 8) [1,9]. TABLE 1 LOAD DEMAND & RESERVE REQUIREMENT OF TEST SYSTEM.
Period 01 02 03 04 05 06 07 08
Demand (MW) 400 470 520 510 360 240 240 450
Reserve + Demand 450 530 600 540 400 280 290 500
Authorized licensed use limited to: Sanjivani Rural Education Society's. Downloaded on February 10, 2010 at 03:14 from IEEE Xplore. Restrictions apply.
output variable using if-then statements. Then if (condition) of each rule is an antecedent to the then (consequence) of each rule.Load capacity of generator, incremental cost, and startup cost are considered as input variables and production cost is treated as the output variable. This relation between the input variables and the output variables is given as: Production Cost= Load Capacity of Generator} and {Incremental Cost} and {Start-up Cost} In Fuzzy set notation this is written as: PRC = LCG IC SUP .Hence, the membership function of the production cost, PRC is computed as follows: PRC= LCG IC SUP 4.4 Defuzzification process One of the most commonly used methods of defuzzification is the centroid or centre of gravity method. Using this method, the production cost is obtained as follows [2], n n PRC= [ (PRC)i * (PRC)i] / [ (PRC)I ]-------(7) i=1 i=1 where,(PRCi):the membership value of the clipped output PRCi :the quantitative value of the clipped output n: the number of the points corresponding to quantitative value of the output [9].
is simply the net heat rate at full load multiplied by the fuel cost[8]. At each hour when the load is dropping, determine whether dropping the next unit on the priority list will leave sufficient generation to supply the load plus spinning reserve requirements. If not, continue operating as is; if yes, go to the next step. Determine the number of hours, H, before the unit will be needed again. That is assuming that the load is dropping and will then go back up some hours later. If H is less than the minimum shut down time for the next step; if not, go to next step. Calculate two costs. The first is the sum of the hourly production costs for the next H hour s with the unit up. Then recalculate the same sum for the unit down and add in the smart-up cost for either cooling the unit or banking it, whichever is less expensive. If there is sufficient savings from shutting down the unit, it should be shut down, otherwise keep it on. Repeat this entire procedure for the next unit on the priority list. If it is also dropped, go to the next and so forth [1].
Hour j 01
OCj 09966 09738 11166 11166 09738 07238 07238 09966 85216
H 01 02 03 04 05 06 07 08
P3j 0 0 50 0 0 0 0 0
P4j 0 0 0 0 0 0 0 0
OCj 09426.7 10927.0 10121.0 10927.0 08488.6 05417.3 05800.0 8576.0 69683.6
02 03 04 05 06 07 08
85,216 (INR)
69,683.6 (INR)
Priority list based method uses power output limits at their maximum value for selected generating units. Fuzzy logic based approach to UCP operates each generating unit within its minimum and maximum power operating limits and resulted the operating cost in INR as 69683.6.
Authorized licensed use limited to: Sanjivani Rural Education Society's. Downloaded on February 10, 2010 at 03:14 from IEEE Xplore. Restrictions apply.
7 CONCLUSION
This paper examined the feasibility of applying Fuzzy Logic & Priority List Method in solving short-term thermal unit commitment. These methods guarantees the production of solution that do not violet system or unit constraints; so long as there are generators available in the selection pool to meet the require load demand. Though the global optimality is desirable, but in most practical cases near optimal solutions are generally sufficient. This paper attempts to find the best schedule from a set of good feasible commitment decisions The result shows that it is possible to achieve improvements using these methods. Cost comparison indicates that Fuzzy logic approach achieves a logical and feasible economical cost of operation of the power system, which is the major objective of unit commitment.Fuzzy logic method allows a qualitative description of the behavior of a system, the systems characteristics and response without the need for exact mathematical formulations. Priority list method usually suffer from large computational times and excessive memory requirements as the problem size increases. The result shows that Fuzzy Logic method is a powerful tool that can be used to solve short-term thermal unit commitment problem. An advantage of Fuzzy Logic lies in its ability to handle any type of unit characteristics data. So the qualitative interpretation of results using Fuzzy Logic appears to be attractive
[8]
S. Baskar, Dr. P. Subbaraj & (Ms) P. Chidambaram (Mar 2001), Application of Genetic Algorithm to unit commitment problem, Journal of Institute of Engineering (India), Vol 81, pp 195-199.
Prof. D. P. Kadam had completed his Graduation in Electrical Engineering from Goverment Engineering College, and M. E. From Walchand Engineering college, Sangli in Power System. His area of interest is Power Quality, FACTS, Optinization of Reactive Power. Currently he is with Department of Electrical Engineering, K. K. Wagh Institute of Engg. Edu. & Research, Nashik. And persuing Ph.D. from Pune university. Prof. P. M. Sonwane had completed his Graduation in Electrical Engineering from Chandrapur Engineering College, and M. Tech. From Viswashareya Reginal College of Engineering in Integrated power systems. His area of interest is power system. Microprocessor, Microcontroller, Artificial Intelligence and distribution system reliability. Currently He is with Department of Electrical Engineering, K. K. Wagh Institute of Engg. Edu. & Research, Nashik. And persuing Ph.D. from Pune university. Prof. Dr. B. E. Kushare had completed his P.hD. in Power Quality from Pune University. Currently he is with K. K. Wagh Institute of Engg. Edu & Research, Nashik as Prof. & Head of Electrical Engineering Dept. He is also Energy Auditor and consultant in power quality problems. He had given his consultancy services to various industries in India and Japan. He also a member of IEEE and various organizations.
8 ACKNOWLEDGMENT
Author thanks ...To Dr. B.E. Kushare (Head,Electrical Engg. Dept, K.K.Wagh Institute of Engineering Education & Research, Nashik ) & Dr. K. N. Nandurkar ( Principal, K.K.Wagh Institute of Engineering Education & Research, Nashik ) for supporting to conduct such research work.
9. REFERENCES
[1] A. J. Wood and B. F. Wollenberg (2006), Power generation operation and control, John Wiley and sons (Asia), second edition, 2006. A. Perlin and P. Sandrin (May 1983), A new method for unit commitment at Electricite De France, IEEE Transaction on Power apparatus and system, Vol. PAS-102, No. 5, pp 1218-1225. B. Gerald, Sheble and George N. Fahd (Feb 1993), Unit Commitment Literature Synopsis, IEEE Transactions on Power System, Vol.9, No.1, pp 128-133. Chuan-Ping Cheng, Chih-Wen Liu & Chun-Chang Liu (May 2000), Unit commitment by Lagrangian relaxation & Genetic Algorithms, IEEE Transaction on Power system, Vol.15, No.2, pp 707-714. D. Dasgupta, and D.R. McGregor (1994), Thermal Unit Commitment Using Genetic Algorithms, IEEE proceedings on Generation, transmission and distribution, vol 141, No. 5, pp 459-465. David E. Goldberg (2001), Genetic algorithms in search, optimization and machine learning, Pearson Education Asia. Dipankar Dasgupta (June 1993), Unit Commitment in Thermal Power Generation Using Genetic Algorithm, In proceeding of the Sixth International Conference on Industrial and Engineering application of Artificial Intelligence and expert system, Edinburgh, UK, pp 374-383.
Authorized licensed use limited to: Sanjivani Rural Education Society's. Downloaded on February 10, 2010 at 03:14 from IEEE Xplore. Restrictions apply.
[2]
[3]
[4]
[5]
[6]
[7]