Fuse: Z loop L-PE / Z line L-L, L-N IEC 60364-6 61.3.6.3., 61.3.11., equipment: IEC 61557- 3 Parameters / Limits are characteristics of particular built-in Fuse, designed for trip-out time of: 0.1s (Explosive), 0.2s (3Phase Circuits), 0.4s (1Phase systems) or 5s (fixed connections). Measured values of Impedances from the end of the circuit must be lower than Zs from the table. In (A) 2 4 6 10 16 20 Tip B Tip C Ia=5x Zs=() Ia=10x Zs=() In (A) (0,2 s) In (A) (0,2 s) 10 22 20 11 20 11 40 5,5 30 7,3 60 3,65 50 4,4 100 2,2 80 2,8 160 1,4 100 2,2 200 1,1 Tip G In Zs=() (A) (0,4 s) 16 13,7 32 6,8 47 4,6 82 2,6 110 2,0 147 1,4
RCD: Trip out time, Trip out Current IEC 60364-6 61.3.6.1., 61.3.7., equipment: IEC 61557- 6 RCD trip out at difrent Id (ms) RCD Slope range (from-to) RCD AC 1/2 x IN 1 x IN 2 x IN 5 x IN 0.2 1.0 x IN A General No trip t < 300 t < 150 t < 40 0.35 1.4 x IN B Selective No trip 130 x t < 500 60 x t < 200 50 x t < 150 0.5 2.0 x IN
More Parameters/Limits could be found in Metrel Handbooks and inside Eurotest/Smartec testers.
L1 L2 L3 N TT PE TT
L1 L2 L3 N PE
Limits: Where no RCD, select limit from the FUSE characteristics, test by Z loop. Where RCD: Nominal Differntial current IN (mA) 10 30 100 300 500 1000 R earth () max. (Uc<50 V) 5000 1666 500 166 100 50