Timber Piles
Timber Piles
125mm x 125mm Kempas Pressure Treated Timber Piles with 110mm x 110mm x 16mm gauge anti split fixed at one end. A. BIL 1 2 Total number of pile 6.00m long ITEMS Material Cost for timber piles Supply cost including delivery to site Unloading Cost Rental of 25T crawler crane (including operator and fuel) 2 unskilled worker 450.00/day = 2 @ RM40.00/day 80.00/day Assumption 530.00/day Capacity of 5T lorry = 96 Nos of piles Time taken for unloading = 2 hrs Cost of unloading/No = RM530.00/day @ 2 hrs 8 hrs/day @ 96 Nos 3 Shoe Cost Supply cost including delivery to site Labour cost for fixing (unskilled worker) Assumption Time taken for fixing = 10 minutes/No So = RM40.00/day @ 10 minutes/No 8 hrs/day @ 60 min/hr 4 Add 10% Overhead Add 5% Profit TOTAL COST
QSD 281 MEASUREMENT OF CONSTRUCTION WORKS IV COST ANALYSIS
No RM RM 64.00/No
1.38/No 10.00/No
0.83/No
B. BIL 1
Total length of extension piles exceeding 3.00m ITEMS Extension Pile Cost As per item A (without profit and overhead) Shoe Cost @ Total cost/No without shoe cost So = RM 79.41/No - RM 10.83/No = RM 68.58/No 6.00m RM
m RM
11.43/m
C. BIL 1
Total length of extension piles not exceeding 3.00m ITEMS Extension Pile Cost As per item A (Total cost/No without shoe cost) Add 10% So = RM 75.44/No 3.00m 68.58/No 6.86/No 75.44/No RM
m RM
25.15/m
D.
BIL 1
ITEMS Handle, transport, pitch Rental of 25T crawler crane (including operator) Consume 10% for fuel 1 skilled worker 3 unskilled workers = 3 @ RM40.00/day Assumption Output pile point / day = 20 Nos So = RM695.00/day 20 Nos/day
RM
RM
32.75/No
Driven Cost Rental of driving equipment (including operator) 300.00/day Consume 10% for fuel 30.00/day 330.00/day So = RM330.00/day 20 Nos/day 16.50/No 48.50/No
Total Cost / m Assumption Driven length = 6.00m + 3.00m = 9.00m So = RM 48.50/No 9.00m
5.39/m
Add 10% Overhead Add 5% Profit QSD 281 MEASUREMENT OF CONSTRUCTION WORKS IV
COST ANALYSIS
TOTAL COST
E. BIL 1 2
Total number of pile extension ITEMS Material Cost Extension Sleeve Supply cost including painting
No RM RM 25.00/No 40.00/day
Labour Cost (for fixing the sleeve) 1 unskilled worker Assumption Time taken for fixing So = = 10 minutes/No
Timber Preservative
F.
No
BIL 1
ITEMS Cutting Pile Head Cost Rental of chain saw Consume 50% for fuel 1 unskilled worker Assumption No of head can be cut in 1 day = 80 Nos/day Cutting Pile Head Cost/No = RM92.50/day 80 Nos/day Timber Preservative
RM
1.16/No 0.25/No
Disposal of surplus Cost Assumption Disposal surplus length = 10% from pile length = 0.60m Capacity of 5T lorry = 96Nos = 96Nos @ 6.00m 0.60m = 960 Nos Time taken for loading = 2hrs Loading cost Rental of 15T crawler crane 2 unskilled workers = 2 @ RM40.00/day Bring Forward
BIL
RM
RM 1.41/No
Disposal of surplus Cost (contd) Loading Cost/No = RM480.00/day @ 2hrs 8 hrs/day @ 960 No 0.12/No 300.00/day 30.00/day 80.00/day 410.00/day
Transportation Cost Rental of 5T Lorry Consume 10% 2 unskilled workers = RM40.00/day @ 2 Assumption Nos of prepare head in the project = 400 Nos (req 8 trips) No of trip per 1 day = 4 trips Total Transportation Cost = RM410.00/day @ 8 trips 4 trips / day Transportation Cost / No = RM 820.00 400 Nos.
820.00
2.05/No 0.12/No
5 6