MITISA HOLDINGS SDN BHD Jobs Safety Analysis


JSA NO : 002 PILING WORKS

Revision No. 0 Page No. Effective Date 15/01/09

of

Project Name: Cadangan Pmbangunan Lumpur (IPK KL) Bangunan Tambahan Serta Komponennya Bagi ibu Pejabat polis Di Atas Lot PT112, kontijen Kuala Seksyen 56,Mukim , Bandar Kuala Lumpur.

Location:

PILING Task/ Activity: WORKS Duration: 150 Days (Start on-19- Job Item 12-08 - Finish on-Steps 04-06-09) 1 General Resources planning Trades Involved: Mobilization of Equipment Used: rig. CRAWLER CRANE, Maintenance PILE RIGS, GEN checks: SET, WELDING Materials SET. Used: 2 Mobilization , Safety Item Job Unloading Legislation: and of Steps Assembly rig
http://www.scribd.com/doc/40209551/JSA-NO-2-Piling-Work (1 of 3)2/16/2012 9:20:44 AM

MITISA HOLDINGS SDN BHD Jobs Safety Analysis


Hazards
1
2

Revision No. 0 Page No. Effective Date This SWMS/JSA 15/01/09 has been developed
Effects
Serious Illn ess / ury Maj or Inj Damag e

of

Risk Rating
3 3 L L
2

and Controlsapproved by:


1

. Traffic problem. MITISA . Poor HOLDINGS Access.

. Slips, trips and falls; Hazards abrasions, strains and manual sprains; handling injuries such as 7. Potential fire back damage. Low

SDN BHD Jobs Safety Analysis

________________________ Position: . Traffic control __________________ Piling by signalman supervisor flag. Date: No. / _ / __ Revision with Foreman 0 Page of 3 Access ways and unloading No. identified. Rig zone Effective operator

Responsible Person

12 Fatal ity/ Of Practice H Code/s Effectsent Risk Per (COP) Applicable man To The Rating Disability Works

Date 15/01/09 .Work area to be


kept clear at Controls all times no storing of materials and/or rubbis 7. Ensure no

Piling Responsible supervisor Person Foreman

JSA NO 2-Piling Work

. Load unbalance. . Congestion 3. Plant overturn

Fatal ity/ Per man ent Disability

welding material at 2flammablerig seating Piling site.

3 Stockpiling of piling materials.

M M H L L
Serious Illn ess 1 / ury Inj or Maj Damag e

. Trips and falls 3. Excessive dragging of Pile causing wire rope 4 Deformed wire and sling rope and damage sling. 4. Broken pile. of 5. Fall equipment materials / . Fall of material due . Oil to snapping of wire rope leakage. or unsecured placement in the casing.

Fatal ity/ Per man ent Disability

12

H L H

Provide plates. on extinguisher 2 .1 Usage of crane for activities. 1 . Sufficient lifting area 2 . 2forUsage piling stock of tagline taking into to guide load. consideration the distance from stock 3. Sufficient work zone. area to ground Ensure crane is preparation 3. 1 tested 2 thoroughly . Correct and examined. 2 stackingcrane operator 3. Ensure manner rope competent 3 Ensure wire is a person. and sling are examined and tested. Homemade 4 All wire rope and splice is sling are to be prohibited.prior to inspected 4. All brokenusage. pile to 5.be removed zone to Pile lifting from site be cleared is in accordingly. lifting when progress.
1

nos. of steel

Crane driver Piling rig operator. Piling supervisor Foreman


y

Crane driver

4. Lifting of pile and placing into prior casing to be driven to the design depth.

1 6

H M

. Ensure wire rope and sling of and .examined Usage are hydraulic joint tested. Homemade avoid is splice clips to leakage. prohibited. 1 .1 Area to be kept clear other than responsible person for the task.
6

Piling supervisor Foreman Piling rig operator.

. Struck by lifted pile


Download this Document for Free Print Mobile Collections Report Document

1 .2

JSA NO 2-Piling Work

Pile to be driven only after it has been well secured into the casing and confirmed by responsible person.

Info and Rating


Follow

knabpsho

3
Share & Embed

Related Documents
Previous

Next

1.

17 p.

2 p.

15 p.

2.

13 p.

http://www.scribd.com/doc/40209551/JSA-NO-2-Piling-Work (2 of 3)2/16/2012 9:20:44 AM

JSA NO 2-Piling Work

12 p.

10 p.

3.

91 p.

10 p.

10 p.

4.

27 p.

16 p.

84 p.

5.

79 p.

79 p.

79 p.

6.

10 p.

27 p.

More from this user


Previous

Next

1.

6 p.

1 p.

6 p.

2.

5 p.

3 p.

Recent Readcasters

Add a Comment

Submit

Characters: 400

Upload a Document
jsa for piling work
Search Documents
q q q q

Follow Us! scribd.com/scribd twitter.com/scribd facebook.com/scribd About Press Blog Partners Scribd 101 Web Stuff Support FAQ Developers / API Jobs Terms Copyright Privacy

Copyright 2012 Scribd Inc. Language: English

http://www.scribd.com/doc/40209551/JSA-NO-2-Piling-Work (3 of 3)2/16/2012 9:20:44 AM

You might also like