2011 Subsea equipment status in preparation for 2011 OSS Date 4/6/2010 Attendees James Kent Mark Hay

Robert Tiano Robert Phillips MikeFry

RMA Deepwater Horizon Horizon subsea supervisor Project QGC Project manger TFS

The purpose of this meeting was to discuss BOP component condition and condition of support equipment.
BOP COMPONENTS

Diverter: Replacement diverter in process ofPA approval. 1825 day maintenance required. Diverter flex joint 1825 day maintenance required. Presently there is not a replacement in shared spares. Mike Fry will get a quote I lead time for rebuild parts and estimated out of service time to rebuild. Last quote was 50 week lead time. Mike Fry to check the availability of
Riser adapter flex joint New in service in 2009 will not require maintenance.

Upper annular Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks. Lower annular Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks. Key seating is evident. LMRP connector 1825 day PM required. Connector not available from shared spares. Mike Fry to check connector coming from the Pathfinder.
Isolation valves Require rebuild.

Mini collet connectors New in service no maintenance required.

EXHIBIT #

I ) cr6

WIT: _ _ __ __
(

\.

CONFIDENTIAL

TRN-MDL-00467327

Blind shear ram bonnets 1825 day maintenance required. Will swap from shared spares. Blind shear ram body Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks. Super shear ram bonnets
No maintenance required

Super shear ram body Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks. 3 Yz to 6 5/8 ram bonnets 1825 day maintenance required. Will swap from shared spares. Blind shear ram body Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks.
3 Yz to 6 5/8 ram bonnets

1825 day maintenance required. Will swap from shared spares. Blind shear mm body Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks.
3
~

to 6 5/8 ram test bonnets

1825 day maintenance required. WiJI swap from shared spares.

Blind shear ram body Cameron to inspect, take dimensional readings and report findings. This inspection will take place in approximately 6 weeks. Failsafe valves No action required, normal maintenance rotation. Cameron connector
New in service in 2009 will not require maintenance.

Vetco connector 1825 day maintenance required. Will swap from shared spares.

BOP studs 3"


NDT, order 20 spare studs to replaced any damaged during removal.

ex ling gaskets
Replace all.

CONFIDENTIAL

TRN-MDL-00467328