Website Design and Development WBS Project: Website Project

Project: Prepared By:

Website Project Anna Carlos Date: 1/21/2012

Website Design and Development WBS

1. PLANNING 1.1. Website Contract Agreement 1.1.1. 1.1.2. 1.1.3. 1.1.4. Contract agreement development Contract Agreement Sending to Client Contract Agreement Review and Signing by Client Signed Contract Agreement by Client Sending to Developer

1.2. Website Design Deposit 1.2.1. 1.2.2. 1.2.3. 50% Deposit Invoice Creation Send 50% Deposit Invoice to Client Client sends 50% payment via check or via direct deposit or via paypal

1.3. Website Plan and Specifications 1.3.1. 1.3.2. 1.3.3. 1.3.4. 1.3.5. Website Plan and Specifications Creation Website Plan and Specifications Sending to Client Website Plan and Specifications Review and Signing by Client Signed Website Plan and Specifications Sending to Developer Schedule Skype Call with Client to confirm comments and finalize the Signed Website Plan and Specifications 1.4. Website Page Content Materials 1.4.1. Send Client a List of Website Page Content Materials (logo, text, photos, graphics and etc.) 1.4.2. Client Sends All Required Materials Necessary to Develop Website

1.5. Website Timeline 1.5.1. 1.5.2. Website Development Timeline Creation Website Development Timeline Sending to Client

2. DESIGN REVIEW 2.1. Website Mock-up online creation 2.2. Website Mock-up online presentation to client 2.3. Website Mock-up online review and approval by client 2.4. Client submits request and suggestions for design changes, if there s any

2/29/2012

Copyright@2010. All Rights Reserved Enveesiondiz Business Solutions

Website Design and Development WBS Project: Website Project


3. DESIGN MODIFICATION [STAGE 1] 3.1. Developer works on the first round of design modifications as per client change requests 3.2. Developer completes the first round of modifications

Website Design and Development WBS

4. DESIGN MODIFICATION [STAGE 2] 4.1. Client reviews and approves latest changes and/or submits request for second round of modifications 4.2. Developer works on the second round of design modifications as per client change requests 4.3. Developer completes second round of modifications

5. DESIGN MODIFICATION [STAGE 3] 5.1. Client reviews and approves latest changes and/or submits request for third round of modifications 5.2. Developer works on the third round of design modifications as per client change requests 5.3. Developer completes third round of modifications

6. DESIGN APPROVAL 6.1. Client reviews and provides final approval for design concept

7. CONTENT DEVELOPMENT 7.1. Content development phase begins 7.2. Completed content pages are submitted for Client s approval 7.3. Review and revision stage commences 7.4. Developer makes any final content edits/changes requested by client

8. PROJECT APPROVAL 8.1. Client reviews, approves and signs off on completed website project

9. WEBSITE FINAL PAYMENT 9.1.1. 9.1.2. 9.1.3. 50% Final Payment Invoice Creation Send 50% Final Payment Invoice to Client Client sends 50% final payment via direct deposit or via paypal

10. TESTING & QUALITY ASSURANCE 10.1. Testing stage commences

2/29/2012

Copyright@2010. All Rights Reserved Enveesiondiz Business Solutions

Website Design and Development WBS Project: Website Project


10.2. If necessary, final modifications are made to assure quality

11. SEARCH ENGINE OPTIMIZATION 11.1.Insertion of Meta Tags (Global Title, Description, and Keywords) on major web pages

Website Design and Development WBS

11.2.Site Map Creation and Submission to Major Search Engines 11.3.Submission of URL to Google, Yahoo, and Bing 11.4.Installation of Google Analytics Tracking, Webmaster Tools, Yahoo Site Explorer and Bing Webmaster

12. WEBSITE LAUNCH 12.1.Website is uploaded to the Client s web hosting server; live website is launched to the internet 12.2.Preparation of Website Transition Checklist 12.3.Website Transition Checklist Sending to Client 12.4.Schedule 1-hour (Skype) website backend training with Client

2/29/2012