Professional Documents
Culture Documents
Space Shuttle Integration Lessons Learned
Space Shuttle Integration Lessons Learned
Lessons Learned
Bo Bejmuk
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
2 8/31/2006
Introduction
Two types of Shuttle Program Lessons Learned are addressed
Problems How they were resolved and their applicability to Ares I Success Stories How they were achieved and their applicability to Ares I
Top-level Lessons Learned from Zenit Derived Launch Systems Sea Launch are included
3 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
4 8/31/2006
Independent evaluation of all elements changes Definition and verification of system interfaces and interface parameters and associated documentation Integrated Hazard Analyses Integrated vehicle configuration management
5 8/31/2006
6 8/31/2006
7 8/31/2006
Liftoff Loads Ground Winds Liftoff Clearances Acoustics ET Pressurization Main Propulsion System Avionics Sequencing & Timing Electrical Power Integrated Hydraulics Software Requirements Integrated Checkout Requirements
8/31/2006
Evaluation of flight test results and the establishment of operational boundaries for all flight phases
Shuttle Elements
External Tank
Ground Systems
Orbiter*
* Two cargo configurations analyzed 65K lbs and 0 lbs payloads
8/31/2006
Technical panels were established early in the development cycle to provide a forum for the smooth interchange of information between system integration and element experts The Systems Integration technical effort was iterative and involved several Design Cycles
8/31/2006
10
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
11 8/31/2006
Post flight analysis revealed that water spray designed to suppress SRB IOP was not directed at the source of IOP
Source of IOP was believed to be at the plume deflector STS-1 data analysis showed the primary source located immediately below the nozzle exit plane
Tomahawk ignition transient used for preflight characteristics were very different from that of the SRB
12 8/31/2006
A new scaling relation was developed based on blast wave theory A series of 6.4% scale model tests were conducted to evaluate various concepts of IOP suppression schemes Final fixes
Redirected water spray for SRB IOP suppression toward the source of SRB IOP (Figure 1) Installed water troughs in the SRB exhaust duct Very significant IOP reduction was achieved (Fig. 2)
8/31/2006
13
Water spray at The flame deflector and side pipes along the duct
STS-1 Configuration
8/31/2006
STS-2 Configuration
14
Figure 2: An overall factor of 5 reduction for the primary IOP waves was achieved with the redesigned system prior to STS-2
15 8/31/2006
16 8/31/2006
Ascent Aerodynamics
Problem Plume simulation used during the preflight wind tunnel test program was not adequately implemented
Observed significant wing lift and vehicle lofting in STS-1
Measured strains showed negative structural margins
Corrective Actions The Post-flight tests using hot plume simulations improved base and forebody pressure predictions The ascent trajectory was changed to a flight with a greater negative angle of attack through High Q
The negative angle reduced wing lift The negative angle had to be evaluated for Orbiter windows and the ET side wall pressures
17 8/31/2006
18 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
19 8/31/2006
Structures
Problem Throughout Shuttle development and the initial years of operations many costly structural modifications had to be made to maintain the required 1.4 structural safety factor
The Shuttle structure was designed for a 1.4 safety factor with no additional margin to accommodate changes occurring during the development phase
Corrective Actions As mathematical models and definitions of the environments matured, resulting changes required many hardware changes to eliminate areas of negative margin (below a 1.4 safety factor)
These hardware modifications were expensive and time consuming. Additionally, they increased workload at the launch site This tedious activity ensured safe flights and compliance with the safety factor requirement, however it created a significant impact on Shuttle operations
20 8/31/2006
Structures (continued)
Lessons If development time is short, structural margin management could be pursued to avoid costly hardware changes as loads analyses mature
A suggested approach could be as follows:
Assign additional factor to be applied to the design loads for environments with the greatest uncertainties
For example, gravity and pressure loads could have a factor of 1.0 but dynamic and aero loads could have a factor of 1.2 All factors would converge to 1.0 as a function of program maturity
A method of structural margin management could minimize costly hardware redesign, and program stand downs, but it may result in a somewhat heavier vehicle
21 8/31/2006
Corrective Actions Flight instrumentation and ascent photography were used to measure response in flight
Ascent environments were updated to correspond to measured response The body flap critical design case was entry (thank goodness), no action was required since including buffet loads on ascent was still enveloped by entry The vertical tail had sufficient margin to accommodate increased buffet loads
22 8/31/2006
23 8/31/2006
Common Shuttle/Ares I SRB grows 0.9 during ignition MLP deflects downward Forward interface translates upward
SRB growth loads are transmitted directly to 2nd stage potentially creating more sever L/O loads
SRB Growth
MLP
Ares I
Problem Shuttle liftoff (L/O) loads were very difficult to analyze Configuration complexity SRB Ignition Overpressure Twang during the SSME thrust buildup Vandenberg experience showed that loss of the MLP compliance significantly increased L/O loads Flexible washers were planned to restore compliance and avoid vehicle redesign
8/31/2006
24
25 8/31/2006
Element GVTs
SRB L/O & Boost Phase, & Burnout ET with various liquid levels Orbiter FREE-FREE & constrained at ET interface
Mated GVTs
Orbiter/ET Boost Phase 4 Body mated, L/O, High Q, & SRB Burnout
8/31/2006 26
Upper stage alone in Free-Free and constrained at SRB interface configurations could be a sufficient and cost effective GVT for Ares I
27 8/31/2006
Prior to test start, the decision was made to limit loading to limit plus load level
Test article was not stressed beyond yield This test was supplemented by component testing to 1.4 times limit loads in areas of low margin and sensitive joints The Orbiter test article was treated as flight hardware (configuration management, problem dispositions)
Post test, the STA was converted to flight hardware and used as the Challengers airframe Lesson Thoughtful planning of the test hardware and transitioning it to flight status could result in significant cost savings 28
8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
29 8/31/2006
Corrective Action The Program was cancelled, but the lesson remained Lesson Consider imposing minimum modal frequency on the launch vehicle to avoid coupling with slosh and control system modes
May require stiffness requirements (in addition to strength requirement) for Stage I/Stage II interface hardware
8/31/2006 30
Lesson Instrument every FCS sensor location preferably with flightlike sensors in future GVTs
31 8/31/2006
Slosh baffles are easily removed, but difficult to add as the program matures Lesson Retain a conservative approach for slosh baffle implementation
Avoids redesign to increase slosh damping Allows easy weight reduction as FCS stability is confirmed by flight data
32 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
33 8/31/2006
Corrective Actions System Integration led the evolution from a single ascent I-load, through seasonal I-loads, alternate I-loads, and finally arriving at DOLILU This process extended over a 10+ year period (Figure 3) Concurrently the Program executed 3 load cycles (Integrated Vehicle Baseline Characterization - IVBC) combined with hardware modifications to expand vehicle certified envelopes (Figure 4) Current launch probability is well in excess of 95% Lesson Commit to a DOLILU approach during early development
Significantly improves margins
8/31/2006 34
Lesson Learned:
Percent of Winds Violating Certification (%)
Operations Overhead
Qb
Qb
DOLILU drives toward center of Qa Qb envelope and reduces winds violation to < 5%
36
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
37 8/31/2006
Avionics Architecture
Problem Prevention of loss of vehicle/crew or mission due to avionics failures considering mission duration up to approximately 12 days Dissimilar solutions (primary, backup and two fault tolerance in avionics hardware/software) Establishment of SAIL Simulation of hardware/software interaction Four LRU Mid Value Select (MVS) implemented with appropriate cross strapping to ensure two fault tolerance The Redundancy Scheme was required to be test verified Two fault tolerance became an avionics system mainstay on the Shuttle Orbiter The Orbiter system provided a reliable avionics system. For a short duration, missions such as Ares I ascent suggested a tradeoff to be performed between one and two fault tolerance. Overall system reliability could be used in the evaluation.
Actions
Lesson
38
8/31/2006
Low Time Exposure Trade off study suggested: One vs. two fault tolerance on Booster A tailored level of fault tolerance could emerge as the best solution
The Shuttle approach of two fault tolerance* was robust, but may be excessive for a boost only vehicle. The overall system reliability (for example 0.999) should drive redundancy requirements.
* With some compromises
39 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
40 8/31/2006
Main Propulsion
Problem Pressure oscillations upstream of the SSME first stage pumps were not fully appreciated and not included in the design environments
This caused inadequate design resulting in fatigue of the H2 temperature probe located 18 upstream of pump Combined environments (vibroacoustics and pressure oscillations) also created fatigue cracks in the flow liners Neither were protected by screens
Corrective Actions Eliminated temperature probe and switched LCC to upstream manifold measurement impact 2 months Program stand down A massive analytical and test effort, resulting in polishing flow liner slots, welding existing cracks and implementing inspection after each mission impact 4 months Program stand down Based on Shuttle analytical and test experience, develop and incorporate pressure oscillations in the Main Propulsion System (MPS) hardware design environments
8/31/2006
Lesson
41
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
43 8/31/2006
Backup was never engaged over the life of the Program and software reliability has improved since the Shuttle Development timeframe Lesson For Ares I, Backup software is not recommended for ascent flight. However, for Orion, it should be considered for crew escape.
44 8/31/2006
Lesson Manage Ground and Flight Software and avionics facilities on the Ares I Program to preclude unnecessary proliferation and duplication
Force labs to terminate when their role is finished
8/31/2006 45
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
46 8/31/2006
Lightning Requirements
Problem The Shuttle started with strict requirements
TPS could not be certified Avionics were difficult
Years of unnecessary cost and effort prior to decision Starting with a fair weather vehicle may be a cost effective approach
Some avionics hardening could be worthwhile Crew escape should be considered for hardening
47
Lesson
8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
48 8/31/2006
50 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
51 8/31/2006
RCS Thrusters
The Orbiter has two bipropellant RCS systems
Primary 870 lbs thrust used during ascent from SRB separation through entry Vernier 25 lbs thrust used on orbit for attitude adjustment and maintenance
Only applicable lessons learned from the Primary thrusters will be discussed
Approximate thrust range of potential roll control Ares I thrusters
52 8/31/2006
Corrective Actions Combustion stability screening added to hot fire ATP (Helium injection) Incorporated wire wrap around combustion chamber to shut down the thruster at the onset of burn through Lesson Avoid pressurant gas in the propellant if possible (eg. Use bladders) Address combustion stability during the development and test program
8/31/2006 54
Corrective Actions
Eliminated pre-weld etch for new build Developed NDE to inspect for cracks at White Sands Depot and on vehicle
Lesson
Avoid processes or chemicals that would result with Fluorine coming into contact with Columbium at temperatures above 500 Degrees F
55 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
56 8/31/2006
57 8/31/2006
Lesson Try to avoid using metal flexible hoses, especially in high traffic areas and incorporate hard protection whenever possible Educate workers and visitors on the vulnerability of flex hoses from the Programs onset
58 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
59 8/31/2006
Risk Management
Problem Although risk was managed by good engineering practices, very little formal risk classification and management was employed Probabilistic Risk Analysis (PRA) was rarely used on the Shuttle Program
Distrust of the methodology, lack of suitable data, Apollo experience
Frequently funds were expended pursuing corrective action for extremely low probability threats no means to measure effectiveness of a corrective action on the overall system reliability or safety Corrective Actions A 5X5 matrix risk classification was implemented on the Shuttle Program
Up and down the organization, from individual technical disciplines to the Program Manager (Figure 5)
61 8/31/2006
Figure 5: Risk Rating Developed Since the Columbia Accident (Program View)
15 Redesign of FRCS Paper Covers Using Tyvek (Completed design/drawings) 18 Orbiter Processing Issues Hardware (Numerous processing issues at KSC) 22 Water Spray Boiler Freezing (Mitigation design in work, on-orbit testing planned) 23 MPS Surface Mounted GO2 Temp Sensor Mod (Complete design drawings/ MASR II database update) 28 Cold Plate Manufacturing Issues
8/31/2006
23
4 Likelihood
28
15
18
22
1
1 2 3 4 5
Consequence
62
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
63 8/31/2006
64 8/31/2006
Operational Reality
NASA, KSC Photo, dated September 25, 1979, index number KSC-79PC-500
8/31/2006
65
Corrective Actions Very labor intensive (high operational cost) vehicle was developed and put into operations Lesson Must have the Concept of Operations defined Levy the requirements on contractors to support the Concept of Operations Must have continuity and integration between designers, ground operations, and flight operations requirements during the developmental phase
8/31/2006
66
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
68 8/31/2006
Continuous pursuit of the elusive 65K lbs due East ascent capability precluded the possibility of holding back some structural margin to avoid costly redesign changes as Program development matured Prior to performance enhancement program the Shuttle had an ascent performance shortfall of ~10K lbs Actions Taken All priorities were subordinated to the quest for ascent performance
Very few features supported effective operations Costly structural modifications to maintain the required factor of safety were made
8/31/2006 69
Use factors on not well understood environments to protect against costly design modifications as Program knowledge matures Transition to operations should be made consistent with vehicle operational capabilities imbedded in the design
70 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
71 8/31/2006
5
Applicability to Ares I
3
RCS Seat Extrusion
2 1 1
Less
Less
4
Greater
5
72
Significance to Shuttle
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing The Big Lesson
73 8/31/2006
Launch Platform
74
Launch
76 8/31/2006
System was built and brought to operational state in less than 3.5 years
22 flights to date, 21 successful
77
8/31/2006
Small Team performs ground checkout and launch Ground Processing Team Americans Russians Ukrainians Norwegians Totals 80 200 50 75 405 Launch Team* 40 140 50 70 300
* Launch Team is a subset of the Ground Processing Team; Ground Processing team members that are not required to participate in launch at sea are sent back to their companies and are off the Sea Launch payroll
8/31/2006
78
Single string accountability, no duplications of effort (to some extent driven by export compliance restrictions) Low operational cost benefited from original design criteria of Zenit
Rollout to pad, fuel and launch in 90 minutes Allows very little time for ground or flight crew involvement Imposes requirements for automatic processes
79 8/31/2006
OUTLINE
Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Lessons learned from Day-of-Launch I-Loads Evolution Shuttle development & Avionics Architecture operations can reduce Main Propulsion Constellation life-cycle cost Software and development schedule, Lightning and result in more reliable Flight Instrumentation and safer systems RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned Zenit Derived Launch System Sea Launch Delta IV Separate Briefing
80 8/31/2006
A gap existed between actual and perceived state of vehicle robustness and safety Although strong indications were present, neither the design nor the operations team identified the problem
81 8/31/2006
Integration and element engineering should be staffed with the best in their fieldinquisitive by nature, respected by peers and management, and who have the courage to take on the Program regarding issues Transition to operations should be made consistent with vehicle operational capabilities imbedded in the design
82 8/31/2006
BACK-UP
83 8/31/2006
5.) FCS Flex Stability 6.) High Q static Elastic Loads 7.) High Q Response to Gust
84 8/31/2006