Professional Documents
Culture Documents
Summary of PMP Knowledge Area Cost Management
Summary of PMP Knowledge Area Cost Management
About 12 exam questions on earned value. 6 of these require calculations. PCM includes the processes involved in estimating, budgeting and controlling costs so that the project can be completed within the approved budget. Cost Management is part of the Planning and Monitoring & Controlling Process group. There are 3 processes - Estimate Costs per activity or control account - Determine Budget - aggregate estimates to authorized cost baseline - Control costs monitor against baseline and manage changes to baseline Cost Management Plan Also known as Budget (management) plan. Similar to other management plans and part of the project management plan. Answers the following questions - How will I go about planning cost for the project - How will I effectively manage the project to the cost baseline, control costs and manage cost variances Life Cycle Costing Looking at the cost of the whole life of the product, not just the cost of the project Value Analysis Find less costly way to do the same work Cost Risk Cost related risk. E.g. Who has the cost risk in a fixed price contract? The seller
Estimate Costs
Coming up with cost estimates for each activity Estimating Principles are the same as in Project Time Management Types of Cost Variable Costs, Fixed Costs, Direct Costs, Indirect Costs Estimation Techniques Bottom-Up Expert Judgement One-point Analogous (top-down) Parametric Three-point Most likely, Optimistic, Pessimistic expected = (o+4*m+p) / 6 Reserve Analysis Cost of Quality
Accuracy of estimates Rough Order of Magnitude Estimate: +/- 50% project initiation Budget estimate: -10 / +25% project planning Definite Estimate: +/- 10% When completed, the Estimate Costs process results in activity cost estimates and an explanation of how those estimates were derived.
Determine Budget
Calculate total cost of project (incl. risk contingency reserves). This is the cost baseline. Project Manager has authority to mange and control cost baseline. Cost baseline + management reserves = cost budget
Control Costs
The control costs process is similar to the control part of any other knowledge area. Meaning follow the cost management plan