Khalid’s attitude
immature, says Khir
SHAH ALAM: Umno Supreme Council member tion where just because of 20 people, Selangor
Datuk Seri Dr Mohamad Khir Toyo has described residents will face a big problem of power supply
Selangor Mentri Besar Tan Sri Abdul Khalid Ibra- shortage,” he said.
him’s “wash my hands off” attitude in the issue Mohamad Khir said he learnt that TNB would
of the Central Area Reinforcement (CAR) project not budge from its original plan to install the
in Rawang as immature. power line through Kampung Sungai Terentang
Last Saturday, Abdul Khalid had stated that the as the other suggestions given by the state gov-
state government would have no part in solving ernment could not be implemented because of
the issue of the CAR project in Kampung Sungai technical reasons.
Terentang, Rawang, which had been delayed for He, therefore, hoped that the state govern-
a year, if Tenaga Nasional Berhad (TNB) kept to its ment would take firm action to acquire the land
original plan without considering other proposals and hand it over to TNB.
from the state government. TNB president and chief executive Datuk Seri
“As this project comes under the jurisdiction Che Khalib Mohamad Noh had voiced the utility
of TNB, we have met up with the Energy, Water company’s concern that if the project was not
and Communications Minister, Datuk Shaziman completed, Selangor, Kuala Lumpur and a large
Abu Mansor, and asked him to meet personally part of the peninsula’s southern region would
with the villagers to solve any problems,” he had be facing power supply disruptions for three to
told reporters. four months.
However, Mohamad Khir, the former mentri The CAR project, costing RM400 million, with
besar, said although the land involved was TNB a large portion of it already spent by TNB, could
reserve, it did not have the power to acquire the not proceed further because of objection from
land for the project and only the state govern- 20 of the 40 affected families although TNB was
ment could do so under Section 3 (1)(a) of the willing to double the relocation compensation,
Land Acquisition Act 1960 in the interest of the Mohamad Khir said.
public. About 98% cent of the project has been
“We understand that the state government completed and the uncompleted 2%, involving
tried to shift the power line to Kampung Sungai a distance of 1km, requires the installation of
Samak and Kampung Tun Perak but the residents four monopoled towers before electricity could
there protested. We hope the state government be channelled to almost 6.5 million homes.
can solve the problem. We don’t want a situa- – Bernama