Professional Documents
Culture Documents
1 20RiskScheduleexample
1 20RiskScheduleexample
1 20RiskScheduleexample
Qty of Risks at level Project Ref: Project Manager: Project Board: HMLB 0800 EC Harris Project Name: College Customers / Business Contacts: Hammersmith L Block Red Amber Green Average APPROX IMPACT Average Impact Average Impact () x Prob %age STATUS ACTION Total Approx impact of Risks at level 0 0 39 14,605,000.00 4,978,800 MITIGATION ACTION 1 ACTION OWNER RiskType Business Project Stage Probability 1.Very unlikely say 20% 2. Unlikely say 40% 3. Likely say 60% 4. Very likely say 80% Impact 1. < 200k 2. 200k- 500k 3. 500k- 1.0 million 4. 1.0 million> ACTION OWNER ACTION BY LAST 3rd Party DATE UPDATED Impact
ID
TYPE
AUTHOR
DATE IDENTIFIED
RISK CATEGORY
DESCRIPTION
PROB
IMPACT
109 Project
P Gudge
Construction
H 4 4,500,000
M 3,000,000
L 1,500,000
3,000,000
600,000 Open
Acceptance
Carry out credit checks prior to entering into contract and implement bonds etc as appropriate Clearly identify areas of direct cost to tenant users Do not accept Client change during construction unless no impact upon programme Monitor and proactively manage to ensure power supply provided on time. Transfer delivery risk to main contractor. Early review and programming of commissioning and ensuring that all parties fully understand the ICL commissioning requirements Design Team to review and confirm design changes during Stage E Appointment of internal specialist PM and full time user coordinator to assist in decant coordination Ensure key milestones for selection and placing order of client direct equipment is included on the programme Comprehensive survey of existing services Coordinate and monitor decant works Ensure contractor carries out Type 3 asbestos survey Manage user expectations during design & construction Acoustic enhances 4m high boarding to be priced Ensure that client suppliers are fully on board with the scheme and are informed about the scheme Regular liason with the CWB project team to ensure they are aware of impact of completion of CBW for L/J blocks Main contractor carry out credit checks prior to entering into contract and implement bonds etc as appropriate Comprehensive review of tender deliverables prior to going out to tender Implement strict change control during construction and implement major changes post contract.
ECH
Jan-09
ECH
Ongoing
14/07/08
57 Project
P. Chiew
EC Harris
Organisation
51 Project
A. Collins
EC Harris
Organisation
Implementation of changes requested by tenants without agreement of funding between IC & Tenant Extended construction programme due to amended design i.e Variations Power supply not provided in accordance with programme requirements Insufficient level of detail for commissioning
500,000
350,000
250,000
366,667
183,333 Open
Reduction
TT
Ongoing
Any proposed tenant changes to be subject to strict change control All changes required to go into post contract change HL to request for quotation on time in order for order to be placed and cheque issued Robust management of the commissioning process including the early appointment of external validation engineer Implementation of Change control to approve items with cost effects. Coordinate and monitor decant works Full engagement with users and ensure that users are aware of milestones and implication of not meeting milestones Desktop study of all existing services information
Matt Lee
Ongoing
14/07/08
3 1,000,000
750,000
500,000
750,000
300,000 Open
Prevention
ECH
Ongoing
ECH
Ongoing
14/07/08
112 Project
P Gudge
EC Harris
Construction
3 1,000,000
500,000
300,000
600,000
240,000 Open
Acceptance
ECH
Ongoing
HL
Sep-08
14/07/08
132 Project
P. Chiew
Imperial College
Construction
250,000
150,000
100,000
166,667
66,667 Open
ECH
Ongoing
ECH
M.Irmiger P. Chiew
Design General Design Development between Stage D & Stage E Enabling Works Failure of management of IC decant to & Decant Activity achieve decant by 31.03.09 Construction Late selection of client direct equipment
3 3
2 2
700,000 500,000
450,000 300,000
250,000 200,000
466,667 333,333
SR IC
Sep-08 Ongoing
ECH ECH
Sep-08 Ongoing
15/08/09 14/07/08
133 Project
P. Chiew
Imperial College
500,000
300,000
150,000
316,667
190,000 Open
ECH
Ongoing
Matt Lee
77 Project
P. Chiew
Hoare Lea
30/04/08 Enabling Contractor 10/07/08 Imperial College 30/04/08 Imperial College 30/04/08 Imperial College 30/04/08 Shared Imperial and Contractor 30/04/08 Imperial College
88 Project 84 Project
P Gudge P. Chiew
60 Project 81 Project
P. Chiew P. Chiew
73 Project
P. Chiew
Imperial College
121 Project
P. Chiew
EC Harris
Enabling Works Damage/ disconnection of services to & Decant Activity other campus buildings during enabling works - MAJOR ITEMS Programme Failure of management of ICHT decant to achieve decant by 31.03.09 Enabling Works Unexpected levels of asbestos found in & Decant Activity building structure (principally contractor risk) Organisation User dissatisfaction with output compared to expectations Enabling Works Disruption caused by demolition works & Decant Activity is unacceptable to neighbouring buildings Design Lack of interface between client and design team leading to unsuitable provision of equipment and inadequate furniture Programme Late finish of CWB Phase 3 project [Risk: order of magnitude assumed in order of 2 weeks] Construction Sub contractor insolvency
4 1,400,000
900,000
500,000
933,333
186,667 Open
Transference
ECH
Dec-08
HL
Sep-08
14/07/08
2 1
2 2
500,000 100,000
400,000 75,000
300,000 50,000
400,000 75,000
Reduction Reduction
ECH ECH
Ongoing Dec-08 Ensure demolition contract accounts for disposal of contaminated waste Appoint full time user coordinator Contractor appointed for a 6 day week Meetings to be convened between user coordinator and SR/HL to ensure suitability of provisions Ensure early warnings on delays are communicated in order for joint mitigation actions to be produced Main Contractor careful monitoring of sub contractor during construction period TT Sep-08
14/07/08 14/07/08
2 2
2 2
500,000 350,000
350,000 200,000
150,000 75,000
333,333 208,333
Reduction Reduction
IC (user coordinator) TT
Ongoing Ongoing
IC ECH Dec-08
14/07/08 14/07/08
300,000
200,000
100,000
200,000
80,000 Open
Reduction
ECH
Ongoing
ECH
Ongoing
14/07/08
300,000
250,000
150,000
233,333
93,333 Open
ECH
Ongoing
ECH
Ongoing
130 Project
P. Chiew
Imperial College
27/11/08 Contractor
200,000
150,000
50,000
133,333
80,000 Open
Main Contractor
Ongoing
Main Contractor
Ongoing
131 Project
P. Chiew
Imperial College
Tender
2 1,000,000
500,000
250,000
583,333
233,333 Open
T&T
Jan-09
104 Project
P Gudge
Imperial College
Programme
106 Project
P Gudge
Hoare Lea
Design
122 Project
P. Chiew
Sheppard Robson
08/09/08 Contractor
Design
Changes of potential occupants leads to changes to design solution [Minor only - assumed significant change of use funded through separate budget/funding] Poor performance of sub cocntractor for engineering elements [Additional Management costs to ICL - contractor risk] Future ammendments to ICL standards and procedures leads to the requirement for changing the design Chill beam detailed design solution is not suitable for purpose Reserve Matters not met - additional cost required to meet detailed planning conditions No alternative location has been identified for the multi faith Prayer Room Damage/ disconnection of services to other campus buildings during enabling works - MINOR ITEMS Delay to sign off of change orders within the scheme leading to uncertainty regarding cost and time Indequate commissioning and validation of facility leading to dissatisfied users post occupation
200,000
150,000
100,000
150,000
120,000 Open
Reduction
ECH
Ongoing
14/07/08
100,000
75,000
50,000
75,000
60,000 Open
Reduction
Comprehensive evaluation of sub contractor designers as part of main tender evaluation. Review any ammendments to ICL standards and procedures when issued
ECH
Apr-09
14/07/08
200,000
150,000
50,000
133,333
100,000 Open
ECH
Ongoing
Advice implementation of ammended ICL standards prior to inclusion within project Ensure that users have an understanding of the chilled beam system to be provided Discharge conditions as soon as possible
ECH
Ongoing
66 Project
P. Chiew
Hoare Lea
Design
3 1,000,000
750,000
250,000
666,667
133,333 Open
Transference
Chilled beams mock up to be carried out Regular discussions with LBHF to ensure they are satisfied with the progress of the design Coordinate and monitor decant works Comprehensive survey of existing services Ensure sign off all change orders prior to Stage E report sign off Ensure revised ICL commissionning & validation standards and procedures are included within tender docuemnt
HL
May-09
HL
Sep-08
14/07/08
69 Project
P. Chiew
Imperial College
Design
250,000
150,000
100,000
166,667
16,667 Open
Acceptance
SR
Dec-08
SR
May-09
14/07/08
129 Project
P. Chiew
Imperial College
03/11/08 Imperial College 30/04/08 Enabling Contractor 30/04/08 Imperial College 06/03/08 Contractor
Enabling Works & Decant Activity Enabling Works & Decant Activity Organisation
10,000
5,000
2,000
5,667
1,133 Open
ECH
Mar-09
77A
Project
P. Chiew
Hoare Lea
150,000
100,000
50,000
100,000
80,000 Open
Transference
ECH
Dec-08
Desktop study of all existing services information Ensure change orders signed off as created Milestone for 'booking of ICL validators' to be included within the programme
HL
Sep-08
14/07/08
56 Stage
P. Chiew
Imperial College
750,000
500,000
250,000
500,000
100,000 Open
Reduction
ECH
Jan-09
ECH
Ongoing
14/07/08
52 Project
A. Collins
EC Harris
Organisation
350,000
250,000
200,000
266,667
53,333 Open
Reduction
TT / Design Team
Jan-09
ECH
Sep-08
14/07/08
50 Project
A. Collins
T&T
55 Stage
P. Chiew
EC Harris
30/04/08 N/A
P. Chiew P. Chiew
Project Project
P. Chiew P. Chiew
30/04/08 Imperial College 30/04/08 Imperial College 10/07/08 Imperial College 10/07/08 Hoare Lea
P. Chiew
Project
P. Chiew
Imperial College
P Gudge
Project
P Gudge
Hoare Lea
P Gudge
Project
P Gudge
Sheppard Robson
P Gudge
Project
P Gudge
Imperial College
Cost Plan exceeds budget because of inability to undertake extensive market testing of cost plan due to insufficient/late design information Organisation Impact of duty holder comments of Stage E/tender package on tender programme Enabling Works Unforeseen obstruction (in the ground) & Main Works Organisation Timescales for the installation of HH CHP does not coincide with Block L project Programme Liquidated damages are insufficient to cover ICL's cost if construction is in delay Design Detailed aspects of Engineering services of design not in accordance with IC published standards Design Architectural aspects of design not in accordance with IC published standards Programme Inadequate commissioning time allocated within construction/delivery programme Enabling Works Space allocated for decant staff & Decant Activity insufficient. Areas of design where crossover occurs between IC and ICHT do not meet ICHT standards Design Several aspects of the design would need to be amended to accommodate requirements of alternative specialist equipment - current design is based on Siemens Enabling Works Delay in achieving the J Block outline & Decant Activity planning consent impacting on the commencement of the demolition of J block Construction Lack of coordination between contractor and client direct equipment Design
Organisation
500,000
350,000
250,000
366,667
36,667 Open
Reduction
SR
Ongoing
TT to ensure DT are fully aware of what and when key packages are required.
TT
Ongoing
14/07/08
400,000
250,000
100,000
250,000
50,000 Open
Reduction
ECH
Jan-09
14/07/08
1 1
2 2
200,000 750,000
150,000 500,000
100,000 250,000
150,000 500,000
Reduction Reduction
Review all service information Regular programme discussions between Block L team and ICHT to ensure both projects tie in ICL to advice proper calculation of damages Ensure specification complies with IC requirements Ensure specification complies with IC requirements Clarify within tender documentation commissioning requirements and critically evaluate contractor's programme Monitor IC decant programme and ensure corrective action if required Single point of contact within ICHT to disseminate information ICHT/ICL to re-confirm that Siemens is the preferred equipment Supplier
ECH ECH
Dec-08 Ongoing
Scan prior to any excavation works Ensure legal documentation in place between IC/ ICHT to guarantee delivery
ECH IC (AS)
Oct-08 Sep-08
14/07/08 14/07/08
250,000
200,000
100,000
183,333
36,667 Open
Acceptance
ICL
Dec-08
14/07/08
500,000
350,000
100,000
316,667
63,333 Open
Reduction
HL
Dec-08
ECH
Dec-08
14/07/08
250,000
200,000
150,000
200,000
40,000 Open
Reduction
SR
Dec-08
ECH
Dec-08
14/07/08
500,000
400,000
100,000
333,333
66,667 Open
Reduction
ECH
Apr-09
Ensure adequate commissioning time within tender docs and specify items required for commissioning
TT
Dec-08
14/07/08
P Gudge
Project
P Gudge
Imperial College
250,000
200,000
150,000
200,000
20,000 Open
Reduction
Ongoing
P. Chiew
Project
P. Chiew
Sheppard Robson
500,000
250,000
100,000
283,333
56,667 Open
Reduction
Jul-08
P. Chiew
Project
P. Chiew
Sheppard Robson
08/09/08 Contractor
500,000
300,000
200,000
333,333
66,667 Open
SR
Sep-08
P. Chiew
Project
P. Chiew
Imperial College
250,000
150,000
75,000
158,333
31,667 Open
P. Chiew
Project
P. Chiew
Imperial College
250,000
150,000
100,000
166,667
33,333 Open
Currently there is a 8 week mobilisation period after the appointment of the demolition contractor prior to the commencement of demolition Ensure full coordination between users and contractor including early visibility of Group 2/3 equipment Reduction Carry out desktop study & site investigation to verify borehole suitability Comprehensive evaluation of suppliers as part of main tender evaluation. Inflation / Deflation agreements to be clearly identified with main contractor during contract negotiations
Confirmation of scope of works for IC (user areas where IC personnelwill decant coordinator) to ICHT stakeholders to review Design Team drawings which affect the ICHT areas ICHT/ICL to advice within a timely ICL manner if they wish to proceced with an alternative equipment specialist to ensure minimal impact on the programme Demolition Contractor to start demolishing L block first
Sep-08
14/07/08
Dec-08
14/07/08
Ongoing
ECH
Ongoing
P. Chiew
Project
P. Chiew
Imperial College
Design
Boreholes do not yield sufficient amount to satisfy the GLA Poor performance of architectural elements suppliers i.e. supplier of keys/locks Market Volitility:- Reduced prices / inflation allowance within cost plan. Potential risk priced by Tenderers exceeds adjusted Cost Plan Allowances
500,000
350,000
150,000
333,333
66,667 Open
HL
Jul-08
Full engagement with users and ensure that users are aware of milestones and implication of not meeting milestones Ensure sustainable alternatives are available
Matt Lee
HL
Jul-08
14/07/08
P Gudge
Project
P Gudge
Sheppard Robson
Design
50,000
40,000
30,000
40,000
16,000 Open
Reduction
ECH
Apr-09
14/07/08
M.Irmiger
Project
M.Irmiger
Imperial College
Construction
4 2,000,000
1,500,000
750,000
1,416,667
566,667 Open
Transference
TT
Jun-09
TT
Jun-09
20/01/09
- 109
###############