Professional Documents
Culture Documents
I-91 Interchange 19 Improvements I-91 Interchange 19 Improvements
I-91 Interchange 19 Improvements I-91 Interchange 19 Improvements
I-91 Interchange 19 Improvements I-91 Interchange 19 Improvements
Northampton, MA
Project Advisory Committee
Meeting #10
June 5, 2012
Meeting Agenda
Review of Alternatives Discussion of Evaluation Matrix Discussion of Public Information Meeting
I-91 Interchange 19
June 5, 2012
Concept 13
Concept 13 Intersection & Ramp Improvements
Modified to add additional WB left turn lane onto SB on-ramp Modified to add additional NB through lane to Damon Road from NB off-ramp Left turn lane extended under bridge by relocating sidewalk or replacing the structures Improves on and off-ramps
I-91 Interchange 19
June 5, 2012
Concept 13
Concept 13 Intersection & Ramp Improvements
Modified to add additional WB left turn lane onto SB on-ramp Modified to add additional NB through lane to Damon Road from NB off-ramp Left turn lane extended under bridge by relocating sidewalk or replacing the structures Improves on and off-ramps
I-91 Interchange 19
June 5, 2012
Concept 13A
Concept 13A Intersection & Ramp Improvements with Roundabout
Adds additional WB left turn lane onto SB on-ramp Converts Damon Road/Route 9 intersection to a roundabout Left turn lane extended under bridge by relocating sidewalk or replacing the structures Improves on and off-ramps
I-91 Interchange 19
June 5, 2012
Concept 13B
Concept 13B Ramp Improvements with Double Roundabout
Converts Damon Road/Route 9 & Route 9/SB On-Ramp intersections to roundabouts Improves on and off-ramps
I-91 Interchange 19
June 5, 2012
Concept 13B
Concept 13B Ramp Improvements with Double Roundabout
Converts Damon Road/Route 9 & Route 9/SB On-Ramp intersections to roundabouts Improves on and off-ramps
I-91 Interchange 19
June 5, 2012
Concept 13C
Concept 13C Ramp Improvements with Roundabout at SB On-Ramp
Converts Route 9/SB On-Ramp intersections to roundabout Improves on and off-ramps Adds additional NB through lane from NB Off-Ramp to Damon Road
I-91 Interchange 19
June 5, 2012
Alternatives C13 Rating Discussion Rating C13A Discussion Rating C13B Discussion Rating C13C Discussion
Construction Costs were estimated by quantifying the labor and material required for the major construction items for each alternative using the 2012 Weighted Average Bid Price Information available at the MassDOT website.
Construction Costs were estimated by quantifying the labor and material required for the major construction items for each alternative using the 2012 Weighted Average Bid Price Information available at the MassDOT website.
$3.4 M
Construction Costs were estimated by quantifying the labor and material required for the major construction items for each alternative using the 2012 Weighted Average Bid Price Information available at the MassDOT website.
$3.8 M
Construction Costs were estimated by quantifying the labor and material required for the major construction items for each alternative using the 2012 Weighted Average Bid Price Information available at the MassDOT website.
$4.0 M
Construction Costs were estimated by quantifying the labor and material required for the major construction items for each alternative using the 2012 Weighted Average Bid Price Information available at the MassDOT website.
$3.7 M
Duration (Years)
duration has been estimated based on the anticipated time required to implement a traffic management plan, relocate necessary utilities and to construct the major items required for each alternative.
Construction duration has been estimated based on the anticipated time required to implement a traffic management plan, relocate necessary utilities and to construct the major items required for each alternative.
2-3
Construction duration has been estimated based on the anticipated time required to implement a traffic management plan, relocate necessary utilities and to construct the major items required for each alternative.
2-3
Construction duration has been estimated based on the anticipated time required to implement a traffic management plan, relocate necessary utilities and to construct the major items required for each alternative.
2-3
Construction duration has been estimated based on the anticipated time required to implement a traffic management plan, relocate necessary utilities and to construct the major items required for each alternative. In addition to repaving, widening and infrastructure modifications, construction staging at the roundabout will require more elaborate staging, including temporary realignment of the intersection.
N/A
Majority of work involves repaving, widening and modifications to existing infrastructure. Two primary stages of construction are anticipated.
In addition to repaving, widening and infrastructure modifications, construction staging at the roundabout will require more elaborate staging, including temporary realignment of the intersection.
In addition to repaving, widening and infrastructure modifications, construction staging at the roundabouts will require more elaborate staging, including temporary realignment of the intersections.
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
Second level
Crash Rates
No Change
Fifth level
Emergency Vehicle Access
No Change No Change
Roundabout is more difficult to maneuver than a signalized intersection with emergency pre-emption but substantial queue reductions facilitate emergency vehicle passage.
Roundabout is more difficult to maneuver than a signalized intersection with emergency preemption but substantial queue reductions facilitate emergency vehicle passage. Roundabout is more difficult to maneuver than a signalized intersection with emergency pre-emption.
Roundabout is more difficult to maneuver than a signalized intersection with emergency preemption.
Traffic Calming
No Change
No Change as currently developed however there is a possibility to add some traffic calming elements (street trees, median, etc.) if this alternative advances into design.
A roundabout at Damon Rd/Route 9 intersection will force vehicles to reduce speed when entering the roundabout. The roundabout will also serve as a visual signal to drivers of a change in roadway character.
A roundabout at Damon Rd./Route 9 and 2nd at Route 9/SB On-ramp will magnify the traffic calming affect discussed in 13A.
A roundabout at SB On-Ramp intersection will force vehicles to reduce speed when entering the roundabout. The roundabout will also serve as a visual signal to drivers of a change in roadway character.
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
Delays (LOS)
Travel Time
No Change
Reduced delay improves travel time through project area. Reduction in average and maximum queues
Reduced delay improves travel time through project area. Significant reduction in average queues, slight reduction in maximum queues
Reduced delay improves travel time through project area. Reduction in average and maximum queues
Queuing
No Change
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
COMMUNITY IMPACTS
No Build
No Change
No recreation impacts anticipated. Wider sidewalks will improve pedestrian access to Elwell Conservation Areas .
No recreation impacts anticipated. Wider sidewalks will improve pedestrian access to Elwell Conservation Areas .
Community Cohesion
Improved sidewalk network and wider shoulders make roadway more pedestrian and bicycle friendly.
Improved sidewalks and paths make roadway more pedestrian and bicycle friendly. Intersection of Route 9 with Damon Road becomes unsignalized, but the roundabout encourages lower speeds throughout the project area.
Improved sidewalks and paths make roadway more pedestrian and bicycle friendly. Route 9 intersections become unsignalized, but the roundabouts encourage lower speeds throughout the project area.
Agricultural
No Change
Aesthetics
No Change
Opportunities for improved streetscape along Route 9. Some clearing along ramps will be required.
Central island of roundabout provide area for landscaping. Opportunities for improved streetscape along Route 9. Some clearing along ramps will be required.
Central island of roundabouts provide area for landscaping. Opportunities for improved streetscape along Route 9. Some clearing along ramps will be required.
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
No Build
No Change
No Impacts Anticipated
No Impacts Anticipated
No Impacts Anticipated
No Change
No Impacts Anticipated Slight improvement in air quality due to reduced congestion along Route 9
No Impacts Anticipated Slight improvement in air quality due to reduced congestion along Route 9 Some increase in light impacts to residences at roundabout.
No Impacts Anticipated Slight improvement in air quality due to reduced congestion along Route 9 Some increase in light impacts to residences at roundabouts.
No Impacts Anticipated Slight improvement in air quality due to reduced congestion along Route 9 Some increase in light impacts to residences at roundabout.
No Change
Light
No Change
No Impacts Anticipated
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
No Build
Wider sidewalks; improved pedestrian ramps, but slightly longer crossing distance
Fifth level
Bicycle Accommodation
No Change
Intersections of Route 9 with ramps can be made more parallel, reducing bike-car conflicts
Traffic operates at lower speeds through the roundabout. Eastbound Route 9 bicyclists may encounter more conflict points through the roundabout.
Traffic operates at lower speeds through the roundabout. Eastbound Route 9 bicyclists may encounter more conflict points through the northern roundabout.
Transit Access
No Change
Reduced intersection delay along Route 9 (east-west) will make a small improvement in overall transit travel time.
Reduced intersection delay along Route 9 (east-west) will make a small improvement in overall transit travel time.
Reduced intersection delay along Route 9 (eastwest) will make a small improvement in overall transit travel time.
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
Alternatives C13A C13B $4.0 M 2-3 C13C $3.7 M 2-3 $3.8 M 2-3
Fifth level
Rare & Endangered Species Open Space Air Quality Light Alternatives MULTI-MODAL No Build Rating Pedestrian Accommodation C13 Rating C13A Rating C13B Rating C13C Rating `
LEGEND
Benefits
Some
Moderate
Substantial
I-91 Interchange 19
June 5, 2012
Alternatives No Build
$0 0
C13
$3.4 1
C13A
$3.8 2-3
C13B C13C
$4.0 2-3 $3.7 2-3
Second level
Crash Rates Third level SAFETY Emergency Vehicle Access Fourth level
Fifth level
TRAFFIC
COMMUNITY IMPACTS
Property Aesthetics
I-91 Interchange 19
June 5, 2012
Next Steps
Modify Evaluations (if necessary) Review Modifications with PAC (if necessary) Public Informational Meeting PAC Meeting(s) to Select Alternatives Begin Design (if required)
I-91 Interchange 19
June 5, 2012
I-91 Interchange 19
June 5, 2012