Professional Documents
Culture Documents
3 Water Worth
3 Water Worth
1/EMCh, 1998
12
Reliability assessment technique for HVdc
systems
D A Waterworth,
1
ME
C P Arnold,
2
MSc, PhD, CEng, MIEE, SMIEEE
and N R Watson,
2
BE(Hons), PhD, MIEEE, MIPENZ
This paper describes a computational analysis technique for determining the stand
alone reliability of HVdc transmission systems. A contingency enumeration and
simulation package named DCREL is used. DCREL uses the fault tree contingency
enumeration technique, and a customised version of the Ford-Fulkerson maximal
network flow algorithm for contingency simulation. Indices recommended by
CIGRE for the reporting of HVdc operation are calculated using the Frequency
and Duration technique. The New Zealand hybrid bipolar HVdc link is used to
illustrate the methodology. A failure mode and effects analysis is performed to
determine the reliability of the system.
Keywords: reliability HVdc transmission systems network flow algorithm
1
Power Systems Consultants NZ Ltd, and
2
Senior Lecturer, Department of
Electrical and Electronic Engineering, University of Canterbury, Private Bag
4800, Christchurch
This paper, which was originally presented at the 1996 IPENZ Conference, was
received in revised form on 7 December 1997
1. Introduction
1.1 Background
A certain amount of generation capacity must be maintained in an electrical power system as spinning
reserve to allow for the possibility of loss of generation or sudden increased demand. The spinning
reserve required is a function of the size of the major generators and the load demand and this imposes
a constraint on generation scheduling which results in increased electrical losses in the system, and
increased fuel costs.
It is common practice for neighbouring power utilities to connect their networks with interties. If
one utility cannot supply its customers load demand, and a neighbouring utility has an excess of
generation available, then this excess can be supplied to the deficient system via the intertie. Because
the probability of requiring spinning reserve is low, the interconnected systems can share the same
reserve, benefiting both with significant cost savings.
In addition to reducing the spinning reserve requirement, an intertie can provide an increase in
system security. The total generation capacity dictates the inertia or stability of an electrical network. A
small system will have very little inertia, increasing the likelihood of frequency variations and voltage
fluctuation. When two small systems are interconnected, the result is a single large system with less
likelihood of voltage and frequency problems.
Systems may be interconnected via either HVac or HVdc interties, or even a mixture of both. Each
type of link has its advantages and disadvantages depending on the electrical and operational
characteristics of the systems being connected. The use of HVdc transmission links has increased
markedly over the past two decades and they have proved to be cost effective alternatives to long HVac
links and in many cases are the only option. When connecting systems with different frequencies an
HVac link cannot be used and it may be impractical when the systems have different control policies or
when underground or under sea cables must be used for the link.
1.2 HVdc intertie reliability assessment
The basics methods of reliability assessment have been established over many years and have been
successfully applied to power systems
1
. A basic introduction to power system reliability can be found in
the IEE Power Engineering Journals of 1992-93.
2,3
13
HVdc links are increasingly being used to interconnect power systems operating under market type
contracts. The contracts may well set performance reliability targets and include penalties for non-
achievement. It is therefore important that good reliability assessment of HVdc links is done both prior
to construction and during its operating lifetime.
This paper discusses the basic techniques necessary to determine the reliability of an HVdc link and
the New Zealand hybrid bipolar HVdc link is used to illustrate the methodology. A contingency
enumeration and simulation package named DCREL is used. This program has been produced as part
of the ongoing power system research activity at the University of Canterbury. DCREL uses the fault
tree contingency enumeration technique, and a customised version of the Ford-Fulkerson maximal
network flow algorithm for contingency simulation. Indices recommended by CIGRE for the reporting
of HVdc operation are calculated using the Frequency and Duration technique. A failure mode and
effects analysis is then performed to obtain the reliability diagram of the system.
From a reliability-worth view point, the power system state space consists of all possible
combinations of generation levels, load demand levels and intertie capacities. Each combination is
termed a scenario, and each scenario can be classified into either the A-set (acceptable set, comprising
scenarios which do not result in loss of load) or the L-set (loss of load set).
4
The total probability of the
L-set is the Loss of Load Probability (LOLP). Where an HVdc link is included in the overall system, it
is necessary to first consider the HVdc link in isolation. It is the determination of the set of capacities
for HVdc interties which is considered in this paper.
2. HVdc intertie capacity levels
A typical HVdc system consists of the following components: ac switchyard; ac filters; reactive
compensation; valve groups and auxiliaries; converter transformers; dc filters; smoothing reactors; dc
switchgear; dc line; and neutral electrodes.
At any given time each item of plant will be in one of two states: either available or unavailable.
Items may be unavailable either due to a forced outage or unplanned outage, or due to a scheduled
outage involving routine maintenance which cannot be performed when the plant is energised. Items
may also be unavailable because they depend on other items being available before they can operate.
The state space of the HVdc system consists of all possible combinations of equipment states. For
each combination, there exists a maximum MW capacity C which may be transmitted through the
system. The combination where all items are available is termed the base case, and all other
combinations are termed outage cases.
3. Determining the outage capacity
To determine the outage capacity, the system must be represented as a flow network
5
using the
reliability diagram concept. The reliability diagram represents the available transmission capacity
between two nodes, the source s and the sink t. The source node represents the rectifier station whilst
the sink represents the inverter. For analysis purposes it is assumed that the ac network can supply and
absorb as much power as the HVdc link can transport. Because many HVdc transmission systems are
bi-directional, a separate reliability diagram and operating table is required for each transmission
direction. Multi-terminal systems can be analysed in a similar manner.
6
In most cases, each component can represented by a single arc on the reliability diagram. Each arc
is assigned an integer capacity c
i
representing the amount of power curtailed when the component is
unavailable. More complex failure behaviour may require more than one arc to represent a single
component. Some arcs may appear for modelling purposes only, and do not represent any specific
component.
For each outage the network flow routine is called with the outages component states as the input.
The arc capacities are assigned using the following expression:
available is Component =
e, unavailabl is Component
i
c
i 0 =
A
i
i
where Ai = Capacity of all arcs representing component I
14
In some cases it is not possible to explicitly assign a capacity to a component. Occasionally the
capacity of one component is dependent on the state of others. This often occurs when k items out of n
are required for a subsystem to operate. The capacity of each item is ci provided at least k items are
available, and zero if there are less than k items available. To model this behaviour, DCREL allows
components to be grouped. Combinations of available components from the group are listed, with
component capacities for the combination. For any combinations which are not listed, the components
are assigned a capacity of zero.
The output of the flow routine is the outage capacity C
j
and a list of components which, although
available, had no flow through them. Such components must be connected in series with one or more
unavailable components and are set to isolated. Since the failure rate of electrical devices is
proportional to the applied voltage and current, isolated equipment is unlikely to fail.
7
For this reason
the failure rate of isolated equipment is set to zero for the duration of isolation. The capacity of all
isolated components is zero.
3.1 Flow routine
The flow routine used by the program DCREL is based on the method of Sankar et al.
8
which uses a
modified Ford-Fulkerson maximal flow algorithm.
9,10
When DCREL is first invoked, all paths from s
to t are generated using the Breadth-First Technique (BFS). Only the arc capacities and not the
topology of the network change when different outages are considered, so path enumeration is
performed only once. The paths are then sorted into order of increasing number of arcs. This ordering
guarantees that the maximal flow can be determined by scanning every path once only.
To determine the network flow, each path is scanned in turn. Scanning involves determining the
maximum flow which the path can carry without violating any arc capacities.
Each component has two flags; zero flow and non zeroflow. For every arc along a path the
algorithm sets either the zero flow or non zeroflow flags. Once all paths have been considered, the
status of these flags is checked for each component. Any available component where the zero flow flag
is set and the non zeroflow flag is unset must be in series with one or more unavailable components
and hence becomes isolated.
Since the flow routine can alter the state of components from available to isolated, and the capacity
of grouped components is dependent on the group state, the capacity of the grouped components may
change. When this occurs the network flow must be recalculated using the changed component states.
The routine iterates until the system capacity and component states remain the same for two successive
iterations.
4. Determining the state space
The state space of all outages is determined using fault tree enumeration.
1,11
Each outage state, and the
base state appear as nodes on the fault tree. Each node can be linked to a single parent and multiple
children. Every child node is related to its parent by the transition of a single component state from
available at the parent to unavailable at the child. This assumes that simultaneous outages do not
occur, and isolated components cannot transition to unavailable. The last assumption is not necessarily
correct as continuously operating control equipment could fail.
To illustrate this, consider a four component system at an arbitrary node j on the tree. If the system
state j is, for example, {A,A,I,U} where A represents available, U represents unavailable and I
represents isolated, then node j will have two child nodes when either of the available states is made
unavailable. These child nodes are {U,?,?,U} and {?,U,?,U}. The ? denotes a state which will not be
determined until after the flow calculation has been performed, and will be either available or isolated.
Hence before the child nodes can be determined for any given node, the flow routine must be called
with the given node state as the input.
For practical systems it has been determined that the likelihood of more than three items of plant
being unavailable is negligible. For this reason enumeration is only performed up to level three. This
saves a considerable amount of processing time and does not degrade the solution accuracy.
15
5. Determining the indices
For each outage the probability, frequency and duration of the outage is determined using the
Frequency and Duration (F&D) technique.
11
The F&D technique assumes that components are
statistically independent. Because this assumption is not always valid, the indices are an
approximation. However the error due to the approximation is small and can be ignored. The F&D
technique requires as its input the failure rate (i) and mean time to repair (ri) for each component i.
The limiting state probability of an outage j is defined as:
P
=
P i
j
n
1 = i
j
where
'
,
_
D
i
=
D
i
j
n
1 i=
-1
j
where:
'
,
_