WORK SLIP FOR CONSTRUCTION OF 2 NUMBERS OF 110 KV TERMINAL BAYS AT 220/110/11 KV K B CROSS STATION IN TIPTUR TALUK Description SUPPLY ERECTION CIVIL TOTAL AS PER DWA AS PER ACTUALS EXCESS % EXCESS
WORK SLIP FOR CONSTRUCTION OF 110 KV DC LINE FROM 220/110/11 KV K B CROSS STATION TO LINK TO THE EXISTING 110 KV THIMMANAHALLY TAP POINT IN NEW CORRIDOR FOR A DISTANCE OF 26 KMS Description SUPPLY ERECTION CIVIL TOTAL AS PER DWA AS PER ACTUALS EXCESS % EXCESS
Authorised Signatory.
AS PER DWA
AS PER ACTUALS
EXCESS
% EXCESS
Authorised Signatory.
Construction of 2 Numbers of 110 KV Terminal bays at 220/110/11 KV KBCross Station in Tiptur taluk for construction of 110 KV DC line from K.B.cross station to link to the existing 110 KV Thimmanahally tap point in new corridor for a distance of 26 Kms WORK SLIP OF CIVIL PORTION FOR TERMINAL BAY
Sl. No. As per DWA Description Unit Qnty Unit rate As per actuals Qnty Unit rate Excess Qnty
Amount 6=(4*5)
Amount 9=(7*8)
Remarks
10=(7-4)
1. Grounding of equipment with GI flat 50 x 6 mm and connecting equipment to the earth mat/ground pit. Each point of earthing with all formation works like Mtrs bending,twisting,drilling of holes and connecting by welding(inclusive of T & P and consumables) to the earthmat/Ground pit/point of earth connection 2. Grounding of equipmetn by providing cast iron pipe of 100 mm ID 13 mm thickness ,2.75 meters long with 2 part clamp out of GI flat 50 x 6 mm continuously welded aroudn the pipe using cast iron welding electrodes as per drawing including the cost of excavation,providing and laying homogeneous mixture of charcoal lumps,salt and sand all round the pipe as per specification and supplying and fixing of RCC collar of size 450 mm dia, 450 mm height and 50 mm thick 3.providing 25 mm dia MS rod 1.05 meters long earth mat spikes including heating, bending top 50 mm over lap flattening and making spike edge at one end dfiving into the earth below the ground level and welding the rod with ground mat flat
240
194.6
46704.00
590
194.6
114814.00
350
68110.00
Nos.
6532.40
39194.40
6532.40
58791.60
19597.20
Nos.
0.00
0.00
15
166.00
2490.00
15
2490.00
4. supplying of MS flat 50 x 6 mm welding and applying ACB paid to welded portion as per Rmtr the drawing/standard specification and consolidation without sodium bentonite clay 5.EXCAVATIONS : Supply of all labour,materials,machinaries etd., & excavation with all leads and lifts for tower foundations including back filling with available approved earth/approved new earth, watering and compaction in layers of 150 mm thick, disposal of surplus earth to the places directed, spreading,levelling etc., and other items not specified Cmtr but required for the completion of work, complete for the following types of soil & rock as per detailed specification, drawings and directions of the engineer incharge of the works, Dry fissured Rock Total
0.00
0.00
350
115.00
40250.00
350
40250.00
Approval obtained vide L.No CEE/Tumkur/T Z/SEE(O)/AEE1/3461-62 dtd 5.09.2011 and for non DWA items current SR rates is adopted
0.00
0.00
180
700.00
126000.00
180
126000.00
85898.40
342345.60
256447.20
Authorised Signatory.
Page 4 of 7
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED DWA NO:T &P/KBCross-Thimmanahally/TLSS-413/1834 dtd 15.09.2010
WORK SLIP FOR CONSTRUCTION OF 110 KV DC line from 220/110/11 KV K.B.Cross Station to link to the existing 110 KV Thimmanahally tap point in new corridor for a distance of 26 Kms WORK SLIP FOR SUPPLY OF MATERIAL
As per DWA
Unit FOR Destination Price including all duties & Taxes. Total FOR Destination Price including all duties & Taxes.
As per actuals
Unit FOR Destination Price including all duties & Taxes. Total FOR Destination Price including all duties & Taxes.
Sl. No.
Description
Unit
Qnty
Wt. in MT
Total MT
Qnty
Wt. in MT
Total MT
Excess Qnty
Excess Amount
Remarks
1 B)
Fabrication and supply of galvanised 110 KV Transmission line towers TOWER TYPE 'B' a) Normal tower No/MT 13 3.05987 39.77831 63027.50 2507127.43 14 3.05987 42.83818 63027.50 2699983.39 1
Loc No 73 B+3 tower provided in place of A+3 16195.546 tower,Loc No 71 C+3 tower provided in place of A+Otower, 192855.956 approved vide L.No CEE/SEE(O)/ 45631.91 3461-62 dtd 5.09.2011
192855.956
No/MT
13
0.25696
3.34048
63027.50
210542.10
14 0.25696
3.59744
63027.50
226737.65
1.000
No/MT
3.05987
27.53883
63027.50
1735703.61
10 3.05987
30.59870
63027.50
1928559.56
1.000
No/MT No/MT
0.00 145759.92
1 10
0.724 0.257
0.724 2.570
63027.50 63027.50
45631.91 161980.68
1.000 1.000
16220.757
No/MT
27
4.2466
114.6579
63027.50
7226602.68
30
4.2466
127.3977
63027.50
8029558.54
12.73977
802955.85
0 0 0
1 2 1
e) Stubs for Normal, 3m & 6m No/MT extension towers Supply of bolts and nuts and washers required for 110 KV DC transmission line TOWER TYPE 'B' a) Normal tower No/MT d) Stubs for above No/MT
27
0.364
9.826
63027.50
619298.13
30
0.3639
10.9176
63027.50
688109.03
1.09176
68810.90
Additional towers at location 54 (a), change of towers to D type at Loc No 54 & 55 as per site condition approved in check survey L.No SEE/Tr (W & M)/4146 dtd 13.01.2011
2 B)
13 13
0.08405 0.001488
1.09265 0.01934
77180.00 77180.00
84330.73 1492.97
14 0.08405 14 0.00149
1.17670 0.02083
77180.00 77180.00
90817.71 1607.81
0.08405 0.00149
6486.98 114.84
Page 5 of 7
As per DWA
Unit FOR Destination Price including all duties & Taxes. Total FOR Destination Price including all duties & Taxes.
As per actuals
Unit FOR Destination Price including all duties & Taxes. Total FOR Destination Price including all duties & Taxes.
Sl. No.
Description
Unit
Qnty
Wt. in MT
Total MT
Qnty
Wt. in MT
Total MT
Excess Qnty
Excess Amount
Remarks
c)
D)
TOWER TYPE 'C' a) Normal tower b) 3 meter extension c) Stubs for above TOWER TYPE 'D' a) Normal b) 3M Extension c) 9 meter extension d) 9 cross arm
9 0 9 27 0 0 0 27
3 a) b) c) d) e) f) g) 5
e) Stubs for Normal, 3m & 6m No/MT extension towers Tower Accessories Anti climbing devices (Set) as per specification for 110 KV DC tower Number plates (1 No per tower) Caution plate (1 No per tower) Circuit plates Phase plates (Set of 3 Nos) Grounding sets i) Pipe type set Earth bonds ii) 450 mm long Insulator string with clamps, arcing horns and Hardware for ACSR conductor a) single tension string fittings using 8 Nos of 90 KN disc insulators, clamps,arcing horns and Hardware (Set) Accessories for ACSR Lynx conductor PG clamps Vibration dampers Hardware and accessories for ground wire P G clamps Compression type tension clamp TOTAL Nos Nos Set Nos Nos Nos Set Set Nos
Set
570.000
7123.50
4060395.00
582
7123.50
4145877.00
12.000
85482.00
6 D) e) 7 c) d)
600.000 1236.000
506.50 823.00
303900.00 1017228.00
648 1248
506.00 823.00
327888.00 1027104.00
48.000 12.000
23988.00 9876.00
Nos Nos
106.000 112.000
243.00 770.50
112 118
243.00 770.50
6.000 6.000
Authorised Signatory.
WORK SLIP FOR CONSTRUCTION OF 110 KV DC line from 220/110/11 KV K.B.Cross Station to link to the existing 110 KV Thimmanahally tap point in new corridor for a distance of 26 Kms
Qnty
Wt. in MT
Total
Unit rate
Amount
Qnty
Wt. in MT
Total
Unit rate
Amount
Excess Qnty
Excess Amount
Remarks
Erection of Towers including tack welding, fixing of tower accessories and earthing (The weight includes the wt. of std., tower & stubs, including bolts nuts and washers) Note :- The tenders are reauired to quote the rates taking in to consideration the charges for sorting of towers, loading, unloading, fixing of accessories, grounding, stub seting and tack welding B) Tower type B a) Normal tower d) Stubs for above TOWER TYPE 'C' a) Normal tower b) 3 meter extension c) Stubs for above TOWER TYPE 'D' a) Normal b) 3M Extension c) 9 meter extension d) 9 cross arm e) Stubs for Normal, 3m & 6m extension towers TOTAL
No of Towers
Ceiling Weight in MT
Total weight in MT
Total weight in MT
13 13 9 0 9 27 0 0 0 27
3.14392 40.87096 0.25845 3.35985 3.14392 28.29528 0.00000 0.00000 0.25845 2.32605 4.4274 119.5387 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
4920.00 4920.00 4920.00 0.00 4920.00 4920.00 0.00 3290.00 3290.00 4920.00
201085.12 16530.46 139212.78 0.00 11444.17 588130.50 0.00 0.00 0.00 48963.50 1005366.53
14 3.14392 44.01488 14 0.25845 3.61830 10 3.14392 31.43920 1 0.72400 0.72400 10 0.258 2.58460 30 1 2 1 30 4.427 0.826 2.344 0.276 0.369 132.822 0.826 4.689 0.276 11.058
4920.00 4920.00 4920.00 4920.00 4920.00 4920.00 4920.00 4920.00 4920.00 4920.00
216553.21 17802.04 154680.86 3562.08 12716.23 653484.24 4065.89 23068.50 1357.92 54403.88 1141694.86
1.000 1.000 1.000 1.000 1.000 13.283 0.826 4.689 0.276 1.106
15468.09 1271.57 15468.09 3562.08 1272.07 65353.74 4065.89 23068.50 1357.92 5440.39 136328.33
c)
0.368590 9.951930
WORK SLIP FOR CONSTRUCTION OF 110 KV DC line from 220/110/11 KV K.B.Cross Station to link to the existing 110 KV Thimmanahally tap point in new corridor for a distance of 26 Kms WORK SLIP OF Civil PORTION
As per DWA Sl. No. 1 Item Description 2 EXCAVATIONS : Supply of all labour,materials,machinaries etd., & excavation with all leads and lifts for tower foundations including back filling with available approved earth/approved new earth, watering and compaction in layers of 150 mm thick, disposal of surplus earth to the places directed, spreading,levelling etc., and other items not specified but required for the completion of work, complete for the following types of soil & rock as per detailed specification, drawings and directions of the engineer incharge of the works ii) Dry fissured rock/ordinary rock/laterite soil iii)Hard rock by blasting/Hard laterite iv) Wet Black cotton soil PROVIDING 1:2:4 CONCRETING: Supply of all labour materials, tools & plants etc., and providing 1:2:4 concrete using 20mm & down size jelly and clean approved sand for foundation of lattice type transmission line towers including ply wood/steel centering and shuttering, scaffolding, curing and other items not mentioned here in but required for completion of works as per detailed specification, drawing and directions of engineer incharge of works for different types of tower foundations i) Plain cement concrete 1 :3:6 Cmtr ii)plain/reinforced cement concrete 1 : 2:4 (Excluding cost of steel and Cmtr fabrication charges) PROVIDING STEEL REINFORCEMENT: Providing and fabricating mild steel/HYSD steel reinforcement including straightining , cutting, bending, hooking, lapping and or welding wherever required, placing in position tieing with binding wire or approved quality and guage including the cost of binding wire and anchoring to the adjacent member wherever necessary including all laps and wastages etc., complete as per design and specification and directionsfor different types of tower foundations. Total 27.980 4397.40 611.220 5026.00
123039.25 3071991.72 As per acutals Amount 6=4*5
Amount 9= 7 * 8
Excess Qnty
Excess amount
11=9-6
Remar ks
10=7-4
700.00
1193.50 232.40
1679.550
508.81 3290.22
700.00
1193.50 232.40
261249.53 4109760.20
31.430 206.480
138210.28 1037768.48
Kgs
8630.000
50.40
434952.00 21853.500
50.40
1101416.40
13223.500
666464.40
5195926.53
8020023.00
2824096.47
Tumkur
Assistant Executive Engineer (El) No 4 Major Works Sub Division KPTCL, Tumkur