Sourcing Domestic Inverter - Issues and Challenges: ISA Workshop On Solar Inverters - 23 July, 2010
Sourcing Domestic Inverter - Issues and Challenges: ISA Workshop On Solar Inverters - 23 July, 2010
ISA Workshop on Solar Inverters 23rd July, 2010 Dr. J. N. Roy Vice President (R&D/Engineering) Solar Semiconductor Pvt Ltd
Presentation Layout
1. Solar PV Value Chain 2. Company Overview 3. Cost Structure of PV Installation Solar Power Electronics 4. Classification of Inverter 5. Desired Features of Inverter 6. Comparison between Inverter and PCU
Thin Film
Company Overview
A Vertically Integrated System Integrator providing end to end SI services
Our Product & Services
Family of mono and multi crystalline modules
Overview
Global Company founded in 2006 Subsidiaries in India & Dubai
Incorporation
Financials
Solar cells
Strong customer base in the key markets of USA, Europe and India Strategic tie-ups with top tier suppliers
Sizable Manufacturing 200 MW Manufacturing Capacity in Fab City SEZ 200MW North America /Canada Manufacturing by 2011
Power Systems
Team
Experienced Silicon Valley Team, with strong background in high quality, hitech mass manufacturing of Semiconductors and Systems Over 900 full-time employees as of April30, 2010
Apr 06
Jan 07
July 07
Sept 07
Dec 07
Jan 08
Feb 08
Mar 08
Apr 08
Jun 08
Feb 09
Jun 09
Announced IBC Solar as a strategic partner; contract for over 100MW over next three years
UL Certification
Expansion of module manufacturing facility in Hyderabad Signed AS Solar contract for 224MW over 7 years Signed DS Wafer Supply Contract
Date
Nov 2007
Certification
CE Mark ISO 9001:2000 certification IEC 61215 certification IEC 61730 certification CSA listing VDE certification UL certification
Jan 2008
Feb 2008
SPC
Feb 2008
Six Sigma
March 2008
April 2008
Quality Circles
June 2009
Flash testing
Residential Roof
Cost Structure
Cost of Poly- Wafer Cell- Module Cost of Inverter. Costly DC connections. Inverter life issue. Maintenance Issue
No batteries/grid as buffer! Match power consumption with power generation by controlling speed of the pump. Make power generation as close as possible to maximum power
On Grid
Central Inverter
Input
Solar Panel
Half-Bridge Inverter
Transformer
Classical Rectifier
H-Bridge Inverter
Battery
Output
Output Protection
Challenges :PCU
Parallel operation of PCU Units Parallel operation needs synchronism of PCUs Should have communication between PCUs Controlling should be done based on input from each PCUs Control should be there based on inputs from each Battery bank units of PCUs Load Management control is needed Master-Slave mechanism should be available Control should take care of optimal operation of PCUs Control should take care of safe operation of PCUs Failure of one or more of PCUs should not affect Parallel Operation of others
PCU (Cont.d)
Comparison
Comparison INDIAN INVERTERS FORGIEN INVERTERS 5 Year Warranty with AMC. It can be extended to 10 Years Indoor and Outdoor 20 Years has been proved Wireless is available Standardized & Simulation support Greater than 97% 24 V and 48 V are fixed compact size light weight more IEC,TUV,UL
Reliability Flexibility Durability Control Design & Support Efficiency Battery Voltage Size Weight Cost Certification
2 Years Warranty Indoor 20 Years Expected Wireless is not available Custom made less than 94% 24,48,96,120,240 V Large size Heavy weight Less compared to Forgien IEC,TUV
Limitations
1. Indian manufacturer mainly manufactures PCU . 2. PCU combines Inverter and battery charging unit. 3. Indian PCU unit are custom made not standardized to feed customer requirement 3. Engineering support is minimal.
Thank You!