ORAP means (Operational Reliability Analysis Program) is a service provided by Strategic Power Systems, Inc. (SPS) to owners/operators and Original Equipment Manufacturers (OEMs) for monitoring the Reliability, Availability and Maintainability (RAM) of the total plant, both simple and combined-cycle, including gas and steam turbines.
Common Questions
How Often Should I Submit Data? -At a minimum monthly, but optional daily or weekly What Type of Information Should I Enter? - Events - Operational Data - Counter Readings
Events Examples
Failure to Start: used for instantaneous trip prior to completion of start
sequence or unit did not start in the startup time defined by dispatcher.
-Start was initiated and unit could not achieve flame, it was discovered that ignitor cable was cracked, needed replacement. - Start was initiated, unit achieved flame, breaker would not close due to faulty relay.
Events Examples
Forced Outage Automatic Trip (FOA): A trip from a state of operation
when a component failure or other condition which causes the unit to be shut down automatically by the control system.
- Unit tripped on high lube oil temperature, due to a shorted transmitter. Replaced transmitter and the unit returned to service.
Counter Readings
Service Hours Lifetime total for the package. Factored Hours Lifetime total factored fired hours. Fired Starts Start where flame achieved in gas turbine. Lifetime total. Total Starts Number of times that the start button was pushed. Trip Count Number of times the unit tripped.