Planning Engineering & Project Management: Lecturer: Engr. Afshan Naseem
Planning Engineering & Project Management: Lecturer: Engr. Afshan Naseem
Planning Engineering & Project Management: Lecturer: Engr. Afshan Naseem
Earliest (ES) & latest (LS) start Earliest (EF) & latest (LF) finish Slack (S): Allowable delay
Longest path in network Shortest time project can be completed Any delay on activities delays project Activities have 0 slack
A B C D E F G
A B B D C E,F
1 6 3 2 3 4 1
NETWORK SOLUTION
B A
1
D
2
E
3
G
1
C
3
F
4
EF = ES + Activity time
Activity A B C D E F
ES 0
EF 1
LS
LF
Slack
B A
1
6
D
2
E
3
G
1
C
3
F
4
Activity A B C D E F G
ES 0 1 1 7 9 4 12
EF 1 7 4 9 12 8 13
LS
LF
Slack
B A
1
6
D
2
E
3
G
1
C
3
F
4
LS = LF - Activity time
Activity A B C D E F G
ES 0 1 1 7 9 4 12
EF 1 7 4 9 12 8 13
LS
LF
Slack
B
A
6 1 C 3
D E
2 3 G F 1 4
13
Activity ES EF A 1 B0 D E B A 61 2 7 3 C 1 1 4 C F D 7 9 3 4 E 9 12 F 4 8 G 12 13
G 1
LS 0 1 4 7 9 7 12
LF 1 7 7 9 12 12 13
Slack
COMPUTE SLACK
Activity A B C D E F G
ES 0 1 1 7 9 4 12
EF 1 7 4 9 12 8 13
LS 0 1 5 7 9 8 12
LF 1 7 8 9 12 12 13
Slack 0 0 4 0 0 4 0
CRITICAL PATH
B A 1 6
D 2
E 3 G
C
3
F
4
NEW NOTATION
ES EF
C7
LS LF Compute ES, EF for each activity, Left to Right Compute, LF, LS, Right to Left
EXAMPLE
C7 A 21 B5 D2
F8 G2 E5
EXAMPLE
21 28 28 36
C7
0 21
F8
36 38
A 21
21 26 26 28 28 33
G2 B5 D2 E5
F cannot start until C and D are done. G cannot start until both E and F are done.
EXAMPLE
21
21 21 21 21 21 26 26 26 26 28 28 28 31 33 36
28
28
28
28
36
36 36 36 38 38
C7
0 0
F8 G2
A 21 B5 D2 E5
E just has to be done in time for G to start at 36, so it has slack. D has to be done in time for F to go at 28, so it has no slack.
PROBLEM
Event ID Pred. None Description Prepare Site Pour fdn. & frame Buy shrubs etc. Roof Do interior work Landscape Move In Time (Wks)
A B C D E F G
A B B D C E,F
21 5 7 2 5 8 2
18
PROBLEM
21
21 21 21 21 21 26 26 26 26 28 28 28 31 33 36
28
28
28
28
36
36 36 36 38 38
C7
0 0
F8 G2
A 21 B5 D2 E5
PROBLEM
Event ID Pred. None Time (Wks)
1 2 3 4 5 6 7
1 None 3 1 2 4,5,6
8 6 4 9 11 3 1
20
PROBLEM
DISCUSSION
22
Assignment no.2 Draw a Gantt chart for the following project. A batch of mobile phones is to build within 1st January 2013 to 31st December 2013. No work will be done during following period: 15th June 10th July 7th October 9th November Note: Think of minimum 15 activities to build a car. Minimum 4 activities must be overlapping. No work will be done on weekends. Construct a Gantt chart and calculate total no. of days to finish this project with time frame. Due Date: 22nd November,2012
23
Engr.Afshan Naseem