Professional Documents
Culture Documents
Power Sector Opportunities
Power Sector Opportunities
Agenda
Evolution of the Indian Power Sector Industry Structure and Present Scenario Thermal Power Projects Hydro Power Projects Renewable Energy Projects Transmission Distribution Conclusion
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Development of the power sector has traditionally been the responsibility of the Central & State Utilities Govt. utilities (SEB) monopoly buyers Poor financial health of SEBs mainly due to Low tariff & High commercial losses (theft) Minimal Participation by Private Sector
Introduction of Independent Power Producers (IPPs) Facilitated Private Participation in Power sector Foreign ownership up to 100% was allowed Facilitated tapping of domestic and foreign capital markets, provided assured returns on investment and reduced legal hassles to allow the private investors to set-up generation capacities or operate as licensee in distribution segments, which were hitherto a monopoly of the SEBs
Post-liberalisation Developments
Revised Mega Power Policy 2009
1995
Introduced Open Access
Exemption from customs duty on imports of equipment Refund of terminal excise duty paid by various domestic supplier on supply of equipments and material based on Deemed Export Benefit In order to qualify for the mega power project status power to be sold to more than one state and thermal power projects would have to have power plant of a capacity of 1,000 MW or more located in states other than Jammu & Kashmir and NE states The power purchasing States have constituted the Regulatory commission with full powers to fix tariffs;
The power purchasing States shall undertake to carry out distribution reforms as laid down by the Ministry of Power.
The existing condition of privatization of distribution by power purchasing states has been replaced by the condition that power purchasing states shall undertake to carry out distribution reforms as laid down by the Ministry of Power. The conditions requiring inter-state sale of power for getting mega power status has been removed.
Encouraging investment by introducing competition and reforming distribution Reduction in entry barriers by:
Delicensing generation Freedom to the captive generation and group captives Recognition of trading as separate activity
Open access to consumers consuming more than 1 MW by January 2009; Multiple licenses in distribution; Setting up of regulatory commission to fix tariff and develop the sector Independent Regulatory Commissions in the States as well as in the Center Freeing up of thermal generation from the requirement of any prior approvals/ license Full freedom for setting up captive power plants including group captive plants Competitively bid generation tariffs to be accepted by Regulatory Commissions. Power purchase costs of customers availing open access to be market determined.
Objective To ensure competitive tariffs, financial turnaround and commercial viability of state utilities and providing electricity at reasonable rate Opening the sector for private sector participation by introducing competitive bidding as the basis for all future projects (except for Central & State Utilities) Enforcing adoption of multi-year tariffs by all regulatory commissions Tariff benchmarks discovered through competitive bidding has primarily replaced the cost-plus method of tariff determination with effect from January 2011 Case 1: Plant location & Fuel independent
Tariff in recent bids in Noida have been bid at Rs 4/unit Recent bids in Rajasthan, Maharashtra, Gujarat have been upwards of Rs 3/unit Adani Power bid Rs 3.25/ unit in Rajasthan; Adani Power, Indiabulls & GMR bid Rs 3.3/unit, Rs 3.27/unit and Rs 2.88/unit resp. in Maharashtra Recent long term tariffs determined via Case 2 have also been around Rs 3/unit Many states have taken up the Case 2 bidding route for meeting their power requirements Some recent Case 2 bids won are: Jaypee groups winning bids of Rs 2.97/unit and Rs 3.02/unit for Karchana and Bara project in UP, and L&Ts Rs 2.89/unit bid for Rajapura project in Punjab
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Industry Structure
State Sector Policy & Regulation Generation Inter State Transmission Intra State Transmission Central Sector Private Sector Ministry of Power / *Central Electricity Authority / Central & State Electricity Regulatory Commissions SEBs, GENCOs NTPC, NHPC, NPCIL, DVC, Neyveli Lignite PGCIL Torrent, Essar, Reliance,Tata, GMR, Jaypee, GVK, Jindal, JSW, Lanco, Adani
SEBs, TRANSCOs
Trading
PTC, Tata, NTPC, Adani, Reliance, GMR SEBs, DISCOMs Reliance, TATA, CESC, Torrent
Distribution
*CERC is the regulatory body for matter related to tariff and other issues whereas CEA is the authority related to technical matters and overall planning
Gas
Diesel Nuclear Hydro Renewable
Thermal (Coal + Gas + Diesel): 122,964 MW (67% of total) Hydro: 38,748 MW (21% of total) Nuclear: 4,780 MW (3% of total) Renewable: 20,162 MW (11% of total)
As on December 11
Per capita consumption in India is low at 733 kWh as compared to Chinas 2,180 kWh, USAs ~13,000 kwh and current world average at 2,750 kWh
Under its Power for all by 2012 initiative GoI aims to increase Indias per capita consumption to 1,000 kWh
1)SVL TPP, U-1 (63 MW) of SV Power Ltd. has been commissioned successfully (i.e. Achieving of full load) on 07-12-2011 2) Kasaipalli TPP , U-1 (135 MW) of ACB India Ltd. has been commissioned successfully (i.e.Achieving of full load) on 13-12-2011 3)Sipat St-1 STPP, U-2 (660 MW) of NTPC Ltd. has been commissioned successfully ( Full load) on 24-12-11 4) Coal based Rosa TPS, U-3 (300 MW) of Rosa Power Supply Company Ltd has been commissioned successfully ( Full load) on 28-12-2011
12
Demand-Supply
20%
15%
10% 400
200 0 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 Demand Supply %Shortage %Peaking Shortage 100 5%
The total electricity generation in the country increased from 558 Billion Units (BU) during 2003-04 to 788 BU during 2010-11 However, the Deficit is still high at:
0%
80 60
45,000 40 30,000 15,000 0 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th Target Achieved % Shortfall 20 0
Slow capacity addition owing to delay in equipment supply Heavy congestion Transmission corridors on
Targeted generation capacity addition for the 11th Five Year plan is 78,577 MW Till December 2011, approx. 45,927 MW (59.39% of planned capacity) has already been commissioned and around 63,000 MW of total capacity is expected to be commissioned by 2012 with high level surety.
Gas, 6843
2009-10
2010-11 2011-12*
14,507
21,441 13,989
9,585
12,160 11,465
66.07%
56.71% 81.96%
4%
BUs
Traded Power (BUs) Traded Power as % of Generated
25
20 15 10 5 0
3%
2% 1% 0%
Punjab, Rajasthan, Haryana, Delhi Maharashtra and Andhra Pradesh have been among the top buyers of the traded power Presently there are two power exchanges in India namely Indian Energy Exchange (IEX) and Power Exchange of India (PXIL). The total number of power trading license holders in India as on March 2010 is 45. High Volume of Power is Trading in price band Rs 4-6/unit in recent years From 2012-2017, huge peak shortage and capacity shortfall will lead to rise in merchant tariffs
US and India
Generation Capacity in US
Hydro, 8.67% Oil, 5.49% Coal , 30.06% Nuclear, 9.37% Coal Gas Nuclear Oil Gas, 41.31% Hydro Other Other, 5.10%
Oil
Hydro Other Total As on December 2010
62,504
98,742 58,021 1,138,638
Fuel Type Coal Gas Nuclear Oil (Diesel) Hydro Other Total
Coal , 56%
Gas, 10% Diesel, 1% Nuclear, 3%
As on December 2011
2026-27
2021-22
9% GDP 8% GDP
2016-17
2011-12
200
400
600
800
1000
1200
1400
States like UP, Haryana, Bihar, Gujarat, Maharashtra faced huge peak deficit and this is likely to continue in future if capacity addition is not made on time.
Future Outlook
To achieve the 11th and 12th Plan target, the required rate of capacity addition to be ~5 times the present rate.
A total of about Rs. 650,000 Crore would be required by generation segment alone during the 12th plan period. Traded power volumes have grown at the CAGR of 59% and short term power are being traded in Rs. 4-6 /kWh Imported coal requirement will rise in future Gas based plants will increase in number subject to timely availability of domestic natural gas from various fields under development.
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Domestic
Linkage Coal Thermal Gas Domestic
R-LNG
Oil
Reserves in Mn tons Balance : Total reserves minus that given out as captive allocation and expected requirement for linkages upto 2012
Large Coal Reserves are available in Orissa, Jharkhand & Chhattisgarh. Majority of the proven reserves has is of the Low Grade Non-Coking Coal suitable for power generation.
Coal Production
22 11% 25 7% 398.7 28 35 10% 6% 422.6 459.6 8% 487.8
15%
44 10%
400
12 200
347.1
375.5
5%
0 FY05 FY06 Production (Mn MT) FY07 FY08 Imports (Mn MT) FY09 FY10 % Change
0%
India is the 3rd largest producer of coal in the world after China and USA Coal caters to 53% of the total countrys energy needs Domestic coal pricing is regulated by Ministry of Coal Coal India Ltd. produces around 80% of the total coal in the country.
power sector is the major consumer of coal, consuming approximately 73% of the coal produced. In 2009-10, approximately 88% of the coal consumed was from domestic production and around 12 % was imported.
Going forward, natural gas supply in the country is expected to increase due to production from RILs KG D6 field, KG basin satellite fields, NEC field; GSPCs KG Block, ONGCs KG block and Mahanadi field and upcoming and expansion of LNG facilities
Financing Options
Rupee term Loan Most widely used source of financing SBI is at the forefront of RTL financing
NBFC IDFC, PFC, IL&FS, REC has been actively participating in funding of Power Projects ECA EXIM Banks financing the export of equipment KEXIM funding for Mundra UMPP BoC recently sanctioned ECA facility for Sasan UMPPs
Conditions Precedents to Drawdown Timelines for fuel arrangement (Including transportation & handling) Adjustment of Debt Equity vis--vis increased fuel costs impact R&R issues are extremely important Can lead to considerable delays if not addressed adequately Conditions Precedent for main plant, ash pond and green belt Environment / Forest / Coastal Regulation Zone/ Pollution Control as
conditions precedent
Off-take risk
Cost overrun/ Delays Performance Evacuation
Long term power purchase agreements crucial Minimum Quantum for long term tie-up to be assessed Fixed price lump sum construction contracts with adequate LDs preferred Cost overrun undertaking by promoters Adequate Liquidated Damages / Rectification clauses in contracts Assessment of available transmission network Adequate stipulations to cover evacuation risks
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
2005 Guidelines for determination of Tariff based on competitive bidding Guidelines for development by Private developers
1985
1990
1992
1997
2002
2007
2010
Low hydro-thermal mix in India Share of Hydropower in the total installed capacity decreasing (from over 40% in 1960-61 to around 22% at present)
Total
Source: CEA
148,700
37,328
75%
Land acquisition problems (have seriously affected Thein Dam, Doyang, Ghatgar)
Geological surprises Inadequate power evacuation facilities Lack of private sector interest Tariff and regulatory issues (free power to state and cost plus approach) The barriers above pose higher risk, which is detrimental to private sector participation
Government Initiatives:
Prime Ministers 50,000 MW Hydroelectric Initiative Streamlining of clearance procedures, provisions of open access and trading as per Electricity Act 2003 guidelines for the development of hydropower project sites by private developers PFC is giving loans to private projects for up to 70% of the project cost with max repayment period of 20 years with moratorium for construction period + 6 months MOP constituted inter-institutional group of FIs with an objective to expedite financial closure of private sector generation projects and to address last-minute issues impeding project development and financing MOP has also issued guidelines for tariff based bidding
Sikkim
State Govt has formed the Sikkim Power Development Corporation Ltd (SPDCL), to facilitate JV projects between a private developer and government 12% of electricity generated to be made available free of cost to the state For JV projects Govt participation ranges from 10% to 49%
Himachal Pradesh
Projects up to 100 MW via MoU route and those above 100 MW via ICB route No clearances from CEA for projects, upto Rs 2,500 crores, selected on ICB basis Premium on peak power 100% foreign equity permitted on the automatic approval route provided it exceed Rs1,500 crores Also for projects above 100 MW installed capacity, the government has reserved the right of equity participation up to 49% on a selective basis.
Bhutan
Chukha hydropower project (336 MW) is the 1st Joint Venture between India and Bhutan. About 84% of energy generated from Chukha plant is exported to India Kurichu Hydroelectric Project (60 MW) implemented with Indian assistance Tala Hydroelectric Project (1020 MW) the biggest joint project between India and Bhutan. Entire Power is being supplied to India DPRs of Wangchu (900 MW) and Bunakha (180 MW) have also been prepared India has agreed to provide assistance for development of Mangdechhu (360/600 MW) and Punatsangchhu (870/1000 MW)
Free Power
Upfront Premium
Bid Criteria
Levellised Tariff Terminal Value
States free to use a combination of any of the above four criteria Bid for Ratle Hydro in J&K utilized all four of the above parameters to evaluate the winner on the Bid NPV basis
Investors Perspective
Cost & Reliability factors
Plant Load Factor Plant Load Factor dependent on (dependent on water water flow of river flow of river) Potential for secondary energy Peaking Tariff Rates State Policies (for merchant sales)
Technical Aspects
Regulatory Aspects
Availability of land & Govt support for acquisition Environment and other clearances
R&R issues
Financing Options
Rupee Term Loan
Most widely used source of financing
World Bank
10 hydropower schemes funded since 1980. Upper Indravati (600 MW), Indira Sarovar (500 MW), Sardar Sarovar (1,450 MW), Nathpa Jhakri (1,500 MW), Lower Periyar (180 MW), Kalinadi River (270 MW), Gerusoppa (240 MW), Srinagar (330 MW), Koyna IV (1,000 MW) IFC has funded 2 hydro projects in India - Allain Duhangan Hydro Project (carbon finance) and CF IHDC (small hydro)
Financing Options
NBFC
PFC is funding private projects for up to 70% of the project cost with 20 yrs max repayment period with moratorium for construction period + 6 months
Teesta III (1200 MW) and Teesta IV (360 MW) promoted by Teesta Urja and Lanco respectively.
ECA/Bilateral
OECF/JBIC have approved 28 soft loans for hydropower projects since 1978 incl. Srisailam Left Bank (900 MW), Dhauliganga (280 MW), Purulia (900 MW), Nagarjunasagar (960 MW), Teesta Canal (67.5 MW), Tuirial (60 MW), Ghatghar (250 MW) DFID (former ODA) and SIDA funded the Uri I HEP (480 MW)
CIDA has granted loans for Idukki (780 MW), Lower Periyar (182 MW), and Kuttiyadi (75 MW)
KFW has approved export credits for Nathpa Jhakri (1,500 MW) and Tehri (1,000 MW) Hermes covered contracts for Baspa II HEP (300 MW)
Assessing project viability at 90% dependability (primary energy) Assessing seasonal flow variation and peaking capability
Structuring repayments to match generation profile Adequate cost over run undertaking from promoters
Secondary Energy and overrating as upsides CDM benefits for plants above 25 MW highly unlikely
Structuring mechanisms for sharing potential upsides (secondary energy and CDM benefits)
R&R issues are extremely important Can lead to considerable delays if not addressed adequately Long term power purchase agreements crucial Projects with dam/pondage can act as peaking stations Fixed price lump sum construction contracts with adequate LDs preferred Cost overrun undertaking by promoters
Approvals/ Clearances
Seasonal Variation Geological Uncertainties
Repayments structured as per the projected variation and water flows Financing done at P90 / P75 dependability
Sound DPR and extensive site surveys required to be carried out
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Wind Power Small Hydro Power Cogeneration - Bagasse Biomass Waste to Energy Solar Power 0 20000 40000 60000 80000 100000
Installed Capacity
Source: Ministry of Power, Jan 2010
Potential Capacity
Benefits
Zero cost of fuel and low O&M Cost Short gestation period Clean energy with no adverse environmental effects
Opportunities
Indias wind power potential~48.5 GW Planned Capacity addition 11th Plan ~ 10,500 MW 12th + 13th Plan ~ 22,500 MW India has 7,000 km long coast-line with immense off-shore wind energy potential Global majors like Areva, Siemens and GE are queuing up to explore off-shore opportunities
Policy Incentives
Central Govt.
as advance to
IREDA to ensure timely release of funds to the projects
Accelerated Depreciation
Accelerated depreciation (80 %) on Written Down Value (WDV) basis for wind mills
Tax Holiday
Tax holiday available to an undertaking which begins to generate power before March 31, 2012
Financing Options
Rupee term Loan Most widely used source of financing SBI is at the forefront of RTL financing First non recourse debt financing for a wind project done through RTL External Commercial Borrowing Funding via ECB route permitted ECB funding in power sector in India has reached USD 1.5 bn in the half year ended Sep 2010 NBFC Active in the Wind Sector IDFC, IL&FS, REC, IFC etc have participated in Debt and Equity funding of Wind Energy Projects ECA EXIM Banks financing the export of equipment DEG granted a long-term loan of 15.3 million euros to Bhoruka Power Corporation Ltd. (2010) in Karnataka
Financing Options
IREDA To give financial support to specific projects and schemes for generating electricity and / or energy through new and renewable sources and conserving energy through energy efficiency. Nodal Agency: Implementation of Generation Based Incentive and Accelerated Depreciation scheme ADB Rs 352 Crores to Tata Power Company Ltd. for projects in Maharashtra (2007) 100 MW (Facilities at Ahmednagar & Dhulia) Rs 445 Crores to Gujarat Paguthan Energy Corporation (GPEC) for projects in Gujarat and Karnataka totaling 183 MW (2008)
Lenders comfort level of debt to be provided for the project Reduction in Project Cost & favorable O&M terms
Availing GBI for shorter period than the normal period which is for 410 years.
1 MWh energy generated from a Wind Energy Project is eligible for 0.93 CER
DisCom Renewable purchase obligations High peak deficit in most states Prevailing peak power prices more than wind energy prices Introduction of Renewable Energy Certificates.
Comprehensive provision for liquidated damages payable by the EPC contractor may be stipulated. Promoters undertaking to bear any cost overrun in the Project. Stringent clauses for defect liability backed by guarantees
Sites receiving higher levels of insolation: Rajasthan, TN, AP, Ladakh, Gujarat
power?
Obsolescence Risk: Will new low-cost technologies threaten
enforceable?
Technology
Most Prevalent Technologies: Photo-Voltaic (PV) & Concentrated Solar Power (CSP or Solar Thermal)
Photo-Voltaic SOLAR THERMAL
Crystalline
Thin Film
Poly crystalline
Mono crystalline
Amorphous silicon
CIS
Cadmium telluride
PV- Exposure to light generates electricity variants are Wafer Based & Thin Film Wafer Efficiency 13% to 20%; Thin film Efficiency 6% to 12% More than 21,000 MW of installed PV capacity worldwide
Major Suppliers- QCells, FirstSolar, Sharp, Suntech, JA Solar, Kyocera, Yingli, Sanyo
Solar Thermal
Captures the heat from solar radiation and uses BTG Efficiencies of about 15%. Storage of power using molten salts Higher O&M Physical moving parts Water requirement in dry areas
Major technologies
Parabolic trough/Tower Over 700 MW installed capacity world over Major suppliers E-Solar, Abengoa , Acciona, Iberdrola
57
will mature
for 24-hours solar Hybrid (integrated with gas, coal, wind, biomass, etc.)
PV
Higher-efficiency C-Si Thin-films stabilised, and emergence of CIGS as leader Concentrators in deployment Longer term, nano-dots, full-spectrum PV
Chinese supply-chain
Phase III 20mn sqm solar collectors, 2000 MW off grid capacity & 20000 MW grid power
MECHANISM
Solar power developers
PV: Rs17.91unit x kWh CSP: Rs15.31/unit 4x kWh Rs2.5/unit Cost of bundled power to NVVN PV: (17.91x + 10x)/5x = Rs5.58/unit CSP: (15.31x + 10x)/5x = Rs5.06/unit Cost of Power to State Utilities for 50:50 ratio of PV and CSP = Rs 5.32/unit
NVVN
5x kWh
State Utility
Minimum project capacity for availing benefits has been fixed at 5 MW for both Solar PV and Solar Thermal In the 1st round the State had received EoIs for 365MW PV and 351MW CSP projects from 34 national and international developers. GUVNL signed PPAs for 420MW projects (395MW PV and 25MW CSP) in May 2010 For the solar thermal projects to be commissioned before Dec 2011, the tariff has been fixed at Rs 11 per unit for the first 12 years and Rs 4 per unit for the rest of the period, for the projects commissioned thereafter up to Mar 31, 2014, it is proposed at Rs 9 per unit for first 12 years and Rs 3 per unit for the rest of the period For the solar PV projects commissioned before Dec 2011, the tariff has been fixed at Rs 15 per unit for the first 12 years and Rs 5 per unit for the rest of the period, for the projects commissioned thereafter up to Mar 31, 2014, it is proposed at Rs 12 per unit for first 12 years and Rs 3 per unit for the rest of the period
Indian Banks, NBFC (REC, PFC, IREDA) Have shown keen interest Payment security mechanism still being discussed to give government support
Comprehensive provisions for liquidated damages may be stipulated as part of EPC contract Promoters undertaking to bear additional costs stipulated.
Stringent clauses for defect liability. Temperature coefficient stipulated Performance Ratio Guarantee to be provided by EPC contractor Combination of various source of data including MNRE, NASA, Meteonorm at conservative levels to be used. Repayments structured as per the projected variation
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
The complex transmission system comprises 236,500 ct. km lines and 305,600 MVA and 14,000 MW of substation capacity at 220 kV & above voltages as of March 2010.
148,667
136,866
142,503
50,000
-
59,314
2005-06
66,579 2006-07
2007-08
2008-09
2009-10*
Intra-state
Interstate
Transmission network and transformation capacity grew at 6.4% and 7.5% respectively during the first 3 years of XI plan. [X Plan growth figures were 6% and 8%]
Interregional transfer capacity increased to 20,750 MW from 14,100 MW at end of X Plan. The XI Plan investment is proposed at Rs 1,400 billion - Rs 550 billion by Powergrid, Rs 650 billion by STUs and Rs 200 billion by private sector.
216
100 39 2005-06
45
2006-07
53
60
65
During the first three years of the Plan, Powergrid invested Rs 252 billion (planned another Rs 130 billion in 2010-11). STUs invested Rs 185.84 billion during the first two years.
Total
Source: CEA
91875
56129
61.1 119000-126000
XI Plan investments may not fully fructify given the lower than planned generation capacity addition expected Planned XII Plan investment is Rs 2,400 billion including Rs 1,400 billion in the central sector (interstate system) and Rs 1,000 billion in the state sector (intra-state system) Achieve synchronization of SR grid with NEW grid [to be achieved with the implementation of Synchronous Interconnection between SR and WR] Interregional transfer capacity to increase to 32,700 MW by 2011-12 (latest CEA estimates) further to 57,000 MW by 2015 and 75,000 MW by 2017
State
SEB/Transco
Integrated or Unbundled
Joint Ventures
With PGCIL or STUs
Private Players
Projects Identified by Empowered committee /STU
Standalone private investment in transmission segment opened up in 1998 One PPP project Tala transmission system in operation since May 2007 First ITP (awarded in Oct 2007) under implementation by RPTL to come up by July 2011 Private developers considering integrated approach to generation & transmission Handful of transmission projects being developed by private sector independently or in JV with CTU / STU.
REC
REC REC
400
400 765
PFC
PFC
765
765
Parbati Koldam Trans. Corpn. Ltd Torrent Power Grid Ltd Jaypee Power Grid Ltd Teestavalley Power Transmission Ltd
Reliance (ADA) Group Torrent Power Jaypee Group Teesta Urja Ltd (Athena)
ONGC + IL&FS
Tata Power
Tripura
Tala HEP
727
1020
Tripura
Bhutan
A transmission line right-of-way (RoW) and Crop Compensation is the single largest issue faced by project executors. Other requirements like clearances, financial closures etc. are secondary. New private sector entrants face several problems. Delays in the commissioning of generation capacities resulting in risk of revenue loss if the transmission line is completed as planned, it would lead to the line being idle due to a delay in the commencement of power generation. Although Environmental clearance not required, forest clearance is required, if the transmission line passes through any forest. Approval from Forest Officer required even for carrying out a route survey
Forest Clearances
Financing Options
Key factors for financing Longer tenor requirement (especially for Projects won with competitive bidding) Revenue stream - annuity type Interest expense is the most significant cost during operations Structured repayments with bullet is favoured
Suitable on account of longer tenors Interest cost is not competitive vis--vis other sources Tenor may be a constraint May attempt with refinancing undertaking from promoter Dependent on selection of EPC / Supplier Higher upfront costs and time consuming ADB / IFC funding available to transmission projects Pre-sanction ESDD may be a constraint
Multilateral
Opportunities
Transmission
Rs.140,000 crore (USD 28 billion) required for proposed 220 kV and above transmission schemes in XI Plan Transmission planning moved away from the earlier generation evacuation system planning to integrated system planning Power Grid and State Utilities Driving the Growth in Transmission Many Transmission Project planned to be awarded to Private Sector through Competitive Bidding
6 Projects already awarded through Competitive bid Initiative driven by PFC / REC
22 large transmission projects have been identified for competitive bidding (outlay in excess of Rs 30,000 Cr)
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Distribution
Salient Features
Distribution System could not keep pace with Generation and Transmission Systems Of the aggregate losses of the State Power Utilities, 93% were at the Discom Level Costs of generation and transmission companies are pushed to DISCOM level which are unable to recover the same from the consumers Aggregate Book loss of Discoms have doubled in FY 10 to Rs 274 billion since FY 07 Unfavourable mix of consumer mix and pricing High AT&C losses Low realization of subsidy Due to weak financial profile fresh loans have been curtailed by banks and financial institutions
Distribution Performance
Aggregate Technical & Commercial (AT&C) Losses (%) in Major States 2007-08 Maharashtra Uttar Pradesh Andhra Pradesh Gujarat Punjab Rajasthan Karnataka Madhya Pradesh 31.37 43.09 16.19 22.81 19.10 33.02 32.13 45.85 2008-09 31.64 40.12 12.99 22.04 18.51 29.83 24.94 46.61 2009-10 28.23 39.65 16.43 22.81 17.73 30.07 25.34 41.03
Aggregate Technical & Commercial (AT&C) Losses (%) - Regionwise 2007-08 Eastern North Eastern Northern Southern Western Grand Total 37.19 36.67 32.59 20.10 31.95 29.24 2008-09 36.62 40.70 31.12 16.92 31.64 27.74 2009-10 33.92 36.44 30.83 19.49 28.23 27.15
Distribution Performance
Distribution being the last link in the value chain of the power industry needs to be healthy Sound health of Discom is essential for healthy and efficient functioning of the Power Sector
Way Forward
With the approval of the Prime Minister the Planning Commission in July 2010 appointed a High Level Panel (Shunglu Committee) to look into the financial problems of SEBs. This Committee recommended a plan of action to achieve financial viability in distribution of power by 2017:
Review of accounts and financial projections of SEBs and Discoms; tracking of capital work-in-progress Review Electricity Tariff and role of State Governments, State Regulators and SEBs/ Discoms in periodic revision of tariff Evaluation of functioning of SERCs Assess system improvement measures Energy to agricultural sector to be supplied through a separate feeder Series of anti-theft measures for urban and rural areas
Evolution of the Indian Power Sector Industry Structure and Present Scenario Generation - Thermal Power Projects Generation - Hydro Power Projects Generation Renewable Energy Projects Transmission Distribution Conclusion
Conclusion
Way Forward
Diversifying the fuel mix and the source of supply Political stumbling blocks and change in social behaviour poses a challenge Long term tie up for power purchase Timely fixation of tariffs and timely truing up Lowering of transmission and distribution losses Timely receipt of subsidy
Substantial opportunities emerging in power sector post the reforms being undertaken by government. Sector exposure by Banks brings new opportunities for capital raising for power sector. Foreign financial institutions are keenly observing the reforms being undertaken and would participate. At last but not the least, for economic growth in the country, power sector growth should be robust and consistent.
Thank You
Abbreviations
AT&C BOOT CDM CEA CERC ckm CTU CWET DISCOM DPR DVC ECA EOI GBI GENCO GOI GSPC KG kWh MnMT MNRE Aggregate Technical & Commercial Build Own Operate Transfer Clean Development Mechanism Central Electricity Authority Central Electricity Regulation Commission circuit kilometres Central Transmission Unit Centre for Wind Energy Technology Distribition Company Detailed Project Report Damodar Valley Corporation Export Credit Agencies Expression of Interest Generation Based Incentive Generation Company Government of India Gujarat State Petroleum Corporation Krishna-Godavari kilo Watt-hour Million Metric Tonnes Ministry of New & Renewable Energy MoEF MoP MW NBFC NE NEC NHPC NPCIL NPV PFC PGCIL R&R REC RIL SEB SERC STU TRANSCO UMPP Ministry of Environment and Forests Ministry of Power Mega Watt Non Banking Financial Companies North east North Eastern Coalfields
Formerly known as National Hydroelectric Power Corporation
Nuclear Power Corporation of India Limited Net Present Value Power Finance Corporation Power Grid Corporation of India Limited Resettlement and rehabilitation Rural Electrification Corporation Limited Reliance Industries Limited State Electricity Board State Electricity Regulatory Commission State Transmission Unit Transmission Company Ultra Mega Power Plant