Capacity
The throughput, or the number of units a facility can hold, receive, store, or produce in a period of time Determines fixed costs
*
Add personnel Build or use inventory Schedule jobs Schedule personnel Allocate machinery Use capacity
Effective capacity is the capacity a firm expects to achieve given current operating constraints
Often lower than design capacity
S7 4
S7 5
Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts
S7 6
Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts
S7 7
Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6%
S7 8
Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency)
S7 9
Managing Demand
Demand exceeds capacity
Curtail demand by raising prices, scheduling longer lead time
Product changes
Economies of scale
Diseconomies of scale
25
50 Number of Rooms
75
Figure S7.2
S7 11
Capacity Considerations
Forecast demand accurately
Understanding the technology and capacity increments Find the optimal operating level (volume)
S7 12
Figure S7.4
2006 Prentice Hall, Inc. S7 13
Break-Even Analysis
Technique for evaluating process and equipment alternatives Objective is to find the point in dollars and units at which cost equals revenue Requires estimation of fixed costs, variable costs, and revenue
S7 14
Break-Even Analysis
Fixed costs are costs that continue even if no units are produced
Depreciation, taxes, debt, mortgage payments
Variable costs are costs that vary with the volume of units produced
Labor, materials, portion of utilities
Contribution is the difference between selling price and variable cost
2006 Prentice Hall, Inc. S7 15
Break-Even Analysis
Assumptions Costs and revenue are linear functions
Generally not the case in the real world
Break-Even Analysis
900 800 700 Cost in dollars 600 Total revenue line
500
400 300 200 100
|
Variable cost
Fixed cost
Figure S7.5
2006 Prentice Hall, Inc.
| | | | | | | | | | | 0 100 200 300 400 500 600 700 800 900 1000 1100
Break-Even Analysis
BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx
TR = TC or Px = F + Vx
2006 Prentice Hall, Inc.
F BEPx = P-V
S7 18
Break-Even Analysis
BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx
Break-Even Example
Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit
S7 20
Break-Even Example
Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit
S7 21
Break-Even Example
Multiproduct Case
BEP$ = F
Vi 1x (Wi) Pi
where
V P F W i
= variable cost per unit = price per unit = fixed costs = percent each product is of total dollar sales = each product
S7 22
Multiproduct Example
Fixed costs = $3,500 per month
S7 23
Multiproduct Example
Fixed costs = $3,500 per month
Item (i) Sandwich Soft drink Baked potato Tea Salad bar
Annual Weighted Selling Variable Forecasted % of Contribution Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) $2.95 .80 1.55 .75 2.85 $1.25 .30 .47 .25 1.00 .42 .38 .30 .33 .35 .58 .62 .70 .67 .65 $20,650 5,600 7,750 3,750 8,550 $46,300 .446 .121 .167 .081 .185 1.000 .259 .075 .117 .054 .120 .625
S7 24
Fixed costs = $3,500 per month $3,500 x Forecasted Annual 12 = $67,200 = .625 Units Item Price Cost Sales Sandwich $2.95 $1.25 7,000 $67,200 Daily Soft drink .80 .30 7,000 = sales 312 days = $215.38 Baked potato 1.55 .47 Annual 5,000 Weighted % of Tea Selling Variable .75 .25Forecasted 5,000 Contribution Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) Salad bar 2.85 1.00 x $215.38 3,000 .446 = 33 Sandwich $2.95 $1.25 .42 .58 $20,650 .44632.6 .259 $2.95 sandwiches
Soft drink Baked potato Tea Salad bar .80 1.55 .75 2.85 .30 .47 .38 .30 .33 .35 .62 .70 .67 .65 5,600 7,750 .121 .075 per day .167 .117 .054 .120 .625
S7 25
.25 1.00
Strategy-Driven Investment
Operations may be responsible for return-on-investment (ROI) Analyzing capacity alternatives should include capital investment, variable cost, cash flows, and net present value
S7 26
where
F P i N
S7 27
Year 1 2 3 4 5
S7 29
S7 30
Volume Low Volume Repetitive Process High Volume Mass Customization (difficult to achieve, but huge rewards) Dell Computer Co.
High Variety one or few units per run, high variety (allows customization) Changes in Modules modest runs, standardized modules Changes in Attributes (such as grade, quality, size, thickness, etc.) long runs only
2006 Prentice Hall, Inc.
Process Focus projects, job shops (machine, print, carpentry) Standard Register
Repetitive (autos, motorcycles) Harley Davidson Product Focus (commercial baked goods, steel, glass) Nucor Steel
S7 31
Growth
Decline
Time
Time
Cyclical
Volume Volume
Stable
0
2006 Prentice Hall, Inc.
Time
Time
S7 32
S7 33
Measuring Capacity
By units of output ( barrels of beer , # of cars)
Levels of Capacity
Must be measured at these three levels
Machine or individual worker
Work center
Plant
S7 36
#1 #2 #3
2006 Prentice Hall, Inc.
Calculation
Calculated or rated capacity is based on available time, utilization and efficiency.
S7 38
Capacity Req.
Load determination
1. Determine time needed for each order at each center. 2. Sum the CR for individual orders to obtain a load. Time needed for order
Sum of Setup and Run times
2006 Prentice Hall, Inc.
Example 150 gear shafts with a setup of 1.5 hours and run time of 0.2 hours Standard time = 1.5 + ( 150 x 0.2)
S7 39