Professional Documents
Culture Documents
D1, L8 Critical Path Gantt Diagrams
D1, L8 Critical Path Gantt Diagrams
D1, L8 Critical Path Gantt Diagrams
The table below shows the tasks involved in a project, with their durations and immediate predecessors.
Task A B C D E F G Duration 3 4 6 5 1 6 7 Immediate predecessors A B B C, D, E
10
12
14
16
Hours
The critical activities, A, D and G are placed at the top of the chart.
10
12
14
16
Hours
The earliest that activity B can start is at time 0, and the latest that it can finish is at time 7.
10
12
14
16
Hours
The earliest that activity C can start is at time 0, and the latest that it can finish is at time 8.
10
12
14
16
Hours
The earliest that activity E can start is at time 4, and the latest that it can finish is at time 8.
The earliest that activity F can start is at time 4, and the latest that it can finish is at time 15.
Problem 1
A and B both require the use of the same piece of equipment. Can the project still be completed in 15 hours?
At present, A and B are both scheduled at the same time. Since A is a critical activity, moving A would result in the project being delayed.
Problem 2
A and C must both be done by a qualified person. There is only one qualified person available. Can the project still be completed in 15 hours?
At present, A and C are scheduled at the same time. Again, as A is a critical activity, it is better to move C.
Neither E nor F depend on C, but G does depend on C. C can be moved by two hours
At present, A and C are scheduled at the same time. Again, as A is a critical activity, it is better to move C.
Neither E nor F depend on C, but G does depend on C. C can be moved by two hours but if it moves a further hour to avoid overlap with A, then G must also move.
Duration
2 3
Immediate predecessors
-
Number of workers
2 1
C
D E F
5
6 8 2
A, B C C
2
2 2 2
D, E
How many workers are needed if all activities are scheduled to start as early as possible?
2
2 A(2)
13
13
1
0 0
B(3) 3 C(5)
3
7
D(6)
G(4)
6
17 17
E(8) F(2)
4
5 5
C (2)
E (2)
G (2)
10
12
14
16
Days
Put the critical activities along the top. (The numbers in brackets show the number of workers required)
C (2) A (2)
E (2)
G (2)
10
12
14
16
Days
The earliest start time for activity A is at time 0, and the latest finish time is at time 7.
E (2)
G (2)
10
12
14
16
Days
The earliest start time for activity B is at time 0, and the latest finish time is at time 7.
E (2)
G (2)
10
12
14
16
Days
The earliest start time for activity D is at time 3, and the latest finish time is at time 13.
E (2)
G (2)
10
12
14
16
Days
The earliest start time for activity F is at time 5, and the latest finish time is at time 17. If this schedule is used, 6 workers are needed. (6 are needed on days 6 and 7).
Problem
Only four workers are available.
E (2)
G (2)
10
12
14
16
Days
We need to move some tasks so that only four workers are needed at any given time. At present 5 workers are needed for the first two days. Task B can be moved so that it starts after A has finished. This means that D must also move.
E (2)
G (2)
D (2) F (2)
10
12
14
16
Days
We need to move some tasks so that only four workers are needed at any given time. At present 6 workers are needed for days 6 and 7. Task F can be moved so that it starts after D has finished.
E (2)
G (2)
D (2) F (2)
10
12
14
16
Days
Now only four workers are needed at any given time. Workers 1 and 2 could do activities C, E and G. Worker 3 could do A, B, D and F Worker 4 could do A, D and F (with 3 days off between A and D).