Monthly Performance Review For The Month of April 2012
Monthly Performance Review For The Month of April 2012
108
S.# 1-
Action to be taken
Verified By
To reduce rejection rate of fiber from 1.5% to 1% with in next 6 month. Ensure 100% compliance of Gantt chart and complete production by 25th of each month. Ensure all workers are wearing shoes and cap on daily basis.
During lunch time A/C package unit & lights should be turned off.
To train worker by operation training monthly basis and monitoring weekly basis by preventive maintenance Daily Monitoring and check and balance as per Gantt chart for completion production plan Keep house keeping and monitoring daily basis
100 %
2-
100%
3-
100%
4-
100%
109
2) Status of Open & Follow-up Corrective Preventive Action Request S # 1 CPAR # Brief Description of Problem Nil Open Followup Closing Date Verified by MR
S#
Wild Fiber
OK
4) Status of Pending Demands and Work Orders: Detail Description Current Status of Work
S#
PD #/ WO #
DM/WO Date
Remarks
110
5) Monthly Variance Report (Planned V/s Actual Production): S# 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Product Perfect Angular Bio Junior Smoker New Classic Flex Adult AntiPlaque Falcon Righto Antibac Gumpro Proclean Flex Junior Sensation Clarity Little Star Planned Qty In CTNS 103680 86400 -----51840 164160 75600 205920 83520 97920 17280 25920 51840 20160 54720 64800 ------Achieved Qty In CTNS 118050 111100 -----67700 204600 99800 185300 81800 87300 17600 25900 ------20160 11000 93100 -------% of Achievement 113% 128% -----130% 124% 132% 89.9% 97.9% 89.1% 101% 99.9% 0% 100% 20.1% 143% -------Reason for Not Achieving Target ------------------------------------------------------------------Handle not available ------Handle not available -------------
111
6) Production Rejection Report: S# 1 2 Product Fiber Aluminum Wire Issuance Qty (kg / pcs) 690 --Rejected Qty (kg/ pcs) 3.50 --% Rejection 0.50 % --Threshold Value 1% 1.25% Reason for Rejection -------------
3
4
Nikle wire
Total Brush rejection
399
1123410
1.9
8570
0.72 %
0.7 %
1.25%
.67%
-------------
7) Status of Machine Down Time (KESC Failure, Preventive Maintain, and Break Down):
S#
Machine/ Equipment #
Problem Details
NIL
112
8) Status of Scheduled Preventive Maintenance: S# Machine# Maintenance Details Planned Date Actual Date Reason for achieving deadline Current Status (ok /Not ok)
1 2 3 4
TB 1 TB 2 TB 3 TB 4
113
27 02 -
837 62 -
142 17 -
695 45 -
5560 360 -
83 % 72 %
2493 122
-----
100 % -----
00 % ----
----
Supervisor M-grade
04
124
40
84
672
Production Officer
114
10) Details of Accident / Incident: S# Date of incident FIR/AIR # Problem Description Corrective Action Taken Status/Remarks
Verified by Administration: Sign _______________________ 11) Major Achievement of Section / Department during the month : Improvement in Process Flow Details Improvement Required (If Any)
Effective Man power utilization in the Department Ant improvement done to make work flow efficient:
115
S#
Problem Description
Countermeasure
116
Shahid Ali
Shahid Ali
Checked By HOD:
Checked By Production Manager : Reviewed by: Director Operations:
Date: 04-05-2012
Date: Date:
117