Professional Documents
Culture Documents
IT Data Center Guideline
IT Data Center Guideline
IT Data Center Guideline
Guideline
Power Cooling AFFS Labeling Cabling Drawing & Document Asset Tracking House Keeping ITDC site preparation Cabinet Installation Checklist
Substation, Generator, BBT, MDB, COS, Modular distribution, light & Socket DC power Rectifier/Inverter, UPS, Battery Grounding & Surge protection AC power Server room, Substation & Generator room Equipment & Cable Labeling standard Signal & Optical cable management system Power & Grounding cable management system
Reference:
TIA: Telecommunications Industry Association
Guidelines Considers New Data Center Existing Data center Improving Cooling Efficiency Solution for High dense Server
Products:
Emerson Network Power American Power Conversion (Schneider Electric) SUN Microsystems (Oracle Corporation)
Environment
5 to 35 C
21 to 23 C Recommendation 22 C
5 to 35 C
Preferable 20 C
5 to 35 C
< 27 C , Preferable 25 C
Relative Humidity
20% to 80%
40% - 60%
Cooling Unit
if necessary then dehumidification feature only. Note: also applicable for old air con replacement
During the planning phase of equipments layout, we have to consider : Row Oriented Cooling (Hot-aisle/Cold-aisle Protocol) Placement of cabinet according to air inlet/outlet Spread-out the high-density racks
Gap
Min 2 ft
Min 3 ft
3 ft
4 ft
14 ft
For smooth O & M, it is necessary to extend the maintenance window . So current practice is followed here.
Fig: Spread Concentrate out the high-density high-density racks racks Fig: high-dense row Fig: Concentrate Spread out the high-dense row
AC
AC
AC
Floor vents placed too close to AC units produce negative pressure due to under floor high air velocity, causing air from the room to be drawn back under the floor
Recommendation: Unused vertical space in rack enclosures causes the hot exhaust from equipment to take a shortcut unused vertical back to the space equipments in rack intake. must be enclosed through filler. Also avoid the unorganized cable management Organized of cable the cabinet of thewhich cabinet may hamper as per the cooled guideline and air product flow. manual
Fig: Organized cable will not hampered air flow Fig: Usages of filler
To measure the ambient temperature and humidity of the data center, may follow these guidelines:
Place sensors in cold aisles, where cold air outlets provide conditioned air to the systems.
Hot-aisle measurements will be typically out the systems recommended operating ranges and therefore are not a valid indication of the required temperature and humidity levels. Place sensors 10 to 15 feet (3 to 4.5 m) apart from AC or in front of every fourth rack in the aisle. Place sensors in the middle of the aisle, between the rows of racks. Place sensors 4.9 feet (1.5 m) above the tiled floor.
Hot spot is created due to: Concentration of high heat dissipating nodes in a same location Huge amount of unorganized under raise floor cables, which prevents proper aeration. Inadequate cooling system.
Cooling loads within racks can be improved by the retrofitting of fan-assisted devices that improve airflow and can increase cooling capacity per rack.
Options:
High-Density Pods in a Low-Density Data Center Autonomous Cabinet System
Autonomous Cabinet System : The ACS is a complete data center in a box, incorporating cooling, power, fire and security systems required for very high-density loads. The cooling unit is situated within the enclosure, thus ensuring the maximum effectiveness of cool air delivery to the rack-based equipment.
Redundancy is supportive in cooling systems to permit maintenance of live systems and to ensure the survival of the data center mission if an air conditioning device fails:
Recommendation:
For higher density server, which is also highly business sensitivity, the redundancy approach is sustainable.
Our recommendation at least one redundant Row-oriented provides redundancy at the row level. cooling architecture unit at row level where,
This requires an additional or N+1 AC unit for that particular high dense & cooling sensitive row ( 12 kW Business severity so high Server). High restart time due to failure of cooling High power consumption (> 12 kW) Row area @ 80% occupied
4 Ton AC
4 Ton AC
4 Ton AC
4 Ton AC
5 kW 3 kW
3 kW 4 kW
5 kW 3 kW
3 kW 4 kW
Hot
4 kW
3 kW 4 kW
Cold
3 kW
5 kW 4 kW
Hot
Hot
4 kW
3 kW 4 kW
Cold
12 kW
5 kW 4 kW
Hot
4 Ton AC
4 Ton AC
4 Ton AC
R. AC
4 Ton AC
Fig: Example
Air conditioning unit: Measured supply and return temperatures (Preferable difference > 8 C ) Room temperatures measurement Rack temperatures and airflow measurement Aisle & floor tile arrangement Condition of subfloors