Start Up and Commissioning of Pipelines: D. S. Nanaware, Chief Project Manager, IOCL, Noida
Start Up and Commissioning of Pipelines: D. S. Nanaware, Chief Project Manager, IOCL, Noida
Presentation by D. S. Nanaware, Chief Project Manager, IOCL, Noida IiPM, Gurgaon 10th July 2009
Contents
10th July 2009
Commissioning
Handing/Taking Over Case Study
IiPM, Gurgaon 2
IiPM, Gurgaon
Objectives
Proper handing over & taking over of pipeline system Preparation of check list for all pending activities Liquidation of check list points in a time bound manner
IiPM, Gurgaon 4
Task Forces
For efficient startup/commissioning specialized task-force can be formed including specialists from:
Projects/Construction Group
Operations & Maintenance Group
IiPM, Gurgaon
Mechanical completion of pipeline system Hydro-testing and pigging of entire pipeline Inertization of pipeline
Verification and taking over of all contract, project and operation related documents before pre commissioning activities All checks for ensuring system integrity and functionality Verification of all statutory permissions Verification of relevant inspection reports and certificates etc. Verification of venders documents for material supply
IiPM, Gurgaon 7
Verification of agreements and MOUs with product suppliers and consumers Preparation of check list with target completion dates for all contracts works and material POs Enlisting of all construction surplus materials, and equipment with all relevant inspection, test certificates and other documents Ensure preparation of check list for balance jobs Verification and taking over the project DFR, concept note and project approvals etc
IiPM, Gurgaon 8
Verification of Fire network and equipments as per relevant OISD standards Check the adequacy of first aid fire fighting appliance as OISD Std. 117 Ensuring placement of fire fighting equipments/instruments as per OISD Std. 117
Check the compliance of safety audits, OISD audits and Pre-commissioning audits
Check the integrity of fire fighting system before start up and commissioning
IiPM, Gurgaon 9
Documentation
The O&M Documentation In-charge shall take over and ensure proper distribution of documents related to: A. Statutory clearances/Permissions
Factory License as per factory act 1948 State Pollution Control Board and Ministry of Environment & Forests (MoEF) clearances State & Central Electricity Authority Permissions (wherever required)
Documentation
A. Statutory clearances/Permissions (contd..)
Permissions/Agreements executed for Railways, Road (NH & SH), Canal, OFC and any other crossings
Authorization for hazardous waste rule (Management & handling - 1989) B. Revenue and RoU related documents
Detailed RoU Survey Reports with Survey Numbers Tree & Crop compensation details and documents
Documentation
C. Construction Related Documents
Documentation
C. Construction Related Documents (contd..)
Agreements with contractors, venders, material / Equipment suppliers All taxes and duties statements SAT (Site acceptance Test) of all instruments including certificates and loop testing certificates Process Flow Diagram As-build drawings such as plot plan, cable route drawing, earthing and P&ID etc.
IiPM, Gurgaon 13
IiPM, Gurgaon
14
Objective of Commissioning
Commissioning is to bring the constructed / installed system to deliver the desired function.
Pipeline commissioning means introducing crude/ product/Gas in the pipeline from originating station, filling the entire length and then start delivering to the planned receipt system. In case of crude pipeline, there may be intermediate storage stations for operational requirement but ultimate supply is to be made to a refinery In case of product pipeline/Gas pipeline, there may be several intermediate delivery stations before terminal/dispatch station.
IiPM, Gurgaon 15
Pre-commissioning
Preparation of commissioning manual
A document describing the procedure to be followed for commissioning is to be prepared by experienced persons The purpose of making the document is to set forth the objectives of commissioning of pipeline system and to establish guidelines for safe commissioning in order to achieve the required goals.
A check list is prepared, which covers the technical, safety as well as statutory requirement before the pipeline and associated facilities is declared ready for commissioning.
IiPM, Gurgaon 16
Pre-commissioning (contd..)
Constituting a pre-commissioning team: A committee of experienced engineers is constituted to audit the construction as per pre-commissioning check list and report to the management regarding readiness of the system or any shortcomings to be complied before commissioning. Procurement of consumable/tools/pigs etc: As mentioned in the Commissioning Manual, required consumables, tools, pigs, spares and safety equipments are to be made available prior to commissioning. Availability of product/ crude: As per line fill calculation, the availability of crude oil or the product, as the case may be, is to be ensured at originating / pumping station in coordination with Refinery and Marketing.
10th July 2009 IiPM, Gurgaon 17
Commissioning
Pipeline sections are generally commissioned in phased manner / in totality based on the situation and preparedness.
After hydro-testing and caliper pigging it is expected that the sections are in a fairly clean condition.
IiPM, Gurgaon
18
Constituting a commissioning team: A committee of experienced engineers is constituted to perform the objective of commissioning. Scrutiny of audited pre-commissioning check list: The committee to ensure the compliance of any shortcomings reported in the pre-commissioning check list. Identification and deployment of manpower at new stations Deployment of security personnel at stations Arrangement of water and disposal plan
IiPM, Gurgaon 19
Commissioning steps
Pressurization of pipeline section with compressed air up to 3-5 Kg/sq cm. Injection of about 500 to 1000 KL water into the section from launching barrel end Launching of cleaning (bi-di) pig after introduction of water in the line Maintaining 5-10 kg/sq.Cm back pressure at other end by venting the air
Introducing HSD / Crude in the line and maintaining 5 to 10 Kg/sq.cm back pressure at other end. Draining dirty water to storm water drain / pre-fixed drain outlet at the receiving end Receiving cleaning pig Again draining dirty water to storm water drain
Flow to be diverted to HSD / Crude receipt tank as soon as oil traces are observed. Temporary facility for water draining to be dismantled & permanent blinding put
IiPM, Gurgaon 21
Since, before pumping water, line is filled with air at a predetermined pressure, so monitoring and air draining facility is kept ready at receiving end to maintain back pressure of air at 5 to 10 Kg/sq.cm
Pumping into an empty line will cause excessive flow rate & current in the motors resulting in frequent tripping. May result in increase of interface length.
As the pig reaches at receiving end, it is taken out. The muck & dirt quantity is collected and after analysis it is disposed off. Handing over the system to operating group
10th July 2009 IiPM, Gurgaon 22
IiPM, Gurgaon
23
Handing/Taking Over
HANDING / TAKING OVER FORMAT
NAME OF PROJECT LOCATION PROJECT IDENTIFICATION : ______________________ : ______________________ : ______________________
PROJECT COST
PMC CONTRACTOR DATE OF COMMISSIONING
10th July 2009
: ______________________
: ______________________ : ______________________ : ______________________
IiPM, Gurgaon
24
Handing/Taking Over
I.
1.
_____ INCH DIA. P/L FROM _______ TO ______ (ALONGWITH OFC) HAVING DESIGNED CAPACITY OF ______ MMT/MMSCMD AT PRESSURE _________KG/CM
2.
3.
4. 5. 6.
RECEIVING TERMINAL AT
SV/IP STATIONS ALONG PIPELINE AT ANY OTHER FACILITIES (IF APPLICABLE) HDD (IF ANY) DETAIL
IiPM, Gurgaon
: ______________________
: ______________________ : ______________________
: _____________________
25
Handing/Taking Over
II. IMPORTANT PARAMETERS AND DATES
1. MECHANICAL COMPLETION DATE OF MAIN LINE WORKS: __________ 2. PIGGING (FOAM, GAUGE, CLEANING PIG & EGP) 3. HYDRO TEST & DESIGN PRESSURE OF MAIN LINE 4. MECHANICAL COMPLETION DATE OF RECEIVING & ORIGINATING TERMINALS 5. INSTRUMENTATION COMPLETION DATE OF TERMINAL STATION 6. COMMUNICATION SYSTEM COMPLETION DATE 7. SCADA AND TELEMETRY COMMISSIONING DATE : __________ : __________ : __________ : __________ : __________ : __________
: __________
: __________
26
Handing/Taking Over
III. STATUS OF SYSTEMS / FACILITIES TO BE RECORDED BEFORE TAKING OVER
(A) Pipeline & CP
1. Status of ROU, CP test points and Markers 2. Checking of mainline & bypass line valves & Actuator OK/ Not OK OK / Not OK
3. Physical Status of SV/IP, receiving & Pump stations OK / Not OK 4. Performance test of SVs/IP station 5. Checking of casing shorting at crossings. Done / Not Done Done / Not Done
6. Status of Temporary CP
7. Status of captive power system with battery bank (wherever applicable) 8. if pipeline is not charged, is it dried & filled with inert gas
10th July 2009 IiPM, Gurgaon
Yes / No
27
Handing/Taking Over
IiPM, Gurgaon
28
Handing/Taking Over
(C) INSTRUMENTATION & METERING
1. Status of metering systems (If applicable) 2. Checking of Instrumentation Panel (If Applicable) 3. Status of Chromatographs (If applicable) 4. Status of Instruments at SVs/RRs/IPs 5. Remote operation of Valves at SVs & Terminals. Yes/NO Comm/Not comm. Done / Not Done comm/Not comm. OK/NOTOK
6. Status of UPS
Handing/Taking Over
(E) FIRE & SAFETY
1. Status of Fire fighting Systems OK / Not OK 2. Status of fire detection system at SVs/RRs/lPs & Terminals Comm/Not comm. 3. Status of on line extinguishing system at SVs/RRs/lPs 4. Safety audit by Fire & Safety personal from O&M Comm./Not comm. Done/ Not Done
(F) GENERAL
1. Status Control Buildings Construction 2. Status of basic amenities for security guards at the permanent establishment (Security rest room, water, lighting arrangement) 3. Preparation of final checklist before taking over Done / Not Done Comp./Not Comp. Done / Not Done
IiPM, Gurgaon
30
Handing/Taking Over
(G) DOCUMENTATION
1. Listing & handing over of all procedures, reports, certificates, vender manuals, drawings and related documents which are to be handed over as per Contractual obligation with the venders 2. Listing & handing over of As builds, Alignment sheet, hydro test report, Pigging report, pipeline route map, pipe book, crossing details (Hard copy & soft copy) 3. Revenue records & records for permanent land acquisition Done! Not Done 4. Certificates related to Metering system Done I Not Done Done / Not Done Done / Not Done
(H) SPARES
1. Commissioning spares 2. Two years spares
10th July 2009
Thank You
IiPM, Gurgaon
33