Professional Documents
Culture Documents
Nisi
Nisi
April 2012
Project Location
Baglung District
Nishi SHP
Project Data
Accessibility
By ROAD via Butwal Kathmandu-Butwal Butwal-Ridi Bazaar Ridi-Burtibang Burtibang-Devisthan New (along alignment) By ROAD via Pokhara Kathmandu-Pokhara Pokhara-Baglung Baglung-Burtibang Burtibang-Devisthan New (along alignment)
: : : : :
: : : : :
258km (Black Topped) 71.08 km (Black Topped) 70 Km (Gravel Road) 5 Km (Earthern Track) 3 Km
199.0km (Black Topped) 72.58 km (Black Topped) 40 Km (Gravel Road) 5 Km (Earthern Track) 3 Km
Rated Capacities
Installed Capacity Design Discharge@ 40% exceedance Scheme Gross Head Net Head Design Flood @100 yrs return period Catchment area at Intake Plant Factor D/s release Annual Energy Dry Season Energy Wet Season Energy : 3500 KW
Project Data
: : : :
: : : : : : :
Project Data
Catchment Characteristics
Catchment area at Intake of Nisi SHPP is 202.14 km2 Ungauged catchment No long term flow available Model developed for hydrological study of ungauged catchment are Hydest and MIP. Long term monthly discharge at Intake are prorated from CAR method with discharge at Rudrabeni station (Station no. 417.0)
Parameter
Nisi Khola at proposed intake 202.14 km2 33 km2 169 km2 100% 16.34% 83.66%
Badigad Khola at Rudrabeni 1990.0 km2 378 km2 1612.0 km2 100% 18.99% 81.01%
Comparison of Hydrographs
Month
Hydest MIP 4.72 3.54 2.55
55 50 45 40 35 Flow, m3/s 30 25 20 15 10 5 0
1 2 3
MIP
January February March April May June July August September October November December Mean Monthly Flow
2.04
2.76 9.46 29.15 35.07 26.92 11.79 5.16
1.97
5.11 11.79 28.49 49.13 32.42 15.72 8.06
1.99
2.33 7.86 30.07 40.57 33.47 14.38 6.96
6
Hydest
10
11
12
3.36
11.04
6.09
14.13
4.27
Month
Catchment Ratio
12.53
Catchment ration based on Gauged discharge at Rudrabeni station (Stn no. 417.0
60
40
7.76
6.40 5.06 3.99 3.39 2.40 1.38 0.54
30
20
10
Flow, m3/s 0 0% 10% 20% 30% 40% 50% 60% 70% 80% Probability Exceedence , %
MIP
90% 100%
Hydest
Catchment Ratio
Hydest 169.967 273.945 351.553 431.878 544.573 635.363 732.102 868.807 979.754
Gumbel's distribution
103.12 166.22 207.99 248.06 299.93
500 450 400 350 300 250 200 150 100 0 100 200 300 400 500 600 700 800 900 1000
Gumbel's distribution Log Pearson III Log Normal
338.80
377.53 428.62 467.23
Project Layout
Main structures on Left Bank Diversion weir on 300m upstream of Devistan village Powerhouse approx 2km downstream of Devisthan village
Salient Features:
Diversion weir Underslucie Intake Gravel Trap Desander basin Penstock Pipe : : : : : : Free Overflow type 20m, 3m high, FSL 1126.0m, HFL=1129.5m. 1 bay, 4.0m X 2.5m, crest EL1123.5m Side intake double Orifice 3.5m X 1.3m 15m X 3.0m X 2.5m, 10 mm particles 2 Dufour, 75m long, 5m wide and 4.5m deep, 0.2mm particles 2.4 m dia Steel, (1768.34m +82.15m)=1850.6m, thickness 6mm-12mm 7m dia X 16.65m high, semi exposed Surface type 34 X 10 X 9m Rectangular RCC channel ,length 39.5m X width 2.2m Outdoor type 2 units, Horizontal Francis ,2.5MVA 2 units ,Brushless type Self Excited, 2.5 MVA 6.3/33kV outdoor type 8.0km, 33kV single circuit upto Badigadh A substation NEA 33kV Substation at
Surge Tank Power House Tailrace Switchyard Turbine Generator Transformer Transmission line Interconnection
: : : : : : : : :
Project Cost:
Total Cost of the Project: NRS 418.197 Million based on 2010 Market
Interest Miscellaneous Capitalization Expenses Cost (during 1.20% Preliminary Expenses construction) 1.03% 9.10% Office Equipment & Vehicle 0.47% Project Management & Supervision 2.25% Transmission Line & Switchyard 2.94% Land Procurement 1.93% Infrastructure Development Site Office & 0.36% Camping Facilities Construction 1.29% Construction Design & BOQ Preparation 0.90%
Financial Indicators:
Total Cost of the Project Specific Project Cost Unit Energy Cost : NRs.418.197 million @2010 : US$ 1,572 per kW : NRs. 3.72 per kWH
Internal Rate of Return (IRR) : 16.96 % Benefit Cost Ratio (B/C Ratio) : 1.42
NPV
Discounted payback period Construction Period
10
2.50
2.00
1.50
1.00
0.50
0.00
: :
Project Keydates:
Survey license received Negotiation with local communities Preliminary report submission : 2065/04/28 : 2065-066 : 2066/04/
: 2067/04/25
: 2067/04/25 : 2068/08/29
Major Correspondence:
2067/04/25 2067/06/26 2067/11/18 2068/04/25 2068/05/19 2068/06/12 2068/08/28 2068/11/05 : Application for Project Upgrading and Coordinate Modification : Letter received with time extension but coordinate without being modified : Reply on letter no. 675-067/068 : : : : : Time Extension Self declaration letter Progress Report Net worth Regarding presentation