Professional Documents
Culture Documents
Operation and Protection of 210 MW Turbine Condensation Extracton Pump and Condensation Cycle
Operation and Protection of 210 MW Turbine Condensation Extracton Pump and Condensation Cycle
Introduction of Condenser
After work done in turbine, Steam cannot exhausted to atmosphere because that steam pressure is below atmospheric pressure so recover that steam required a closed vessel into which steam exhausted and condensate, that close vessel pressure is below atmosphere.
Condenser cycle
Function of Condenser
To maintain low pressure (below atmosphere), so obtain maximum energy. To convert exhaust steam to water for reuse thus saving on feed water requirement. Deaeration of make-up water in the condenser.
Advantage of Condenser
Increase Plant efficiency. Reduce temperature of exhaust steam.
Type of Condenser
Condenser is basically two type
Jet Condenser Surface Condenser
Jet type condensation of steam takes place by directly mixing exhaust steam and cooling water Parallel Flow Steam & water enter from same side Counter Flow - Steam & water enter from Opposite side
Surface type condensation of exhaust steam takes place on the outer surface of the tubes which are cooled by water flowing inside
Surface Condenser Steam & water not mixed High capacity plant
Condensate reused Maintenance cast high
Starting Ejector
Starting ejector is recommended to be used for accelerating the initial pulling of vacuum Pressure and temperature of this steam are not to exceed 4.5 Kg/cm2 and 250C This ejector is switched off as and when the vacuum in the condenser reaches 500-600 mm of Hg column
Main Ejector
The suction chamber has been divided into three stage The convergent divergent nozzle has been designed to accelerate the steam flow and thereby reduce the pressure of steam to 0.03 Kg/cm . in the 1st stage of suction chamber. The low pressure in suction chamber sucks the noncondensible gases from the condenser
Make:-Kirloskar Bros. Ltd. Make:-N G E F Flow:- 281 m3/hr Capacity:-250KW(300hp) Head:- 200 m Voltage/Current:- 6.6KV Speed:-l490rpm Speed:- 1490rpm Stage 8 ( unit 5) 5 ( unit 6&7)
C E P Pre check
Ensure all relevant maintenance permits are cancelled. Ensure condenser manhole are tightly closed. Ensure condenser hotwell drain valve & dummy are in place. Hotwell gauge glass, level switches, transmitters are in service. Ensure G.S. cooling water is available for bearing cooling & DM water is available for condenser makeup. Ensure that hotwell level is filled up to of gauge glass.
C E P Pre check
Ensure 6.6 kv breaker is ready & its cold trials are OK Motor direction trials are Ok. Ensure pump thrust bearing oil level is normal. Ensure bearing cooling water & DM gland sealing water flow is established. Pump is charged after opening of suction valve. Keep following valves closed:
i) Discharge valve & its bypass. ii) Valve of FC NRV line. iii) LP bypass spray valve. iv) MC-39 MC-57 v) 15 m syphon filling valve. vi) Syphon filling valve of main ejector
C E P Pre check
Ensure air supply is available for pneumatic valves. Isolating valves of CV-6 are open Open inlet & outlet isolating valves of MC-36. close bypass. Open condensate inlet & outlet valves of main ejector, LP-1, LP-2, LP3 close bypass of GC, close LP heater-4 outlet valve. Open GC1,LP1, LP2 vents. Open pump discharge header vents.
Put selector switch of pump on local & start the pump. Open bypass valve of discharge valve for charging the line. Open discharge valve slowly monitoring pump discharge pressure & close bypass valve. Observe the motor current & discharge header pressure. Close vents of discharge header after sufficient water comes out & air is expelled from system. Measure the vibrations of pump &motor bearing. Monitor thrust bearing temp. observe the oil level for any leakages.
C E P Operation
C E P Operation
Monitor hotwell level, if required CV-7 isolating valve can be opened. Open MC36 valve partially & charge GC2, LP2,3,4 from condensate side. Close vents after sufficient water comes out. Open LP heater4 outlet valve for deaerator make up if needed. Open discharge valve of stand by C.E.P. & keep selector switch on remote.
C E P Interlocks
Hot well level very low Discharge pressure low (< 14.0 kg/cm2 ) Stand by pump pick up at the time of following condition
If running pump trip on motor portion If discharge header pressure is low (< 14.0 kg/cm2 )
C E P Koradi Unit-5
C E P Koradi Unit-6&7