Professional Documents
Culture Documents
Manufacturing Technology (ME461) Lecture29
Manufacturing Technology (ME461) Lecture29
Manufacturing Technology (ME461) Lecture29
is a policy variable which is used as a means of managing external disturbances such as changes in demand and variability in processing and delivery times. D is determined as a smoothed demand. y is normally fixed even if there are variations in demand. In that case, when D increases the value of the lead time must be reduced accordingly.
Example Problem
Johnson and Johnson, a private company, supplies parts to a spark plug manufacturing company, JJ is now planning to introduce JIT production concepts for their shell manufacturing section. The following data are avialable: The requirements are 25,000,000 units per month. Since the company has just started implementing the JIT system, the policy variable is set at =0.20. The container capacity is fixed at 500 shells and the production lead time is 0.10 days. Assume a 20 working days month. (a)Since it is the first time that JJ is implementing JIT, advise JJ in developing a kanban operating system. How many kanbans will be needed? (b) Suppose the company has stable production environment and the policy variable can be fixed at =0.10. Determine the no. of Kanbans and the resulting impact on work-in-process inventory. (c) What happens if the lead time is reduced to 0.08 days because of process improvements?
Typically in a JIT operation the master production schedule is frozen for 1 month and the no. of Kanbans in each working center is set based on average demand for the period. In this section we develop a cost model considering the expected cost of holding and shortages. It is assumed that the probability mass function (PMF) of the number of kanbans required is known. Let us assume the following notations: 1. P(x) = probability mass function for the number of kanbans required 2. Ch = holding cost per container per unit time at a work center 3. Cs = cost of a shortage per container per unit time at a work center Suppose there are n kanbans circulating in the system.
Case 1: The actual requirement for the kanbans, x, is less than n. In that case holding cost will be incurred. Accordingly, Expected holding cost = Ch (n-x) p(x)
Case 2: The actual requirement for the kanbans, x is more than n. In that case shortage costs will be incurred. Accordingly,
Expected shortage cost = Cs (x-n) p(x) Therefore, the total expected cost, TC (n) is given by: TC (n) = Ch (n-x) p(x) + Cs (x-n) p(x) The optimal value of n that gives the minimum value of TC (n) is the smallest integer satisfying the following:
Example : Suppose that the probability mass function of the number of kanbans is known and is given in the table ahead. Furthermore, suppose the holding and the shortage costs per unit time are $50 and $200, respectively. Determine the optimum number of kanbans to minimize the total expected cost.
Probability 0.00
0.20
0.30
0.35
0.10
0.05
No. of kanbans
Example Problem: Johnson and Johnson is also planning to introduce a kanban system in their assembly section. However, there is variability in the lead times. Furthermore, the assembly operation is the last operation before the shells are shipped to the spark plug company. Therefore. There is considerable value addition. The company industrial engineer has conducted a simulation study and developed the probability mass function of demand during the lead time as follows: Probability 0.00 0.15 0.20 0.30 0.20 0.15 No. of kanbans 0 1 2 3 4 5