Professional Documents
Culture Documents
Project Time Management
Project Time Management
Introduction
Construction Schedule
KEY DATE SCHEDULE
- For project control purposes a hierarchy of schedule may be needed, depending on who will use it. - For owners, A/E, and top-level field manager in terms of MILESTONE or KEY DATES.
KEY-DATE SCHEDULE Project No. 1 2 3 4 5 Highway Bridge scheduled operation required Project No. 7908-05 actual
start
Move in Excavation footing No.1 footing No.2 Abutment No.1 June 25 July 30 July 6 July 9 July 20
finish
June 29 July 7 July 14 July 20 July 30
start
June 14 July 19 July 9 July 22 July 20
finish
June 16 August 3 July 19 July 30 July 30
start
finish
6
7 8 9
Abutment No.2
Backfill Deck Cleanup
August 2
August 2 August 17 September 8
August 12
August 17 August30 September 10
August 2
August 10 August 17 September 8
August 12
August 20 August 30 September 10
Construction Schedule
DETAILED SCHEDULE
- For immediate work supervisors and subs. - A projected time program of that particular supervisor work responsibility. - Covers limited time spans. (2 weeks or 30 days) - Total float data can be misleading to field supervisors who are involved with only restricted portions of the project. GIVE THEM FREE FLOAT ONLY.
Activity Activity Number Scheduled Duration (w orking Days) Scheduled Start Date Scheduled Completion Date Free Float (w orking Days) Actual Start Date Actual Comletion Date
Move in Make abut. Forms Excavation abut no.1 Excavation abut no.2 Drive piles abut no.1 Forms & steel, foot no.1 Drive piles abut no.2 Pour foot no.1 strip foot no.1 Forms & steel, foot no.2 Pour foot no.2 *Forms & steel, abut no.1 Strip foot no.2 *Critical Activity
3 3 3 2 3 2 3 1 1 2 1 4 1
June 25 June 30 June 30 July 6 July 6 July 9 July 9 July 13 July 14 July 15 July 19 July 20 July 20
June 29 July 2 July 2 July 7 July 8 July 12 July 13 July 13 July 14 July 16 July 19 July 23 July 20
0 10 0 1 0 0 1 0 0 0 0 0 8
Time management system is no better than the quality of the input information.
GARBAGE IN GARBAGE OUT
Requires direct visual observations in the field by someone familiar with the type of work involved.
P.M. GOOD Field supervisor BAD
DR. SAMIA ALI
PROGRESS MEASUREMENT
HOW OFTEN ?
1- Balance :
Desirable
Feasible
Cost effort
BAR CHARTS
- A widely used method for recording job progress for the day to day time management - An excellent medium for recording progress information and current time status for individual Activities. - Not a proper tool for evaluating the overall time status of the project or for planning corrective measures.
DR. SAMIA ALI
PROGRESS MEASUREMENT
Activity Deliver abut. Steel deliver deck steel Drive piles, abut. No.2 Strip footing no.1 Forms &steel, abut. No. 1 Deliver girders
PROGRESS MEASUREMENT
PROGRESS MEASUREMENT
Progress Analysis
Concerned primarily with determining the effect of the latest information on the project completion date and any milestone goals.
-A quick and simple check for critical activities status. -Check the possibility of a new critical path L.S. or L.F. listing
T.F. values
CORRECTIVE ACTIONS
signs of danger
1-Activities fall appreciably behind L.S. schedule . 2- Resource availability delays. 3- Realizing that time durations of future activities have been materially underestimated. 4- Change logic becomes necessary.
- Use time reduction techniques to bring project back on schedule . - Corrective measures efficiency are known by incorporating it into a network updating. - Periodic job progress meetings enhance time management efficiency . - weekly, biweekly, monthly. - Project managers, field supervisors, major subcontractors, material suppliers, owner representative.
DR. SAMIA ALI
NETWORK UPDATING
Making necessary network corrections and re-computing activity and float times.
Concerned with determining the effect of schedule deviations and plan changes on the portions of the project yet to be constructed. Information needed :
1. New activities to be added. 2. Existing activities to be deleted. 3. Changes in the resource availability and delivery dates. 4. Changes in the job logic . 5. New estimate of the time required to finish unfinished activities. 6. Changes in the scope of work.
Present date
Good for :
. affording a quick grasp of the overall time condition for owner , A/E, top management.
TIME
Limited effectiveness in: . Presenting time status of the construction project . No assistance in solving time slippage problems