Professional Documents
Culture Documents
Layout Strtgy 3 1
Layout Strtgy 3 1
Arrange six departments in a factory to minimize the material handling costs. Each department is 20 x 20 feet and the building is 60 feet long and 40 feet wide.
1. Construct a from-to matrix
50
100 30
0 50 20
0 10 0 50
20 0 100 0 0
Figure 4
Figure 5
Area 4
Area 5 60
Area 6
50
2 10
30
100
50
5
Figure 6
Xij Cij
i=1 j=1
$50 + $200 + $40 (1 and 2) (1 and 3) (1 and 6) $30 + $50 + $10 (2 and 3) (2 and 4) (2 and 5) $40 + $100 + $50 (3 and 4) (3 and 6) (4 and 5)
= $570
50
100
50 50
100
5
Figure 7
Xij Cij
i=1 j=1
$50 + $100 + $20 (1 and 2) (1 and 3) (1 and 6) $60 + $50 + $10 (2 and 3) (2 and 4) (2 and 5) $40 + $100 + $50 (3 and 4) (3 and 6) (4 and 5)
= $480
Figure 8
Area 4
Area 5 60
Area 6
Work Cells
Reorganizes people and machines into groups to focus on single products or product groups Group technology identifies products that have similar characteristics for particular cells Volume must justify cells Cells can be reconfigured as designs or volume changes
Cellular Layout
Current layout - workers in small closed areas. Cannot increase output without a third worker and third set of equipment.
Improved layout - cross-trained workers can assist each other. May be able to add a third worker as additional output is needed.
Figure 10 (a)
Current layout - straight lines make it hard to balance tasks because work may not be divided evenly
Improved layout - in U shape, workers have better access. Four cross-trained workers were reduced.
Figure 10 (b)
U-shaped line may reduce employee movement and space requirements while enhancing communication, reducing the number of workers, and facilitating inspection
10
0
Assemble Paint
Test
Operations
= 140 / 48 = 2.91
High Production
1. Quantity production Equipment is dedicated to the manufacture of one product Standard machines tooled for high production (e.g., stamping presses, molding machines) Typical layout process layout 2. Flow line production Multiple workstations arranged in sequence Product requires multiple processing or assembly steps Product layout is most common
Product-Oriented Layouts
Fabrication line Builds components on a series of machines Machine-paced Require mechanical or engineering changes to balance Assembly line Puts fabricated parts together at a series of workstations Paced by work tasks Balanced by moving tasks Both types of lines must be balanced so that the time to perform the work at each station is the same
Product-Oriented Layouts
Advantages
1. 2. 3. 4. 5. Low variable cost per unit Low material handling costs Reduced work-in-process inventories Easier training and supervision Rapid throughput
Disadvantages
1. High volume is required 2. Work stoppage at any point ties up the whole operation 3. Lack of flexibility in product or production rates
Product Layout
Product/Production Relationships
Total number of product units = Qf = Q j j 1 Product variety Hard product variety = differences between products Soft product variety = differences between models of products Product and part complexity Product complexity np = number of parts in product Part complexity no = number of operations per part
P
Computer Software
Graphical approach only works for small problems Computer programs are available to solve bigger problems Computer Packages are in two domain
Construction Programs
ALDEP CORELAP
Improvement Programs
CRAFT RUGR
PLANET
LAYOP
CRAFT Example
1 2 PATTERN 3 4 5 6
1
1 2 D D
2
D D
PATTERN 3 4 5 D D D D B B
6
B B
1
2 3 4 5 6
A
A D C F E
A
A D C F E
A
A D D F E
A
A D D F E
B
B D D F E
B
B D D D D
3
4 5 6
D
C A A
D
C A A
D
D A A
E
E A F
E
E A F
E
F F F
.00
70.
Figure 9
(a)
(b)
Computer Software
Three dimensional visualization software allows managers to view possible layouts and assess process, material handling, efficiency, and safety issues
It must be possible to group a portion of the parts made in the plant into part families
The part similarities allow them to be processed on the FMS workstations
Automated manufacturing cell with two machine tools and robot. Is it a flexible cell?
Types of FMS
Kinds of operations
Processing vs. assembly
Type of processing
If machining, rotational vs. non-rotational
2. Random-order FMS
Appropriate for large part families New part designs will be introduced Production schedule is subject to daily changes
FMS Components
1. Workstations 2. Material handling and storage system 3. Computer control system
4. Human labor
Workstations
Load and unload station(s)
Factory interface with FMS Manual or automated Includes communication interface with worker to specify parts to load, fixtures needed, etc.
Assembly machines
Temporary storage Convenient access for loading and unloading Compatibility with computer control
4. Open field
5. Robot-centered cell
Straight line flow, well-defined processing sequence similar for all work units Work flow is from left to right through the same workstations No secondary handling system
Linear transfer system with secondary parts handling system at each workstation to facilitate flow in two directions
One direction flow, but variations in processing sequence possible for different part types Secondary handling system at each workstation
Rectangular layout allows recirculation of pallets back to the first station in the sequence after unloading at the final station
Robot-Centered Cell
Suited to the handling of rotational parts and turning operations
3. Production control
Product mix, machine scheduling, and other planning functions
5. Shuttle control
Coordination of secondary handling system with primary handling system
6. Workpiece monitoring
Monitoring the status of each part in the system
9. Diagnostics
Diagnose malfunction causes and recommend repairs
FMS Applications
Machining most common application of FMS technology Assembly
Inspection
Sheet metal processing (punching, shearing, bending, and forming)
Forging
FMS Benefits
Increased machine utilization
Reasons:
24 hour operation likely to justify investment Automatic tool changing Automatic pallet changing at stations Queues of parts at stations to maximize utilization Dynamic scheduling of production to account for changes in demand
FMS Benefits
Greater responsiveness to change Reduced inventory requirements
Different parts produced continuously rather than in batches
Lower manufacturing lead times Reduced labor requirements Higher productivity Opportunity for unattended production
Machines run overnight ("lights out operation")
Processing requirements
Determine types of processing equipment required
Types of workstations Variations in process routings Work-in-process and storage capacity Tooling Pallet fixtures
Machine loading
Deciding what operations and associated tooling at each workstation
Part routing
Selecting routes to be followed by each part
Tool management
When to change tools
Just-In-Time Production
Production and delivery of exactly the required number of each component to the downstream operation in the manufacturing sequence just at the moment when the component is needed Minimizes:
Work-in-process
Manufacturing lead time
A system in which the order to make and deliver parts at each workstation in the production sequence comes from the downstream station that uses those parts JIT is based on a pull system of production control Alternative is a push system in which parts are produced at each station irrespective of the immediate need for those parts at the downstream station
Examples:
Retrieve tooling for next job from tool crib Assemble tools for next job Reprogram machine for next job
Figure 12
Disassembly Lines
Disassembly is being considered in new product designs
Assembly-Line Balancing
Objective is to minimize the imbalance between machines or personnel while meeting required output Starts with the precedence relationships
1. Determine cycle time 2. Calculate theoretical minimum number of workstations
10
11
B
4
G
3
12
11
H
Figure 13
workstations
A Production time B available per day Cycle B time = Units required per day A = 480 / 40 5 C, D = 12 minutes per unit C F 10 11 3 7 n E for taskF i A Time B G Minimum G, H i=1 4 number of =
Cycle D time
12 11
= 66 / 12 E H = 5.5 or 6 stations
Figure 13
H Table 4
Figure 13
480 available mins per day 40 units required Cycle time = 12 mins Minimum workstations = 5.5 or 6
3 7
F
Station 3
I
11
Station 6
H
Station 5 Figure 14
A 10 Cycle time = 12 mins B 11 A Minimum C 5 B workstations = 5.5 or 6 D 4 B E 12 A F 3 C, D Task times G 7 F Efficiency = (Actual number of H 11 Eworkstations) x (Largest cycle time) I 3 G, H = 66 minutes / (6 stations) x (12 minutes) Total time 66 = 91.7%