ACG2
ACG2
Contents
World driving force Costs Methods Design principles Risk concepts Project stage aims
0.00
North Parkes Target Lutopan North Parkes MKO Optimisation Philex Andina Palabora El Teniente Regimento El Salvador El Teniente South Freeport San Manuel MKO Viability
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
ECCONOMIC FORCES
NPVS AUD$ 300- 400 Million Possible NPVS 600- 800 Million IRR 11- 25% 15% IRR realistic number Project life 20 years Total opex US $ 9/ton for block caves
Cut-off grade
40 35 Revenue Open Stoping Sub Level Cave 25 20 15 10 5 0 0.00 Panel Cave Block Cave
30
0.10
0.30
0.40
0.50
Caving methods
underground mining methods
naturally supported
artificially supported
unsupported
shrink stoping
VCR stoping
longwall mining
sublevel caving
block caving
Caving Methods
Pre-break , SLC or core & Shell Free caving methods, Block caving Hybrid methods (Block caving/SLC)
Pre-break Characteristics
SLC most common method Production by drilling and blasting Quicker to bring into production than Block Caving Typical mine size 2 to 5 million/tonnes year
Front cave
Inclined drawpoint
Method selection
CAPEX, pre break less up front OPEX, block caving lower Corporate risk, block caving 70% up front Cavability, pre-break less risk Slusher/grizzly, softer rock. Lower stress LHD, coarse fragmentation, high stress Geology, geometry, geotech etc
Pit Gearing
Cave mining seen as a natural transition from open-cut Very few mines can ramp straight into large scale block caving Block caving costs similar to deep level open cut costs Trend- block caving removes last two pit cutbacks Solution- Hybrid or shared infrastructure
Cave Risk
Caving is one shot mining Get it wrong major problems Hard to fix High levels capex
RISK IMPACTS
30-40% Capital blow out AUD$ 250-300 Million 30-40% recovered grade 30-50% less production in yr 1 5 years longer to achieve full production
Implementation times
Slow - 15 years Fast track - 7 years (super team) Highly aggressive - 6 years Average 10 years Super team personnel exist in the world Small SLC type operations 3 years Brownfield's FC 5 years
Design Detail
Rock factory concept High levels of detail required in every aspect Specialist studies
Risk Amelioration
Caving risks can be mitigated by:
- The use of the super team - Understanding that high levels of design detail are req. - Sanity checks (implementation times) - Hybrid system - Correct modelling techniques - Risk analysis
Cave projects
Critical mistakes Spend too little time on concepts -Mining method selection -Mining geometry - Block attack - Corporate risk profile Unrealistic expectations
Scoping study
General features of project
- Caving footprint - Caving block height - Bottom of open cut - Mining method selection
Best parameters 30-35% accuracy Dont worry about cavability Experiential, empirical input parameters
Well over hurdles, IRR can drop by 10% to DEFS
STUDY CONCEPTS
No gurus Use methods with a track history What is the study basis: - Negative experience - Everything done right - Balance of the above