MRP
MRP
14
14 - 1
PowerPoint presentation to accompany Heizer and Render Operations Management, Eleventh Edition Principles of Operations Management, Ninth Edition PowerPoint slides by Jeff Heyl
Largest manufacturer of ambulances in the world International competitor 12 major ambulance designs
Material plan must meet both the requirements of the master schedule and the capabilities of the production facility Plan must be executed as designed Minimize inventory investment Maintain excellent record integrity
14 - 3
Dependent Demand
For any product for which a schedule can be established, dependent demand techniques should be used
14 - 4
Dependent Demand
Benefits of MRP
1. Better response to customer orders
14 - 5
Dependent Demand
The demand for one item is related to the demand for another item Given a quantity for the end item, the demand for all parts and components can be calculated In general, used whenever a schedule can be established for an item MRP is the common technique
2014 Pearson Education, Inc. 14 - 6
5. Lead times
2014 Pearson Education, Inc. 14 - 7
The MPS is quite often fixed or frozen in the near term part of the plan
The MPS is a rolling schedule
Figure 14.1
2014 Pearson Education, Inc. 14 - 10
Figure 14.1
2014 Pearson Education, Inc. 14 - 11
Figure 14.1
2014 Pearson Education, Inc. 14 - 12
Months Aggregate Plan (Shows the total quantity of amplifiers) Weeks Master Production Schedule (Shows the specific type and quantity of amplifier to be produced 240-watt amplifier 150-watt amplifier 75-watt amplifier
2014 Pearson Education, Inc.
January 1,500
February 1,200
100 500
100 450
(Process Focus)
Number of end items
Schedule orders
Schedule modules
Motorcycles, Examples Print shop Machine shop autos, TVs, fast: Fine dining restaurantfood restaurant
14 - 15
MPS Example
TABLE 14.1
Master Production Schedule for Chef Johns Buffalo Chicken Mac & Cheese
GROSS REQUIREMENTS FOR CHEF JOHNS BUFFALO MAC & CHEESE Day
Quantity
6
450
8
200
9
350
10
525
11
12
235
13
375
14
And so on
14 - 16
Bills of Material
List of components, ingredients, and materials needed to make product Provides product structure
Items above given level are called parents Items below given level are called components or children
14 - 17
Speaker kits, Inc., packages high-fidelity components for mail order. Components for the top -of the-line speaker kit,Awesome (A), include 2 standard 12-inch speaker kits (Bs) and 3 speaker kits with amp-boosters (Cs).Each B consists of 2 speakers(Ds) and 2 shipping boxes each with an installation kit(E).Each of the three 300 Watt speaker kits(Cs) has 2 speaker boosters(Fs) and 2 installation kits(Es). Each speaker booster (F) includes 2 speakers (Ds) and 1 ampbooster(G).
2014 Pearson Education, Inc. 14 - 18
Example
BOM Example
Level 0 1 B(2)
E(2)
E(2)
F(2)
D(2)
G(1)
D(2)
14 - 19
14 - 20
BOM Example
For an order of 50 Awesome speaker kits
Product structure for Awesome (A)
Level
Part B: 2 x number of As = 0 C: Part 3 x number of As = A Part D: 2 x number of Bs of Fs = B(2) 1+ 2 x number Part E: 2 x number of Bs + 2 x number of Cs = Part 2 x number of Cs = E(2) 2 F: Part G: 1 x number of Fs =
3 D(2)
(2)(50) = (3)(50) =
100 150
(2)(100) + (2)(300) = 800 C(3) (2)(100) + (2)(150) = 500 (2)(150) = 300 E(2) F(2) (1)(300) = 300
G(1) D(2)
14 - 21
Bills of Material
Modular Bills
Modules are not final products but components that can be assembled into multiple end items
14 - 22
Bills of Material
Planning Bills
Also called pseudo or super bills Created to assign an artificial parent to the BOM Used to group subassemblies to reduce the number of items planned and scheduled Used to create standard kits for production
14 - 23
Bills of Material
Phantom Bills
Describe subassemblies that exist only temporarily Are part of another assembly and never go into inventory
Low-Level Coding
Item is coded at the lowest level at which it occurs BOMs are processed one level at a time
14 - 24
14 - 25
14 - 26
TABLE 14.2 Lead Times for Awesome Speaker Kits (As) COMPONENT A B C D E LEAD TIME 1 week 2 weeks 1 week 1 week 2 week
F
G
3 weeks
2 weeks
14 - 27
Figure 14.3
D
2 weeks
2 weeks to produce
B E A
2 weeks 1 week
E
2 weeks
1 week
G
3 weeks
C F
1 week
D
| | | | | | | |
12
8
14 - 28
Time in weeks
MRP Structure
Figure 14.4
Data Files BOM Master production schedule Output Reports
MRP by period report
Lead times
(Item master file) Planned order report
Purchase advice
Exception reports
Order early or late or not needed Order quantity too small or too large
Purchasing data
14 - 29
14 - 30
14 - 32
ITEM A
ON HAND 10 20 10
ITEM E
ON HAND 10
5
0
14 - 34
14 - 35
14 - 36
A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5
2014 Pearson Education, Inc. 14 - 37
The on-hand inventory record for Item B is updated to reflect the use of the 15 items in inventory and shows no on-hand inventory in week 8
This is referred to as the Gross-to-Net calculation and is the third basic function of the MRP process
2014 Pearson Education, Inc. 14 - 38
10 10
1 10
2
40+10
3 40
4 50
5 20
7
15+30
=50
=45
Allocations
Total requirements
On hand
Scheduled receipts
Net = requirements
Available inventory
2014 Pearson Education, Inc. 14 - 40
Figure 14.6
14 - 41
Safety Stock
BOMs, inventory records, purchase and production quantities may not be perfect
Consideration of safety stock may be prudent
14 - 42
MRP Management
MRP dynamics
Facilitates replanning when changes occur System nervousness can result from too many changes Time fences put limits on replanning Pegging links each item to its parent allowing effective analysis of changes
14 - 43
MRP Management
MRP limitations
MRP does not do detailed schedulingit plans Works best in product-focused, repetitive environments Requires fixed lead time and infinite size time buckets
14 - 44
Lot-Sizing Techniques
Lot-for-lot techniques order just what is required for production based on net requirements
May not always be feasible
Lot-Sizing Techniques
Periodic order quantity (POQ) orders quantity needed for a predetermined time period
Interval = EOQ / average demand per period Order quantity set to cover the interval Order quantity calculated when order is released No extra inventory
14 - 46
Lot-Sizing Techniques
Dynamic lot sizing techniques
Balance lot size and setup costs Part period balancing (least total cost) Least unit cost Least period cost (Silver-Meal)
14 - 47
Lot-for-Lot Example
WEEK Gross requirements Scheduled receipts Projected on hand 35 35 0 0 0 0 0 0 0 0 0 1 35 2 30 3 40 4 0 5 10 6 40 7 30 8 0 9 30 10 55
30
30
40
40
10
10
40
40 30
30
30
30
30
55
55
30
40
10
40
30
55
Lot-for-Lot Example
No on-hand inventory is carried through the system TotalWEEK holding cost 1 = $0 2 3 4 5 6 7 8 9
Gross There are requirements Scheduled receipts 10 55
seven35 setups for this in this 30 40 0 item 10 40 30 plan 0 Total ordering cost = 7 x $100 = $700
35 35 0 0 0 0 0 0 0
30
Projected on hand
30
30
40
40
10
10
40
40 30
30
30
30
30
55
55
30
40
10
40
30
55
30
73
7
73
4
73
16
73
73
73
73
73
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units
2014 Pearson Education, Inc. 14 - 50
30
73
7
73
4
73
16
73
73
73
73
73
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units
2014 Pearson Education, Inc. 14 - 51
30
70
10
80
0
0
55
85
0
0
70
80
85
EOQ = 73 units; Average weekly gross requirements = 27; POQ interval = 73/27 3 weeks
2014 Pearson Education, Inc. 14 - 52
30
70
10
80
0
0
55
85
0
0
70
80
85
EOQ = 73 units; Average weekly gross requirements = 27; POQ interval = 73/27 3 weeks
2014 Pearson Education, Inc. 14 - 53
Lot-Sizing Summary
For these three examples
COSTS SETUP
Lot-for-lot EOQ POQ $700 $400 $300
HOLDING
$0 $375 $195
TOTAL
$700 $775 $495
14 - 54
Lot-Sizing Summary
In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change In practice, this results in system nervousness and instability Lot-for-lot should be used when low-cost setups can be achieved
2014 Pearson Education, Inc. 14 - 55
Lot-Sizing Summary
Lot sizes can be modified to allow for scrap, process constraints, and purchase lots Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM When setup costs are significant and demand is reasonably smooth, POQ or EOQ should give reasonable results
14 - 56
Extensions of MRP
MRP II Closed-Loop MRP Capacity Planning
14 - 57
LT
Computer Labor Hrs: .2 each Machine Hrs: .2 each Scrap: 1 ounce fiberglass each 1
8
100 20 20 6.25 lb
Payables: $0 each
PC Board (1 each) Labor Hrs: .15 each Machine Hrs: .1 each Scrap: .5 ounces copper each Payables: raw material at $5 each Processors (5 each) Labor Hrs: .2 each Machine Hrs: .2 each Scrap : .01 ounces of acid waste each 2014 Pearson Education, Inc. 4 500 100 100 0.3125 lb 2 100 15 10 3.125 $500 lb
$0
14 - 59
Capacity Management Evaluate Resource Availability (Rough Cut) Planning Determine Capacity Availability
OK? NO
OK? YES Prepare Materials Requirements Pan OK? YES Detailed Production Activity Control (Shop Scheduling/Dispatching) Implement Input/Output Control
14 - 60
Capacity Planning
Feedback from the MRP system Load reports show resource requirements for work centers Work can be moved between work centers to smooth the load or bring it within capacity
14 - 61
Smoothing Tactics
1. Overlapping
Sends part of the work to following operations before the entire lot is complete
2. Operations splitting
Breaking up the order into smaller lots and running part earlier (or later) in the schedule
14 - 62
Order Splitting
Develop a capacity plan for a work cell at Wiz Products
14 - 63
Order Splitting
DAY 1 2 UNITS ORDERED 10 14 CAPACITY REQUIRED (HOURS) 10 14 CAPACITY AVAILABLE (HOURS) 12 12 UTILIZATION: OVER/ (UNDER) (HOURS) (2) 2 Split order: move 2 units to day 1 Split order: move one unit to day 6 or request overtime PRODUCTION PLANNERS ACTION NEW PRODUCTION SCHEDULE 12 12
13
13
12
13
4 5
10 14
10 14
12 12
12 12
61
14 - 64
Order Splitting
Figure 14.8
Capacity exceeded on days 2, 3, and 5
Standard labor-Hours
14 12
2 orders moved to day 1 from day 2 (a day early) 1 order forced to overtime or to day 6 2 orders moved to day 4 (a day early)
10
8 6 4
2
0 1 2 3 Days (a) 4 5
3 Days (b)
14 - 65
MRP in Services
Some services or service items are directly linked to demand for other services These can be treated as dependent demand services or items
Restaurants Hospitals Hotels
14 - 66
MRP in Services
(a) PRODUCT STRUCTURE TREE
Buffalo Chicken Mac & Cheese
Figure 14.9
Baked Buffalo Chicken Mac & Cheese Unbaked Buffalo Chicken Mac & Cheese
Buffalo Sauce
Chopped Scallions
Milk
MRP in Services
(b) BILL OF MATERIALS Production Specifications Ingredients Elbow Macaroni (large, uncooked) Cheese-Pepper Jack (grated) Mac and Cheese Base (from refrigerator) Milk Smoked Pulled Chicken Buffalo Sauce Buffalo Chicken Mac & Cheese (6 portions) Quantity 20.00 10.00 32.00 4.00 2.00 8.00 Measure oz. oz. oz. oz. lb. oz.
Unit Cost
$ 0.09 0.17 0.80 0.03 2.90 0.09
Total Cost
$ 1.80 1.70 25.60 0.12 5.80 0.72
Labor Hrs.
4.00 2.00
oz. oz.
0.19 0.18
0.76 0.36
0.2 hrs
14 - 68
Expected demand or sales forecasts become gross requirements All other levels are computed DRP pulls inventory through the system Small and frequent replenishments
14 - 69
Sustainability
14 - 71
Figure 14.10
14 - 72
Figure 14.10
14 - 73
Figure 14.10
Inventory Management
Bills of Material
MRP
Work Orders
14 - 74
Figure 14.10
Supply-Chain Management Vendor Communication (schedules, EDI, advanced shipping notice, e-commerce, etc.)
14 - 75
Figure 14.10
Finance/ Accounting
Accounts Receivable
General Ledger
Accounts Payable
Facilitates a strategic emphasis on JIT systems and supply chain integration Can be expensive and time-consuming to install
2014 Pearson Education, Inc. 14 - 77
Figure 14.1114 - 78
14 - 79
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.
14 - 80